Common use of Right to Observe Testing Clause in Contracts

Right to Observe Testing. Each Party shall notify the other Parties at least fourteen (14) Calendar Days in advance of its performance of tests of its Interconnection Facilities or Generating Facility. The other Parties have the right, at their own expense, to observe such testing.

Appears in 77 contracts

Samples: Large Generator Interconnection Agreement, Agreement, Interconnection Agreement

AutoNDA by SimpleDocs

Right to Observe Testing. Each Party shall notify the other Parties at least fourteen (14) Calendar Days days in advance of its performance of tests of its Interconnection Facilities or Generating Facility. The other Parties have the right, at their own expense, to observe such testing.

Appears in 65 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Right to Observe Testing. Each Party shall notify the other Parties at least fourteen (14) Calendar Days in advance of its performance of tests of its Interconnection Facilities or Generating Facility. The other Parties have the right, at their own expense, to observe such testing.testing.β€Œ

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Right to Observe Testing. Each Party shall notify the other Parties at least fourteen (14) Calendar Days DaysParty in advance of its performance of tests of its Interconnection Facilities or Generating Facility. .. The other Parties have haveParty has the right, at their theirits own expense, to observe such testing.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Right to Observe Testing. Each Party shall notify the other Parties at least fourteen (14) Calendar Days in advance of its performance of tests of its Interconnection Facilities Facilities, Network Upgrades, or Generating Facility. The other Parties have the right, at their own expense, to observe such testing.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Right to Observe Testing. Each Party shall notify the other Parties at least fourteen (14) Calendar Days daysParty in advance of its performance of tests of its Interconnection Facilities or Generating Facility. .. The other Parties have haveParty has the right, at their theirits own expense, to observe such testing.