Common use of Operational Tests Clause in Contracts

Operational Tests. After the Work is completed and as one of the precedents to final inspection, the Contractor shall perform operational tests as required by the Contract Documents and as required to demonstrate to RMWD the correct and proper operation of the various facilities forming a part of the Work including but not limited to the correct sequences of operation and the satisfactory performance of all components. The Contractor shall repair, replace, adjust, or otherwise correct the improper operation of any system or component and all faulty or defective Work as RMWD may require for his approval. Based upon the operational tests results, the Contractor shall prepare and submit revised or additional information and data for the previously approved submittals as required by RMWD and as provided in Paragraph 12.12. Each operational test shall be performed continuously for not less than 168 hours (7 days).

Appears in 3 contracts

Sources: Contract Agreement, Contract Documents, Contract Agreement