Schedule Modifications. If, as a result of the monthly Schedule Update, it appears the Construction Schedule no longer represents the actual /logical progression of the work or the Construction Manager’s plan for prosecution and progress of the work, the Principal Representative shall require the Construction Manager to submit a revision to the Construction Schedule. Such revisions to the Schedule shall not alter any of the Project Milestone dates.
Appears in 5 contracts
Samples: www.cuanschutz.edu, www.colorado.gov, www.colorado.gov
Schedule Modifications. If, as a result of the monthly Schedule Update, it appears schedule update the Construction Project Schedule no longer represents the actual /logical / logical progression of the work Work or the Construction Manager’s plan for prosecution and progress of the workWork, the Principal Representative shall require the Construction Manager to submit a revision to the Construction Project Schedule. Such revisions to the Schedule shall not alter any of the Project Milestone dates.
Appears in 2 contracts
Samples: pdc.uccs.edu, www.bidnet.com