Common use of Provision for Generation Compensation Clause in Contracts

Provision for Generation Compensation. If the plant is ready but the necessary power evacuation/ transmission infrastructure beyond Delivery Point is not ready, leading to offtake constraint a) The normative CUF of 19% (nineteen per cent) or committed CUF, whichever is lower, for the period of grid unavailability beyond Delivery Point, shall be taken for the purpose of calculation of generation loss. Corresponding to this generation loss, the excess generation by the Sucessful Bidder in the succeeding 3 (three) Contract Years, shall be procured by GUVNL at the PPA tariff so as to offset this loss. b) If the transmission delay is directly attributable to the organization building the transmission network and some penalty is imposed on him, then a part of that penalty may be utilized by GUVNL for compensating the generation loss. However, it is clarified that if the plant is ready before SCOD, but the offtake is constrained because of inadequate/ incomplete power evacuation infrastructure beyond Delivery Point, no compensation shall be permissible.

Appears in 5 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Provision for Generation Compensation. If the plant Project is ready but the necessary power evacuation/ evacuation/transmission infrastructure beyond Delivery Point is not ready, leading to offtake constraint a) a. The normative CUF of 19% (nineteen per cent) or committed CUF, whichever is lower, for the period of grid unavailability beyond Delivery Pointunavailability, shall be taken for the purpose of calculation of generation loss. Corresponding to this generation loss, the excess generation by the Sucessful Bidder SPD in the succeeding 3 (three) Contract Years, shall be procured by GUVNL the Buying Entity at the PPA PSA tariff so as to offset this loss. b) b. If the transmission delay is directly attributable to the organization building the transmission network and some penalty is imposed on him, then a part of that penalty may be utilized by GUVNL SECI for compensating the generation loss. However, it is clarified that if the plant project is ready before SCODfor commissioning prior to the Scheduled Commissioning Date, but the offtake is constrained because of inadequate/ inadequate/incomplete power evacuation infrastructure beyond Delivery Pointinfrastructure, no compensation shall be permissible.

Appears in 3 contracts

Samples: Power Sale Agreement, Power Sale Agreement, Power Sale Agreement

Provision for Generation Compensation. If the plant is ready but the necessary power evacuation/ transmission infrastructure beyond Delivery Point is not ready, leading to offtake constraint a) The normative CUF of 19% (nineteen per cent) or committed CUF, whichever is lower, for the period transmission infrastructure beyond Delivery Point is not ready, leading to offtake constraint of grid unavailability beyond Delivery Point, shall be taken for the purpose of calculation of generation loss. Corresponding to this generation loss, the excess generation by the Sucessful Bidder in the succeeding 3 (three) Contract Years, shall be procured by GUVNL at the PPA tariff so as to offset this loss. b) If the transmission delay is directly attributable to the organization building the transmission network and some penalty is imposed on him, then a part of that penalty may be utilized by GUVNL for compensating the generation loss. However, it is clarified that if the plant is ready before SCOD, but the offtake is constrained because of inadequate/ incomplete power evacuation infrastructure beyond Delivery Point, no compensation shall be permissible.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

Provision for Generation Compensation. If the plant is ready but the necessary power evacuation/ transmission infrastructure beyond Delivery Point is not ready, leading to offtake constraint a) The normative CUF of 19% (nineteen per cent) or committed CUF, whichever is lower, for the period of grid unavailability beyond Delivery Point, shall be taken for the purpose of calculation of generation loss. Corresponding to this generation loss, the excess generation by the Sucessful Bidder SPD in the succeeding 3 (three) Contract Years, shall be procured by GUVNL PSPCL at the PPA tariff so as to offset this loss. b) If the transmission delay is directly attributable to the organization building the transmission network and some penalty is imposed on himit, then a part of that penalty may be utilized by GUVNL PSPCL for compensating the generation loss. However, it is clarified that if the plant is ready before SCODScheduled Commissioning Date, but the offtake is constrained because of inadequate/ incomplete power evacuation infrastructure beyond Delivery Point, no compensation shall be permissible.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Provision for Generation Compensation. If the plant is ready but the necessary power evacuation/ transmission infrastructure beyond Delivery Point is not ready, leading to offtake constraint a) The normative CUF of 19% (nineteen per cent) or committed Declared CUF, whichever is lower, for the period of grid unavailability beyond Delivery Point, shall be taken for the purpose of calculation of generation loss. Corresponding to this generation loss, the excess generation by the Sucessful Bidder in the succeeding 3 (three) Contract Years, shall be procured by GUVNL TPL-D at the tariff as per clause 5.2 of this PPA tariff so as to offset this loss. b) If the transmission delay is directly attributable to the organization building the transmission network and some penalty is imposed on him, then a part of that penalty may be utilized by GUVNL TPL for compensating the generation loss. However, it is clarified that if the plant is ready before SCOD, but the offtake is constrained because of inadequate/ incomplete power evacuation infrastructure beyond Delivery Point, no compensation shall be permissible.

Appears in 1 contract

Samples: Draft Power Purchase Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.