Testing of generators Sample Clauses
Testing of generators a) The following factory and site testing is to be carried out on the generators. These tests are carried out in accordance with this specification and IEC publication 60034–1, except where otherwise indicated.
b) After submission of the Contractor’s “Process Quality Plans” the Project Manager indicates which activities will have hold, check and witness points.
c) The Contractor notifies the Project Manager at least ten weeks in advance of intended tests where hold or witness points are applicable.