Schedule Delays Sample Clauses

Schedule Delays. OIC and Orbital recognize that under this Agreement Orbital is engaged in a technology development program involving the design, development, construction, and integration of sophisticated and complex technical systems, management of a number of different suppliers, and inherent schedule uncertainties of space launch operations, and that there may be schedule delays. Orbital shall provide OIC with regular reports of its performance with respect to the applicable schedules and shall promptly notify OIC when it reasonably expects that there are delays that are likely to cause a material deviation from such schedules. In the event of such delays likely to cause a material deviation, Orbital shall meet with OIC to discuss the cause of such delays, the consequences of such delays and possible courses of action to mitigate the effect of such delays. Each party shall bear its own costs with respect to any delays, except as provided in Section 14.3.
AutoNDA by SimpleDocs
Schedule Delays. Landlord will use commercially reasonable efforts to (a) cause each Building to be delivered to Tenant in TI Ready Condition on or before November 16, 2016 (subject to Tenant Delays), (b) meet the “Key Milestone Dates” set forth on Exhibit F, as such dates may be extended by Tenant Delays and (c) cause the Substantial Completion Date to occur on or before the Phase 1 Rent Commencement Date (as to Building A and Building D and the parking structure (“PS2”) described on Exhibit A as “Parking Structure 2”) and on or before the Phase 2 Commencement Date (as to Building B); provided, however, except as otherwise expressly provided under Section 4.1 above or under this Section 4.6 below, Tenant agrees that in the event any or all of the deadlines set forth in (a), (b) or (c) above are not reached for any reason, then this Lease shall not be void or voidable and Landlord shall not be liable to Tenant for any loss or damage resulting therefrom. Notwithstanding anything above or in the Lease to the contrary, in the event that Building A, Building D and Building B are not in TI Ready Condition (as defined in the Work Letter) on or before the date which is one hundred twenty (120) days after November 16, 2016 (as such November 16, 2016 date may be extended by Tenant Delays) (“Outside Date”), then the sole remedy of Tenant shall be a credit equal to one (1) day of free Base Rent (to be applied commencing on the Phase 1 Rent Commencement Date) for each day beyond the Outside Date that Building A, Building D and Building B are not in TI Ready Condition; provided that if such delay exceeds sixty (60) days, then for each day of delay beyond sixty (60) days, Tenant will receive two (2) days of free Base Rent (to be applied commencing on the day that is sixty-one (61) days following the Phase 1 Rent Commencement Date) for each day of delay beyond sixty (60) days. In the event that Building A, Building D and Building B are not in TI Ready Condition on or before the date (“Outside Termination Date”) which is two hundred forty (240) days after November 16, 2016 (as such November 16, 2016 date may be extended by Tenant Delays), then the sole remedy of Tenant shall be the right to deliver a notice to Landlord (the “Outside Date Termination Notice”) electing to terminate this Lease effective upon receipt of the Outside Date Termination Notice by Landlord. The Outside Date Termination Notice must be delivered by Tenant to Landlord, if at all, not earlier than the Outside Terminati...
Schedule Delays. No extension of time of performance of this --------------- Agreement shall be recognized by the Owner without the written consent of the Owner.

Related to Schedule Delays

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

  • Force Majeure Delays In any case where either party hereto is required to do any act (other than the payment of money), delays caused by or resulting from Acts of God or Nature, war, civil commotion, fire, flood or other casualty, labor difficulties, shortages of labor or materials or equipment, government regulations, delay by government or regulatory agencies with respect to approval or permit process, unusually severe weather, or other causes beyond such party’s reasonable control the time during which act shall be completed, shall be deemed to be extended by the period of such delay, whether such time be designated by a fixed date, a fixed time or “a reasonable time.”

