Common use of Outages; Coordination Clause in Contracts

Outages; Coordination. The Construction Parties acknowledge and agree that certain outages of transmission facilities owned by the Interconnected Transmission Owner, as more specifically detailed in the Scope of Work, may be necessary in order to complete the process of constructing and installing all Interconnection Facilities. The Construction Parties further acknowledge and agree that any such outages shall be coordinated by and through the Transmission Provider.

Appears in 72 contracts

Samples: Construction Service Agreement, Construction Service Agreement, Construction Service Agreement

AutoNDA by SimpleDocs

Outages; Coordination. The Construction Parties acknowledge and agree that certain outages of transmission facilities owned by the Interconnected Transmission Owner, as more specifically detailed in the Scope of Work, may be necessary in order to complete the process of constructing and installing all Interconnection FacilitiesFacilities and Transmission Owner Upgrades and Transmission Owner Upgrades. The Construction Parties further acknowledge and agree that any such outages shall be coordinated by and through the Transmission Provider.

Appears in 11 contracts

Samples: Generation Interconnection Agreement, Generation Interconnection Agreement, Generation Interconnection Agreement

Outages; Coordination. The Construction Parties acknowledge and agree that certain outages of transmission facilities owned by the Interconnected Transmission Owner, as more specifically detailed in the Scope of Work, may be necessary in order to complete the process of constructing and installing all Interconnection FacilitiesFacilities and/or Merchant Network Upgrades. The Construction Parties further acknowledge and agree that any such outages shall be coordinated by and through the Transmission Provider.

Appears in 4 contracts

Samples: Construction Service Agreement, Construction Service Agreement, Original Service Agreement

Outages; Coordination. The Construction Parties acknowledge and agree that certain outages of transmission facilities owned by the Interconnected Transmission Owner, as more specifically detailed in the Scope of Work, may be necessary in order to complete the process of constructing and installing all Interconnection FacilitiesFacilities and Transmission Owner Upgrades. The Construction Parties further acknowledge and agree that any such outages shall be coordinated by and through the Transmission Provider.

Appears in 1 contract

Samples: Generation Interconnection Agreement

AutoNDA by SimpleDocs

Outages; Coordination. The Construction Parties The Transmission Provider and Transmission Owner acknowledge and agree that certain outages of transmission facilities owned by the Interconnected Transmission Owner, as more specifically detailed in the Scope of Work, may be necessary in order to complete the process of constructing and installing all Interconnection Facilities. The Construction Parties further acknowledge and agree that any such outages shall be coordinated by and through the Transmission Provider.Facilities.the Network Upgrades identified

Appears in 1 contract

Samples: Construction Service Agreement