Common use of Provisional Certificate Clause in Contracts

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.

Appears in 7 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.

Appears in 4 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project Highway can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is due to is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.

Appears in 2 contracts

Samples: Model Concession Agreement, Model Concession Agreement

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer Engineer-in-charge may, at the request of the ConcessionaireContractor, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer Engineer-in-charge and the Concessionaire Contractor (the “Punch List”); provided that the Independent Engineer Engineer-in-charge shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.

Appears in 1 contract

Samples: Contract Agreement

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate on completion of completion substantially 100% project length in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.

Appears in 1 contract

Samples: Draft Concession Agreement

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the 14.1.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J Schedule 10 (the “Provisional Certificate”) if the Tests are successful and key activities indicated in the Implementation Schedule have been successfully completed post which the Project Facilities can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List list shall also include the cost of completion for of each of the outstanding items.

Appears in 1 contract

Samples: Draft Concession Agreement

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the 14.1.1 The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J Schedule 10 (the “Provisional Certificate”) if the Tests are successful and key activities indicated in the Implementation Schedule have been successfully completedpost which the Project Facilities can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided List”);provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List list shall also include the cost of completion for of each of the outstanding items.

Appears in 1 contract

Samples: Escrow Agreement

AutoNDA by SimpleDocs

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate”) if the Tests are successful and the Project Bus Port can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire (the “Punch List”); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is due to is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.

Appears in 1 contract

Samples: Concession Agreement

Provisional Certificate. 14.3.1 13.3.1. Subject to the provisions of Clause 14.3.213.3.2, the Independent Authority’s Chief Engineer may, at the request of the ConcessionaireConcessionaire and on the recommendations of the Independent Engineer, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the "Provisional Certificate”) "), if the Tests including the Trial Operations are successful and the Project can be safely and reliably placed in commercial operation operations though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Authority’s Chief Engineer and the Concessionaire (the "Punch List"); provided that the Independent Chief Engineer shall not withhold the Provisional Certificate for reason of any work remaining remain incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.

Appears in 1 contract

Samples: Escrow Agreement

Provisional Certificate. 14.3.1 Subject to the provisions of Clause 14.3.2, the The Independent Engineer may, at the request of the Concessionaire, issue a provisional certificate of completion substantially in the form set forth in Schedule-J (the “Provisional Certificate") if the Tests as per Article – 14 are successful and the Project can be safely and reliably placed in commercial operation though certain works or things forming part thereof are outstanding and not yet complete. In such an event, the Provisional Certificate shall have appended thereto a list of outstanding items (including items mentioned in Clause 3.2 & Clause 3.3 of Schedule 3 of this agreement) signed jointly by the Independent Engineer and the Concessionaire (the "Punch List"); provided that the Independent Engineer shall not withhold the Provisional Certificate for reason of any work remaining incomplete if the delay in completion thereof is attributable to the Authority; provided further that the Punch List shall also include the cost of completion for each of the outstanding items.

Appears in 1 contract

Samples: Concession Agreement