Common use of Review and Acceptance Clause in Contracts

Review and Acceptance. The Engineer will review all Progress Schedule submittals within 7 calendar days of receipt of the Contractor’s complete submittal. Review and acceptance by the Engineer will be based on completeness and conformance with the requirements of this section, the Contract and the Specifications. If the Contractor’s Progress Schedule is deemed to be unacceptable, the Engineer will issue a written notification for resubmission describing the deficiencies in completeness or conformance prompting the Engineer’s decision. Upon acceptance, the Engineer will issue a written notice of acceptance that may include comments or concerns on the schedule. The Contractor shall respond within 7 calendar days of receipt of the Engineer’s comments, concerns or written notification for resubmission. Progress Schedule or Revised Progress Schedule shall become the Schedule of Record (SOR). The SOR is defined as the currently accepted Progress Schedule by which all schedule references will be made and progress evaluated. Review and acceptance by the Engineer will not constitute a waiver of any contract requirements and will in no way assign responsibilities of the work plan, scheduling assumptions, and validity of the schedule to the Department. Failure of the Contractor to include in the Progress Schedule any element of work required for timely completion of the project shall not excuse the Contractor from completing the entire Scope of Work within the Contract specified completion milestone(s).

Appears in 25 contracts

Samples: www.loudoun.gov, www.loudoun.gov, www.loudoun.gov

AutoNDA by SimpleDocs

Review and Acceptance. The Engineer will review all Progress Schedule submittals within 7 calendar days of receipt of the Contractor’s complete submittal. Review and acceptance by the Engineer will be based on completeness and conformance with the requirements of this section, the Contract and the Specifications. If the Contractor’s Progress Schedule is deemed to be unacceptable, the Engineer will issue a written notification for resubmission describing the deficiencies in completeness or conformance prompting the Engineer’s decision. Upon acceptance, the Engineer will issue a written notice of acceptance that may include comments or concerns on the schedule. The Contractor shall respond within 7 calendar cal endar days of receipt of the Engineer’s comments, concerns or written notification for resubmission. Progress Schedule or Revised Progress Schedule shall become the Schedule of Record (SOR). The SOR is defined as the currently accepted Progress Schedule by which all schedule references will be made and progress evaluated. Review and acceptance by the Engineer will not constitute a waiver of any contract requirements and will in no way assign responsibilities of the work plan, scheduling schedulin g assumptions, and validity of the schedule to the Department. Failure of the Contractor to include in the Progress Schedule any element of work required for timely completion of the project shall not excuse the Contractor from completing the entire ent ire Scope of Work within the Contract specified completion milestone(s).

Appears in 2 contracts

Samples: www.loudoun.gov, www.loudoun.gov

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.