PLANNED UTILITY OUTAGE PROCEDURE Clause Samples
PLANNED UTILITY OUTAGE PROCEDURE. A. The Contractor shall not activate or de-activate any campus system, or component of any such system, without express written direction from the Owner.
B. Contractor shall schedule and obtain facilities approval for any necessary outage of campus utilities planning for a minimum of fifteen (15) work days in advance through the Owner’s Project Manager, using the Owner provided “Contractor’s Request for Utility Shutdown” form and process. All outages shall be performed outside the normal working hours or as determined by the Owner.
PLANNED UTILITY OUTAGE PROCEDURE. A. The Contractor shall not activate or de-activate any campus system, or component of any such system, without express written direction from the Owner.
PLANNED UTILITY OUTAGE PROCEDURE. A. The Contractor shall not activate or de-activate any campus system, or component of any such system, without express written direction from the Owner.
B. Contractor must schedule and obtain approval for any necessary outage of campus utilities a minimum of fifteen (15) work days in advance through the Owner’s Project Manager using the Owner provided “Contractor’s Request for Utility Shutdown” forms. All outages shall be performed outside the normal working hours and as determined by the Owner’s Project Manager.
C. The Owner reserves the right to delay or suspend shutdowns or outages to more convenient times at no additional cost. MD ▇▇▇▇▇▇▇▇ Project No. 04-0042 SCRB 3 ▇▇▇▇▇ ▇▇▇▇▇ ISSUE DESCRIPTION AE Project No. 205-079R JULY, 27, 2011
PLANNED UTILITY OUTAGE PROCEDURE. A. The Contractor shall not activate or de-activate any system, or component of any such system, without express written direction from the Owner.
B. Contractor shall schedule and obtain facilities approval for any necessary outage of utilities in accordance with Attachment B, Facilities Planned Utility Outages Policy.