Planning Permission. 6.1 In the event the Phase 1 PARCA Works Report identifies a need for NGG to obtain Planning Permission in relation to reinforcement works NGG shall submit an application for Planning Permission as soon as reasonably practicable after the date on which the Reservation Party provides Acceptable Security to NGG in accordance with Clause 4.1.
Appears in 3 contracts
Samples: Capacity Agreement, Capacity Agreement, www.gasgovernance.co.uk
Planning Permission. 6.1 5.1 In the event the Phase 1 PARCA Works Report identifies or Phase 2 PARCA Works identify a need for NGG to obtain Planning Permission in relation to reinforcement works NGG shall undertake those works necessary and submit an application for Planning Permission as soon as reasonably practicable after the date on which the Reservation Party provides Acceptable Security to NGG in accordance has complied with Clause 4.1its obligations under Clauses 3.1.1 and 3.1.2.
Appears in 2 contracts
Planning Permission. 6.1 5.1 In the event the Phase 1 PARCA Works Report identifies identifiesor Phase 2 PARCA Works identify a need for NGG to obtain Planning Permission in relation to reinforcement works NGG shall undertake those works necessary and submit an application for Planning Permission as soon as reasonably practicable after the date on which the Reservation Party provides Acceptable Security to NGG in accordance with Clause 4.13.1.
Appears in 1 contract
Samples: Capacity Agreement
Planning Permission. 6.1 5.1 In the event the Phase 1 PARCA Works Report identifies or Phase 2 PARCA Works identify a need for NGG to obtain Planning Permission in relation to reinforcement works NGG shall undertake those works necessary and submit an application for Planning Permission as soon as reasonably practicable after the date on which the Reservation Party provides Acceptable Security to NGG in accordance with Clause 4.13.1.
Appears in 1 contract
Samples: Capacity Agreement