Recovery Schedule. In the event progress falls behind schedule dates, the Construction Manager shall prepare a recovery schedule indicating its revised plan to assure the timely completion of the Work. The recovery plan shall be subject to the Principal Representative’s approval.
Appears in 5 contracts
Samples: www.colorado.gov, www.cuanschutz.edu, www.colorado.gov
Recovery Schedule. In the event progress falls behind schedule dates, the Construction Manager Design/Build Entity shall prepare a recovery schedule indicating its revised plan to assure the timely completion of the Work. The recovery plan shall be subject to the Principal Representative’s approval.
Appears in 3 contracts
Samples: www.coloradomesa.edu, www.coloradomesa.edu, www.bidnet.com
Recovery Schedule. In the event If progress falls behind schedule dates, the Construction Manager Contractor shall prepare a recovery schedule indicating its revised plan to assure the timely completion of the Work. The recovery plan shall be subject to the Principal Representative’s approval.
Appears in 2 contracts
Samples: Construction Manager, Construction Manager
Recovery Schedule. In the event progress falls behind schedule dates, the Construction Manager Design Build Entity shall prepare a recovery schedule indicating its revised plan to assure the timely completion of the Work. The recovery plan shall be subject to the Principal Representative’s approval.
Appears in 2 contracts
Samples: www.uccs.edu, uccs.edu
Recovery Schedule. In the event progress falls behind schedule dates, the Construction Manager shall prepare a recovery schedule indicating its revised plan to assure the timely completion of the Work. The recovery plan schedule shall be subject to the Principal Representative’s approval.
Appears in 1 contract
Samples: pdc.uccs.edu
Recovery Schedule. In the event progress falls behind schedule dates, the Construction Manager shall prepare a recovery schedule indicating its revised plan to assure the timely completion of the Work. The recovery plan schedule shall be subject to the Principal Representative’s approval.. AMENDMENTS AND CHANGE ORDERS
Appears in 1 contract
Samples: www.bidnet.com
Recovery Schedule. In the event If progress falls behind schedule dates, the Construction Manager Contractor shall prepare a recovery schedule indicating its revised plan to assure the timely completion of the Work. The recovery plan shall be subject to the Principal RepresentativeTown’s approval.
Appears in 1 contract
Samples: Town of Castle