PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components: 1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000 a.) Acquisition Expenses $ 0 Fee Simple $ 0 Easement $ 0 b.)Planning and Implementation: $ 20,000 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000 d.) Permits, Advertising, Legal: $ 0 e.) Contingencies: $ 0 ==================== f.) Total Estimated Costs: $ 225,000 1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest Park's Percentage Contribution as amounting to a minimum total value of 41% percent of the total Project Cost. The OPWC participation percentage shall be 59% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000419,000
a.) Acquisition Expenses $ 0 395,000 Fee Simple $ 0 395,000 Easement $ 0 b.)Planning and Implementation: $ 20,000 4,000 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site 4,000
c.) Site Improvements: $ 205,00020,000
d.) Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,000419,000
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City Friends of Forest Wooster Memorial Park's Percentage Contribution as amounting to a minimum total value of 4128% percent of the total Project Cost. The OPWC participation percentage shall be 5972% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000170,790
a.) Acquisition Expenses $ 0 133,000 Fee Simple $ 0 Easement $ 0 b.)Planning 133,000
b.) Planning and Implementation: $ 20,000 17,000 Appraisal $ 0 6,000 Title Work $ 0 3,000 Closing costs $ 0 3,000 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site 5,000
c.) Site Improvements: $ 205,00020,790
d.) Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,000170,790
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkThree Valley Conservation Trust's Percentage Contribution as amounting to a minimum total value of 4125% percent of the total Project Cost. The OPWC participation percentage shall be 59% percent75%. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000240,000
a.) Acquisition Expenses $ 0 Fee Simple $ 0 Easement $ 0 b.)Planning and Implementation: $ 20,000 0 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
d.) Permits226,100 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies2,500 e.)Contingencies: $ 0 11,400 ====================
f.) Total Estimated Costs: $ 225,000240,000
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkMuskingum Watershed Conservancy District's Percentage Contribution as amounting to a minimum total value of 4125% percent of the total Project Cost. The OPWC participation percentage shall be 5975% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,0002,441,000
a.) Acquisition Expenses $ 0 2,423,000 Fee Simple $ 0 2,423,000 Easement $ 0 b.)Planning 0
b.) Planning and Implementation: $ 20,000 16,000 Appraisal $ 0 10,000 Title Work $ 0 1,000 Closing costs $ 0 2,000 Environmental Assessments $ 0 3,000 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site 0
c.) Site Improvements: $ 205,0000
d.) Permits, Advertising, Legal: $ 02,000
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,0002,441,000
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkRails to Trails ▇▇▇▇▇ County's Percentage Contribution as amounting to a minimum total value of 4126% percent of the total Project Cost. The OPWC participation percentage shall be 59% percent74%. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000233,431
a.) Acquisition Expenses $ 0 228,431 Fee Simple $ 0 228,431 Easement $ 0 b.)Planning and Implementation: $ 20,000 5,000 Appraisal $ 0 5,000 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
d.) Permits0 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,000233,431
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkBath Township's Percentage Contribution as amounting to a minimum total value of 4150% percent of the total Project Cost. The OPWC participation percentage shall be 5950% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,00068,800
a.) Acquisition Expenses $ 0 62,500 Fee Simple $ 0 Easement $ 0 62,500 b.)Planning and Implementation: $ 20,000 6,300 Appraisal $ 0 4,000 Title Work $ 0 1,000 Closing costs $ 0 1,300 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
d.) Permits0 d.)Permits, Advertising, Legal: $ 0
e.f.) ContingenciesTotal Estimated Costs: $ 0 ====================
f.) Total Estimated Costs: = $ 225,00068,800
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkWestern Reserve Land Conservancy's Percentage Contribution as amounting to a minimum total value of 4132% percent of the total Project Cost. The OPWC participation percentage shall be 5968% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000275,000
a.) Acquisition Expenses $ 0 Fee Simple $ 0 Easement $ 0 b.)Planning and Implementation: $ 20,000 25,000 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 25,000 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