  • Tenant Delays A "Tenant Delay” shall be defined as any delay in the design, permitting or performance of the Base Building Work to the extent that such delay is actually caused by any act or, where there is a duty to act under this Lease, any failure to act by Tenant or Tenant's contractors, architects, engineers, or anyone else engaged by or on behalf of Tenant in connection with the construction of the Tenant Improvement Work as set forth in this Article III (including, without limitation, any delays resulting from the Approved Tenant Finishes under Section 3.l(C) above) and disclosed to Tenant as hereinafter provided. Notwithstanding the foregoing, in no event shall any delays in the completion of the Base Building Work caused by Tenant’s use of non-union labor constitute a Tenant Delay hereunder. Notwithstanding the foregoing, no event shall be deemed a Tenant Delay unless and until Landlord has given Tenant written notice (the "Tenant Delay Notice") advising Tenant: (x) that a Tenant Delay is occurring and setting forth Landlord's good faith estimate as to the likely length of such Tenant Delay; (y) of the basis on which Landlord has determined that a Tenant Delay is occurring; and (z) the actions which Landlord believes that Tenant must take to eliminate such Tenant Delay. No event shall be deemed to be a Tenant Delay unless and until Tenant has failed to rectify the situation causing the Tenant Delay within forty-eight (48) hours after Tenant's receipt of the Tenant Delay Notice (which for the purposes of determining receipt may be delivered by hand to Tenant's Construction Representative, with copies to follow to Tenant at the notice address set forth in Section 1.2 of this Lease within five (5) days thereafter); provided, however, that if Tenant shall fail to eliminate the delay within the aforesaid 48-hour period, then the 48-hour cure period shall be included in the period of time charged to Tenant pursuant to such Tenant Delay Notice (it being understood and agreed that if Tenant shall in fact eliminate the Tenant Delay within the 48-hour cure period, no Tenant Delay shall be deemed to have occurred for the purposes of this Article III). In addition, any delay to the extent caused by (i) Landlord Delay or (ii) subject to the limitations of subsection (D) below, Tenant's Force Majeure (as defined in said subsection (D)) shall not constitute Tenant Delay. Tenant covenants that no Tenant Delay shall delay commencement of the Term or the obligation to pay Annual Fixed Rent or Additional Rent. The Delivery Dates and/or the date of substantial completion of the Base Building Work, as applicable, shall be deemed to have occurred as of the date when such Delivery Dates and/or date of substantial completion of the Base Building Work, as applicable, would have occurred but for any Tenant Delays, as determined by Landlord in the exercise of its good faith business judgment (it being understood and agreed that the foregoing shall not be construed so as to relieve Landlord of its obligation to actually complete the Base Building Work, notwithstanding the fact that substantial completion may have been deemed to have occurred prior to actual completion as the result of Tenant Delays).

  • Time Schedule 4.1. A project schedule is included in Appendix A.

  • Outage Schedules The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability of the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as a result of rescheduling maintenance, including any additional overtime, breaking of maintenance contracts or other costs above and beyond the cost the Developer would have incurred absent the request to reschedule maintenance, shall be in accordance with the NYISO OATT. Developer will not be eligible to receive compensation, if during the twelve (12) months prior to the date of the scheduled maintenance, the Developer had modified its schedule of maintenance activities other than at the direction of the NYISO or request of the Connecting Transmission Owner.

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:

  • Unavoidable Delays Delays due to acts of God, acts of public agencies, labor disputes, strikes, fires, freight embargoes, inability (despite the exercise of due diligence) to obtain supplies, materials, fuels or permits, or other causes or contingencies (excluding financial inability) beyond the reasonable control of Landlord or Tenant, as applicable. Landlord shall use commercially reasonable efforts to provide Tenant with prompt notice of any Unavoidable Delays.

  • SCHEDULE OF WORK FIRST PARTY’S proposed schedule for the various services required will be set forth in Exhibit A-1. A4. CHANGES IN WORK -- EXTRA WORK In addition to services described in Section A1, the parties may from time to time agree in writing that FIRST PARTY, for additional compensation, shall perform additional services including but not limited to: • Change in the services because of changes in scope of the work. • Additional tasks not specified herein as required by the CITY. The CITY and FIRST PARTY shall agree in writing to any changes in compensation and/or changes in FIRST PARTY’s services before the commencement of any work. If FIRST PARTY deems work he/she has been directed to perform is beyond the scope of this agreement and constitutes extra work, FIRST PARTY shall immediately inform the CITY in writing of the fact. The CITY shall make a determination as to whether such work is in fact beyond the scope of this agreement and constitutes extra work. In the event that the CITY determines that such work does constitute extra work, it shall provide compensation to the FIRST PARTY in accordance with an agreed cost that is fair and equitable. This cost will be mutually agreed upon by the CITY and FIRST PARTY. A supplemental agreement providing for such compensation for extra work shall be negotiated between the CITY and the FIRST PARTY. Such supplemental agreement shall be executed by the FIRST PARTY and may be approved by the City Manager upon recommendation of the Department Head.

  • Milestone Schedule Please state the status and progress of each Milestone and identify any completed Milestone(s) for the previous calendar quarter.

  • Permitted Delays The Company shall be entitled to postpone the filing of any Registration Statement under Section 2.3 if (i) at any time prior to the filing of such Registration Statement the Board of Directors of the Company determines, in its good faith business judgment, that such registration and offering would materially and adversely affect any financing, acquisition, corporate reorganization or other material transaction involving the Company, and (ii) the Company delivers the Holders requesting such registration written notice thereof within 10 business days of the date of receipt of such request; provided, that all such periods of postponement may not exceed 45 days during any 365-day period.