Recovery Plan. If slippage has occurred from Buyer’s baseline schedule, the Buyer must provide an analysis, in narrative format, of the slippage that identifies the cause and propose a corrective plan of action that will be taken to complete the remaining work within the Contract performance period.
Appears in 6 contracts
Samples: tendertale.com, voa.marad.dot.gov, voa.marad.dot.gov
Recovery Plan. If slippage has occurred from BuyerXxxxx’s baseline schedule, the Buyer must provide an analysis, in narrative format, of the slippage that identifies the cause and propose a corrective plan of action that will be taken to complete the remaining work within the Contract performance period.
Appears in 1 contract
Samples: tendertale.com