Common use of Schedule Modifications Clause in Contracts

Schedule Modifications. If, as a result of the monthly Schedule Update, it appears the Construction Schedule no longer represents the actual /logical progression of the work or the Construction Manager’s plan for prosecution and progress of the work, the Principal Representative shall require the Construction Manager to submit a revision to the Construction Schedule. Such revisions to the Schedule shall not alter any of the Project Milestone dates.

Appears in 5 contracts

Samples: www.cuanschutz.edu, www.colorado.gov, www.colorado.gov

AutoNDA by SimpleDocs

Schedule Modifications. If, as a result of the monthly Schedule Update, it appears schedule update the Construction Project Schedule no longer represents the actual /logical / logical progression of the work Work or the Construction Manager’s plan for prosecution and progress of the workWork, the Principal Representative shall require the Construction Manager to submit a revision to the Construction Project Schedule. Such revisions to the Schedule shall not alter any of the Project Milestone dates.

Appears in 2 contracts

Samples: pdc.uccs.edu, www.bidnet.com

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.