d.) Permits228,730 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies0 e.)Contingencies: $ 0 21,270 ====================
f.) Total Estimated Costs: $ 225,000275,000
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest Park's Percentage Contribution as amounting to a minimum total value of 4145% percent of the total Project Cost. The OPWC participation percentage shall be 5955% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000162,700
a.) Acquisition Expenses $ 0 Fee Simple $ 0 Easement $ 0 b.)Planning and Implementation: $ 20,000 13,600 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 13,600 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
d.) Permits135,500 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies0 e.)Contingencies: $ 0 13,600 f.)Total Estimated Costs: ====================
f.) Total Estimated Costs: = $ 225,000162,700
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkMuskingum Watershed Conservancy District's Percentage Contribution as amounting to a minimum total value of 4131% percent of the total Project Cost. The OPWC participation percentage shall be 5969% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000390,200
a.) Acquisition Expenses $ 0 Fee Simple $ 0 Easement $ 0 b.)Planning 0
b.) Planning and Implementation: $ 20,000 116,000 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 18,000 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site 98,000
c.) Site Improvements: $ 205,000274,200
d.) Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,000390,200
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkMill Creek Alliance's Percentage Contribution as amounting to a minimum total value of 4126% percent of the total Project Cost. The OPWC participation percentage shall be 59% percent74%. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000335,969
a.) Acquisition Expenses $ 0 265,000 Fee Simple $ 0 265,000 Easement $ 0 b.)Planning 0
b.) Planning and Implementation: $ 20,000 11,000 Appraisal $ 0 4,000 Title Work $ 0 2,000 Closing costs $ 0 3,000 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site 2,000
c.) Site Improvements: $ 205,00053,608
d.) Permits, Advertising, Legal: $ 01,000
e.) Contingencies: $ 0 5,361 ====================
f.) Total Estimated Costs: $ 225,000335,969
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkFairfield's Percentage Contribution as amounting to a minimum total value of 4126% percent of the total Project Cost. The OPWC participation percentage shall be 59% percent74%. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000158,000
a.) Acquisition Expenses $ 0 145,000 Fee Simple $ 0 145,000 Easement $ 0 b.)Planning and Implementation: $ 20,000 3,000 Appraisal $ 0 1,500 Title Work $ 0 Closing costs $ 0 1,000 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 500 c.)Site Improvements: $ 205,000
d.) Permits10,000 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,000158,000
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkLebanon's Percentage Contribution as amounting to a minimum total value of 4126% percent of the total Project Cost. The OPWC participation percentage shall be 5974% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000264,000
a.) Acquisition Expenses $ 0 255,000 Fee Simple $ 0 Easement $ 0 b.)Planning 255,000
b.) Planning and Implementation: $ 20,000 9,000 Appraisal $ 0 4,000 Title Work $ 0 2,500 Closing costs $ 0 2,500 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
d.) Permits0 d.)Permits, Advertising, Legal: $ 0
e.f.) ContingenciesTotal Estimated Costs: $ 0 ====================
f.) Total Estimated Costs: = $ 225,000264,000
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkThree Valley Conservation Trust's Percentage Contribution as amounting to a minimum total value of 4126% percent of the total Project Cost. The OPWC participation percentage shall be 5974% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000282,000
a.) Acquisition Expenses $ 0 256,000 Fee Simple $ 0 256,000 Easement $ 0 b.)Planning and Implementation: $ 20,000 26,000 Appraisal $ 0 3,000 Title Work $ 0 1,000 Closing costs $ 0 500 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 21,500 c.)Site Improvements: $ 205,000
d.) Permits0 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,000282,000
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkCaptina Conservancy's Percentage Contribution as amounting to a minimum total value of 4125% percent of the total Project Cost. The OPWC participation percentage shall be 5975% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000115,000
