Common use of Redispatch Procedures Clause in Contracts

Redispatch Procedures. If (i) a transmission constraint subject to this Section 11.2.13 occurs and continues or reasonably can be expected to continue after the exhaustion of all economic alternatives that are reasonably available to the transmission system on which the constraint occurs and (ii) the affected Party has determined that it must either use Transmission Loading Relief or other emergency procedures, then (iii) the affected Party may request the other to redispatch one or more of the previously identified generation units to alleviate the transmission constraints. Upon such request, the Party so requested shall redispatch such generation if it is then subject to its dispatch control and such redispatch is consistent with good utility practice.

Appears in 3 contracts

Sources: Joint Operating Agreement, Joint Operating Agreement, Joint Operating Agreement