Substantial Completion Inspection. 6.26.2.1 Within 3 business days after receipt of the request for the Substantial Completion inspection of the Work, the Contracting Authority shall notify the DB of acceptance or rejection of the request, stating reasons for any rejection.
Appears in 2 contracts
Samples: www-s3-live.kent.edu, www-s3-live.kent.edu
Substantial Completion Inspection. 6.26.2.1 Within 3 three business days after receipt of the request for the Substantial Completion inspection of the Work, the Contracting Authority A/E shall notify the DB CM of acceptance or rejection of the request, stating reasons for any rejection.
Appears in 2 contracts
Samples: www-s3-live.kent.edu, www-s3-live.kent.edu
Substantial Completion Inspection. 6.26.2.1 6.28.2.1 Within 3 business days after receipt of the request for the Substantial Completion inspection of the Work, the Contracting Authority A/E shall notify the DB Contractor of acceptance or rejection of the request, stating reasons for any rejection.
Appears in 1 contract
Samples: ofcc.ohio.gov
Substantial Completion Inspection. 6.26.2.1 6.27.2.1 Within 3 business days after receipt of the request for the Substantial Completion inspection of the Work, the Contracting Authority A/E shall notify the DB Contractor of acceptance or rejection of the request, stating reasons for any rejection.
Appears in 1 contract
Samples: dam.assets.ohio.gov
Substantial Completion Inspection. 6.26.2.1 6.27.2.1 Within 3 business days after receipt of the request for the Substantial Completion inspection of the Work, the Contracting Authority A/E shall notify the DB CM of acceptance or rejection of the request, stating reasons for any rejection.
Appears in 1 contract
Samples: ofcc.ohio.gov