Common use of Rescheduling of Tests Clause in Contracts

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 46 contracts

Samples: Concession Agreement, Concession Agreement, Draft Concession Agreement

AutoNDA by SimpleDocs

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 39 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. ENTRY INTO COMMERCIAL SERVICE

Appears in 23 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 16 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 16 contracts

Samples: Epc Agreement, And Construction), Model Agreement

Rescheduling of Tests. If the Independent Authority Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 10 contracts

Samples: And Construction Agreement, Engineering, Procurement and Construction, And Construction Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 8 contracts

Samples: Draft Contract Agreement, Construction Agreement, nhidcl.com

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering Healthcare Services or issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire at its own cost and expense, shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. The provisions of this Article 15 shall apply mutatis mutandis to such re-scheduled Tests.

Appears in 7 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority MOR and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 7 contracts

Samples: Model Agreement, Model Agreement, Model Agreement

Rescheduling of Tests. If the Independent Engineer or the Independent Panel, as the case may be, certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering the Services or issue the Completion Certificate or Provisional Certificatefor Project, as the case may be, because of events or circumstances on account of which the Completion Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Completion Tests and hold the same as soon as reasonably practicable.

Appears in 6 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer or the Monitoring Agency, as the case may be, certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering Diagnostic Services and OPD Services or issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Completion Tests could not be held or had to be suspended, the Concessionaire at its own cost and expense, shall be entitled to re-schedule the Completion Tests and hold the same as soon as reasonably practicable.

Appears in 6 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Authority‟s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 5 contracts

Samples: Procurement and Construction Agreement, (Engineering Procurement and Construction, Construction) Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 5 contracts

Samples: Concession Agreement, Model Concession Agreement, Model Concession Agreement

Rescheduling of Tests. If the Independent Engineer Monitor[s] certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 4 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Concessioning Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Samples: Concession Agreement, Draft Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer Expert certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Samples: Draft Concession Agreement, Draft Concession Agreement, Draft Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority Government and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Employer's Engineer certifies to the Authority Employer and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Samples: Procurement and Construction, Epc Agreement, Epc Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority MPRDC and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Employer’s Engineer certifies to the Authority Employer and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 3 contracts

Samples: And Construction Agreement, Epc Contract Agreement, Contract Agreement for Design and Construction

Rescheduling of Tests. If the Independent Engineer certifies to the Authority MPRDC and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests Test and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Rescheduling of Tests. xxx.xxxxxx.xxx Downloaded If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. ENTRY INTO COMMERCIAL SERVICE

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire theContractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Drafit Contract Agreement

Appears in 2 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the TNRDC and Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Engineer or the Independent Panel certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Samples: Stamp Paper, Substitution Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority MOR and the Concessionaire Developer that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Developer shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Samples: Model Agreement, Model Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority Participating ULBs and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Samples: Model Concession Agreement, Model Concession Agreement

Rescheduling of Tests. If the Independent Engineer Expert certifies to the Contracting Authority and the Concessionaire Service Provider that it is unable to issue the Completion Certificate or Provisional Certificate, Certificate (as the case may be, ) because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Service Provider shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. CLAUSE 15

Appears in 2 contracts

Samples: Project Agreement, Project Agreement

Rescheduling of Tests. If the Independent Engineer or the Independent Panel, as the case may be, certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering Healthcare Services or issue the Completion Certificate or Provisional Certificate, as the case may befor Phase I, because of events or circumstances on account of which the Completion Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Completion Tests and hold the same as soon as reasonably practicable.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer Expert certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. Provided, however, that the Concessionaire shall be excused for the delay in Tests arising hereunder if such delay is not solely attributable to the Concessionaire.

Appears in 1 contract

Samples: fci.gov.in

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule reschedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Change of Scope

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the Independent Authority‟s Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Concessioning Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Draft Concession Agreement

AutoNDA by SimpleDocs

Rescheduling of Tests. If the Independent Engineer certifies to the Authority Participating ULBs and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Model Concession Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.. Drafit Contract Agreement

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority SH&DB and the Concessionaire DEVELOPER that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire DEVELOPER shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the Independent Engineer Expert certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable. Provided, however, that the Concessionaire shall be excused for the delay in Tests arising hereunder if such delay is not solely attributable to the Concessionaire.

Appears in 1 contract

Samples: niti.gov.in

Rescheduling of Tests. If the Independent Engineer designated Officer certifies to the Concessioning Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. oject If the Independent Engineer certifies to the Authority MOPIT and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority / SSNNL / FED and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer Supervision Committee certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional CertificateCertificate for the Project/ Phase, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Draft Contract Agreement

Rescheduling of Tests. If the Independent Engineer certifies notify to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of about events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Authority’s Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Model Concession Agreement

Rescheduling of Tests. xxx.xxxxxx.xxx If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Employer‟s Engineer certifies to the Authority Employer and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Procurement and Construction Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Draft Concession Agreement

Rescheduling of Tests. If the Independent Employer’s Engineer certifies to the Authority Employer and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Contract Agreement

Rescheduling of Tests. If the Independent Engineer Engineer-in-charge certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Contract Agreement

Rescheduling of Tests. 14.6.1 If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer Engineer-in-Charge certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer certifies to the Authority TNRDC and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Concession Agreement

Rescheduling of Tests. If the Independent Engineer Supervision Committee certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate Certificate-1 or Completion Certificate-2 or Provisional CertificateCertificate for the Project, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-re- schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Iii Concession Agreement

Rescheduling of Tests. If the Independent Authority's Engineer certifies to the Authority and the Concessionaire Contractor that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.

Appears in 1 contract

Samples: Draft Contract Agreement