a.) Acquisition Expenses $ 0 109,347 Fee Simple $ 0 109,347 Easement $ 0 b.)Planning and Implementation: $ 20,000 1,553 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 1,553 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
0 d.) Permits)▇▇▇▇▇▇▇, Advertising, Legal: $ 0
e.) Contingencies: $ 0 4,100 f.)Total Estimated Costs: ====================
f.) Total Estimated Costs: = $ 225,000115,000
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkBotanical Garden Association, Inc.'s Percentage Contribution as amounting to a minimum total value of 4125% percent of the total Project Cost. The OPWC participation percentage shall be 5975% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,00087,465
a.) Acquisition Expenses $ 0 Fee Simple $ 0 Easement $ 0 b.)Planning and Implementation: $ 20,000 0 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
d.) Permits80,865 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies2,500 e.)Contingencies: $ 0 4,100 ====================
f.) Total Estimated Costs: $ 225,00087,465
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkMuskingum Watershed Conservancy District's Percentage Contribution as amounting to a minimum total value of 4125% percent of the total Project Cost. The OPWC participation percentage shall be 5975% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000189,849
a.) Acquisition Expenses $ 0 Fee Simple $ 0 Easement $ 0 b.)Planning and Implementation: $ 20,000 0 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site Improvements: $ 205,000
d.) Permits172,590 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies0 e.)Contingencies: $ 0 17,259 ====================
f.) Total Estimated Costs: $ 225,000189,849
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkWyoming's Percentage Contribution as amounting to a minimum total value of 4125% percent of the total Project Cost. The OPWC participation percentage shall be 5975% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,00073,190
a.) Acquisition Expenses $ 0 13,200 Fee Simple $ 0 Easement $ 0 b.)Planning 13,200
b.) Planning and Implementation: $ 20,000 12,000 Appraisal $ 0 3,000 Title Work $ 0 2,000 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site 7,000
c.) Site Improvements: $ 205,00047,990
d.) Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,00073,190
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkTecumseh Land Preservation Association's Percentage Contribution as amounting to a minimum total value of 4126% percent of the total Project Cost. The OPWC participation percentage shall be 5974% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,00056,617
a.) Acquisition Expenses $ 0 40,000 Fee Simple $ 0 40,000 Easement $ 0 b.)Planning and Implementation: $ 20,000 3,167 Appraisal $ 0 950 Title Work $ 0 752 Closing costs $ 0 465 Environmental Assessments $ 0 400 Design $ 20,000 0 Other Eligible Planning Costs $ 0 600 c.)Site Improvements: $ 205,000
d.) Permits13,450 d.)Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 ====================
f.) Total Estimated Costs: $ 225,00056,617
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkPerry County Soil & Water District's Percentage Contribution as amounting to a minimum total value of 4126% percent of the total Project Cost. The OPWC participation percentage shall be 5974% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement
PROJECT FINANCING AND EXPENSES SCHEME. The Recipient further designates the Project's estimated financial resources and estimated costs certified to the OPWC under this Agreement for the Project as defined and described in Appendix A of this Agreement to consist of the following components:
1.1 PROJECT ESTIMATED COSTS: Total dollars $ 225,000125,580
a.) Acquisition Expenses $ 0 Fee Simple $ 0 Easement $ 0 b.)Planning and Implementation: $ 20,000 17,100 Appraisal $ 0 Title Work $ 0 Closing costs $ 0 Environmental Assessments $ 0 Design $ 20,000 0 Other Eligible Planning Costs $ 0 c.)Site 17,100
c.) Site Improvements: $ 205,00094,330
d.) Permits, Advertising, Legal: $ 0
e.) Contingencies: $ 0 14,150 ====================
f.) Total Estimated Costs: $ 225,000125,580
1) OPWC/LOCAL SUBDIVISION PARTICIPATION PERCENTAGES: For the sole and express purpose of financing/reimbursing costs of the Project defined and described in Appendix A of this Agreement, the estimated costs of which are set forth and described in this Appendix D, the Recipient hereby designates The City of Forest ParkDayton's Percentage Contribution as amounting to a minimum total value of 4129% percent of the total Project Cost. The OPWC participation percentage shall be 5971% percent. However, in the event of a cost over-run, the maximum OPWC dollar contribution shall not exceed the amount identified in Appendix C.
Appears in 1 contract
Sources: Project Grant Agreement