Common use of Responsibility for Completion Clause in Contracts

Responsibility for Completion. 5.1.9.1 CONTRACTOR shall furnish sufficient manpower, MATERIALS, facilities and equipment and shall work sufficient hours, including night shifts, overtime operations, Saturdays, Sundays and holidays as may be necessary to insure the prosecution and completion of the WORK in accordance with the accepted CONTRACT SCHEDULE. If work on the critical path is seven days or more behind the currently updated CONTRACT SCHEDULE and it becomes apparent that the WORK will not be completed within the CONTRACT TIME, CONTRACTOR will implement whatever steps it deems necessary to make up all lost time. If CONTRACTOR’S solution is not successful, it will make further attempts using the following sequence of events: