{"component": "clause", "props": {"groups": [{"size": 6, "snippet": "24.2.1 Subject to GCC Clause 24.3 (Partial Acceptance) below, Operational Acceptance shall occur within seven (7) days in respect of the System, when\n(a) the Operational Acceptance Tests, as specified in the Technical Requirements, and/or SCC and/or the Agreed and Finalized Project Plan or\n(b) the Purchaser has put the System into production or use for sixty (60) consecutive days. If the System is put into production or use in this manner, the Supplier shall notify the Purchaser and document such use.", "samples": [{"hash": "lVsBOW95FRW", "uri": "/contracts/lVsBOW95FRW#operational-acceptance", "label": "Contract for the Acquisition and Implementation of an Enhanced Financial Analyzer System", "score": 22.9041752225, "published": true}, {"hash": "9YCA7rsjJrW", "uri": "/contracts/9YCA7rsjJrW#operational-acceptance", "label": "Contract for the Acquisition and Implementation of a Sector Benchmarking and Datamining", "score": 22.9041752225, "published": true}, {"hash": "7Ytt4xruyTS", "uri": "/contracts/7Ytt4xruyTS#operational-acceptance", "label": "Supply, Installation, Training and Maintenance Agreement", "score": 22.3374401095, "published": true}], "snippet_links": [{"key": "subject-to", "type": "definition", "offset": [7, 17]}, {"key": "partial-acceptance", "type": "definition", "offset": [35, 53]}, {"key": "in-respect-of", "type": "clause", "offset": [119, 132]}, {"key": "the-system", "type": "definition", "offset": [133, 143]}, {"key": "operational-acceptance-tests", "type": "definition", "offset": [158, 186]}, {"key": "as-specified", "type": "clause", "offset": [188, 200]}, {"key": "technical-requirements", "type": "definition", "offset": [208, 230]}, {"key": "agreed-and", "type": "definition", "offset": [254, 264]}, {"key": "project-plan", "type": "clause", "offset": [275, 287]}, {"key": "the-purchaser", "type": "definition", "offset": [295, 308]}, {"key": "consecutive-days", "type": "definition", "offset": [366, 382]}, {"key": "the-supplier-shall", "type": "clause", "offset": [444, 462]}, {"key": "notify-the", "type": "clause", "offset": [463, 473]}], "hash": "9bddb5737dcf32e2de4b4a0bc730e64b", "id": 1}, {"size": 5, "snippet": "Central \u2587\u2587\u2587\u2587\u2587\u2587 shall notify Con Edison upon completion of the construction of the Second Tie. Central \u2587\u2587\u2587\u2587\u2587\u2587 shall inspect and accept the Second Tie up to and including circuit breaker B9756 to confirm its compliance with the requirements of Section 3.0l (a) and its fitness for commercial operation. Con Edison shall test and accept the disconnect switch to be located in its substation and its associated indication and operational controls to confirm their compliance with the requirements of Section 3.0l (a) and their fitness for commercial operation. Central \u2587\u2587\u2587\u2587\u2587\u2587 and Con Edison will both test the relay protection equipment that operates circuit breaker B9756. Promptly after those matters have been confirmed to Con Edison's reasonable satisfaction, Con Edison shall provide written notification to Central \u2587\u2587\u2587\u2587\u2587\u2587 that the Second Tie is acceptable.", "samples": [{"hash": "9JR6HM6EZm1", "uri": "/contracts/9JR6HM6EZm1#operational-acceptance", "label": "Facilities Agreement", "score": 27.1399154823, "published": true}, {"hash": "2t51Bm4AlsW", "uri": "/contracts/2t51Bm4AlsW#operational-acceptance", "label": "Facilities Agreement", "score": 26.223913044, "published": true}, {"hash": "alO3p52oqwv", "uri": "/contracts/alO3p52oqwv#operational-acceptance", "label": "Facilities Agreement", "score": 26.2211756764, "published": true}], "snippet_links": [{"key": "con-edison", "type": "definition", "offset": [28, 38]}, {"key": "construction-of-the", "type": "clause", "offset": [62, 81]}, {"key": "second-tie", "type": "definition", "offset": [82, 92]}, {"key": "circuit-breaker", "type": "clause", "offset": [169, 184]}, {"key": "the-requirements", "type": "clause", "offset": [222, 238]}, {"key": "commercial-operation", "type": "clause", "offset": [279, 299]}, {"key": "disconnect-switch", "type": "definition", "offset": [338, 355]}, {"key": "located-in", "type": "definition", "offset": [362, 372]}, {"key": "operational-controls", "type": "definition", "offset": [422, 442]}, {"key": "relay-protection", "type": "clause", "offset": [606, 622]}, {"key": "reasonable-satisfaction", "type": "clause", "offset": [735, 758]}, {"key": "notification-to", "type": "clause", "offset": [793, 808]}], "hash": "0eb1db6a997907cb706e1abdfdc32691", "id": 2}, {"size": 2, "snippet": "(a) Subject to GCC Clause 27.4 (Partial Acceptance) below, Operational Acceptance shall occur in respect of the System, when\n(b) the Operational Acceptance Tests, as specified in the Technical Requirements, and/or SCC and/or the Agreed and Finalized Project Plan have been successfully completed; or\n(c) the Operational Acceptance Tests have not been successfully completed or have not been carried out for reasons that are attributable to the Purchaser within the period from the date of Installation or any other agreed-upon period as specified in GCC Clause 27.2.2 above; or\n(d) the Purchaser has put the System into production or use for sixty (60) consecutive days. If the System is put into production or use in this manner, the Supplier shall notify the Purchaser and document such use.", "samples": [{"hash": "i1rRHtThayu", "uri": "/contracts/i1rRHtThayu#operational-acceptance", "label": "Build, Operate and Transfer (Bot) Agreement (On Track Innovations LTD)", "score": 23.2039698836, "published": true}, {"hash": "b8DlMZRSZAW", "uri": "/contracts/b8DlMZRSZAW#operational-acceptance", "label": "Build, Operate and Transfer (Bot) Agreement (On Track Innovations LTD)", "score": 22.9657768652, "published": true}], "snippet_links": [{"key": "subject-to", "type": "definition", "offset": [4, 14]}, {"key": "partial-acceptance", "type": "definition", "offset": [32, 50]}, {"key": "in-respect-of", "type": "clause", "offset": [94, 107]}, {"key": "the-system", "type": "definition", "offset": [108, 118]}, {"key": "operational-acceptance-tests", "type": "definition", "offset": [133, 161]}, {"key": "as-specified", "type": "clause", "offset": [163, 175]}, {"key": "technical-requirements", "type": "definition", "offset": [183, 205]}, {"key": "agreed-and", "type": "definition", "offset": [229, 239]}, {"key": "project-plan", "type": "clause", "offset": [250, 262]}, {"key": "successfully-completed", "type": "definition", "offset": [273, 295]}, {"key": "the-purchaser", "type": "definition", "offset": [440, 453]}, {"key": "period-from", "type": "definition", "offset": [465, 476]}, {"key": "date-of-installation", "type": "definition", "offset": [481, 501]}, {"key": "consecutive-days", "type": "definition", "offset": [653, 669]}, {"key": "the-supplier-shall", "type": "clause", "offset": [731, 749]}, {"key": "notify-the", "type": "clause", "offset": [750, 760]}], "hash": "491bd221e8d6164770c2fd7d633a69fc", "id": 3}, {"size": 2, "snippet": "Acceptance regarding the capability of the software to run on the system defined in the contract.", "samples": [{"hash": "6dPxymEok7O", "uri": "/contracts/6dPxymEok7O#operational-acceptance", "label": "Software Maintenance Contract", "score": 20.8001368925, "published": true}, {"hash": "5y94WrZvXI5", "uri": "/contracts/5y94WrZvXI5#operational-acceptance", "label": "License Agreement", "score": 20.8001368925, "published": true}], "snippet_links": [{"key": "the-software", "type": "clause", "offset": [39, 51]}, {"key": "system-defined", "type": "clause", "offset": [66, 80]}, {"key": "in-the-contract", "type": "clause", "offset": [81, 96]}], "hash": "4e89b7979fad9f28c522c9f31b33adfd", "id": 4}, {"size": 2, "snippet": "Acceptance, subject to Final Acceptance, of an Electronic File or Service Deliverable\u2019s meeting the design and operational specifications as detailed in an Accepted Deliverable. yy) Other Eligible User (OEU) - An Eligible User that is not an Agency. zz) Payment Settlement File - An electronic file, transmitted to DFS by the Contractor, containing State of Florida accounting information for all participating Agency Transactions processed in the Solution. The Payment Settlement File allows for verification of accounting controls in FLAIR before payment is made to the Contractor.", "samples": [{"hash": "cWZWL08et90", "uri": "/contracts/cWZWL08et90#operational-acceptance", "label": "Contract for Purchasing Card Services", "score": 24.0061601643, "published": true}, {"hash": "82nRdTme4Oo", "uri": "/contracts/82nRdTme4Oo#operational-acceptance", "label": "Contract for Purchasing Card Services", "score": 24.0061601643, "published": true}], "snippet_links": [{"key": "subject-to", "type": "definition", "offset": [12, 22]}, {"key": "final-acceptance", "type": "clause", "offset": [23, 39]}, {"key": "electronic-file", "type": "definition", "offset": [47, 62]}, {"key": "service-deliverable", "type": "definition", "offset": [66, 85]}, {"key": "the-design", "type": "clause", "offset": [96, 106]}, {"key": "eligible-user", "type": "clause", "offset": [188, 201]}, {"key": "an-eligible", "type": "clause", "offset": [210, 221]}, {"key": "an-agency", "type": "definition", "offset": [239, 248]}, {"key": "settlement-file", "type": "clause", "offset": [262, 277]}, {"key": "by-the-contractor", "type": "clause", "offset": [319, 336]}, {"key": "state-of-florida", "type": "definition", "offset": [349, 365]}, {"key": "accounting-information", "type": "clause", "offset": [366, 388]}, {"key": "agency-transactions", "type": "clause", "offset": [411, 430]}, {"key": "the-solution", "type": "definition", "offset": [444, 456]}, {"key": "the-payment", "type": "clause", "offset": [458, 469]}, {"key": "accounting-controls", "type": "definition", "offset": [513, 532]}, {"key": "before-payment-is", "type": "clause", "offset": [542, 559]}, {"key": "to-the-contractor", "type": "clause", "offset": [565, 582]}], "hash": "8c44215c55d18ad60ab2772d5f1d690b", "id": 5}, {"size": 2, "snippet": "City\u2019s acceptance of Project shall occur upon Subdivider\u2019s receipt of a letter of acceptance from City after Subdivider complies with the Punch List and passes Final Inspection (as defined in Section 15.4) confirming that Project is substantially complete and operational [Operational Acceptance].", "samples": [{"hash": "ahKWITIdrEt", "uri": "/contracts/ahKWITIdrEt#operational-acceptance", "label": "Reimbursement Agreement", "score": 24.1704312115, "published": true}, {"hash": "bpUfkNKqeYC", "uri": "/contracts/bpUfkNKqeYC#operational-acceptance", "label": "Reimbursement Agreement", "score": 20.0622861054, "published": true}], "snippet_links": [{"key": "acceptance-of-project", "type": "clause", "offset": [7, 28]}, {"key": "receipt-of", "type": "clause", "offset": [59, 69]}, {"key": "letter-of-acceptance", "type": "definition", "offset": [72, 92]}, {"key": "punch-list", "type": "definition", "offset": [138, 148]}, {"key": "final-inspection", "type": "definition", "offset": [160, 176]}, {"key": "section-154", "type": "clause", "offset": [192, 204]}, {"key": "substantially-complete", "type": "clause", "offset": [233, 255]}], "hash": "aaf88afbd7fd185f3590f97ef4d1d73d", "id": 6}, {"size": 1, "snippet": "26.3.1 Subject to GC Sub-clause 26.4 below, Operational Acceptance shall occur in respect of the Facilities or any part thereof when\n(a) the Guarantee Test has been successfully completed and the Functional Guarantees are met; or\n(b) the Guarantee Test has not been successfully completed or has not been carried out for reasons not attributable to the Contractor within the period from the date of Completion specified in the PC pursuant to GC Sub-Clause 26.2.2 above or any other period agreed upon by the Employer and the Contractor; or\n(c) the Contractor has paid the liquidated damages specified in GC Sub-Clause 29.3 hereof; and\n(d) any minor items mentioned in GC Sub-Clause 25.7 hereof relevant to the Facilities or that part thereof have been completed.\n26.3.2 At any time after any of the events set out in GC Sub-Clause 26.\n3.1 have occurred, the contractor may give a notice to the Project Manager requesting the issue of an Operational Acceptance Certificate in the form provided in the Employer\u2019s Requirements (Forms and Procedures) in respect of the Facilities or the part thereof specified in such notice as of the date of such notice.\n26.3.3 The Project Manager shall, after consultation with the Employer, and within seven (7) days after receipt of the Contractor\u2019s notice, issue an Operational Acceptance Certificate.\n26.3.4 If within seven (7) days after receipt of the Contractor\u2019s notice, the Project Manager fails to issue the Operational Acceptance Certificate or fails to inform the Contractor in writing of the justifiable reasons why the Project Manager has not issued the Operational Acceptance Certificate, the Facilities or the relevant part thereof shall be deemed to have been accepted as of the date of the Contractor\u2019s said notice.", "samples": [{"hash": "hUxqFpTCcyy", "uri": "/contracts/hUxqFpTCcyy#operational-acceptance", "label": "Contract for the Plant Design, Supply, Delivery, Installation and Commissioning of an Integrated Security System (Magal Security Systems LTD)", "score": 20.273100616, "published": true}], "snippet_links": [{"key": "subject-to", "type": "definition", "offset": [7, 17]}, {"key": "in-respect-of", "type": "clause", "offset": [79, 92]}, {"key": "the-facilities", "type": "clause", "offset": [93, 107]}, {"key": "the-guarantee", "type": "clause", "offset": [137, 150]}, {"key": "successfully-completed", "type": "definition", "offset": [165, 187]}, {"key": "functional-guarantees", "type": "clause", "offset": [196, 217]}, {"key": "to-the-contractor", "type": "clause", "offset": [346, 363]}, {"key": "period-from", "type": "definition", "offset": [375, 386]}, {"key": "date-of-completion", "type": "definition", "offset": [391, 409]}, {"key": "pursuant-to", "type": "definition", "offset": [430, 441]}, {"key": "other-period", "type": "definition", "offset": [476, 488]}, {"key": "and-the-contractor", "type": "clause", "offset": [517, 535]}, {"key": "liquidated-damages", "type": "definition", "offset": [572, 590]}, {"key": "at-any-time", "type": "clause", "offset": [770, 781]}, {"key": "the-events", "type": "clause", "offset": [795, 805]}, {"key": "set-out", "type": "definition", "offset": [806, 813]}, {"key": "the-contractor-may", "type": "clause", "offset": [854, 872]}, {"key": "the-project-manager", "type": "clause", "offset": [890, 909]}, {"key": "the-issue", "type": "clause", "offset": [921, 930]}, {"key": "operational-acceptance-certificate", "type": "definition", "offset": [937, 971]}, {"key": "forms-and-procedures", "type": "clause", "offset": [1025, 1045]}, {"key": "after-consultation-with", "type": "clause", "offset": [1186, 1209]}, {"key": "of-the-contractor", "type": "clause", "offset": [1264, 1281]}, {"key": "to-issue", "type": "clause", "offset": [1437, 1445]}, {"key": "in-writing", "type": "clause", "offset": [1519, 1529]}, {"key": "relevant-part", "type": "definition", "offset": [1658, 1671]}], "hash": "4b474bf158ddb0c7e0ac33e2145ed7a9", "id": 7}, {"size": 1, "snippet": "Testing (OAT)", "samples": [{"hash": "5W5uhAWG7u0", "uri": "/contracts/5W5uhAWG7u0#operational-acceptance", "label": "Nec3 Engineering & Construction Contract", "score": 26.2511978097, "published": true}], "snippet_links": [], "hash": "a7cde9819b3143dbfe48e43a0de973a2", "id": 8}, {"size": 1, "snippet": "(a) Operational Acceptance shall occur in respect of the New Facility when the Tests on Commissioning have been successfully completed.\n(b) At any time after the successful completion of the Tests on Commissioning, the Operator may give a notice to the Design-Build Engineer requesting the issue of an Operational Acceptance Certificate in respect of the New Facility.\n(c) The Design-Build Engineer shall, after consultation with the Owner, and no later than 7 days after receipt of the Operator\u2019s notice, issue an Operational Acceptance Certificate.\n(d) If within 7 days after receipt of the Operator\u2019s notice, the Design-Build Engineer fails to issue the Operational Acceptance Certificate or fails to inform the Operator in writing of the justifiable reasons why the Design-Build Engineer has not issued the Operational Acceptance Certificate, the New Facility shall be deemed to have been accepted as of the date of the Operator\u2019s said notice.", "samples": [{"hash": "1O9NjNcONzx", "uri": "/contracts/1O9NjNcONzx#operational-acceptance", "label": "Design Build and Operate Agreement", "score": 22.4140999316, "published": true}], "snippet_links": [{"key": "in-respect-of", "type": "clause", "offset": [39, 52]}, {"key": "new-facility", "type": "definition", "offset": [57, 69]}, {"key": "successfully-completed", "type": "definition", "offset": [112, 134]}, {"key": "at-any-time", "type": "clause", "offset": [140, 151]}, {"key": "completion-of-the", "type": "clause", "offset": [173, 190]}, {"key": "the-design", "type": "clause", "offset": [249, 259]}, {"key": "the-issue", "type": "clause", "offset": [286, 295]}, {"key": "operational-acceptance-certificate", "type": "definition", "offset": [302, 336]}, {"key": "after-consultation-with", "type": "clause", "offset": [406, 429]}, {"key": "the-owner", "type": "definition", "offset": [430, 439]}, {"key": "of-the-operator", "type": "clause", "offset": [480, 495]}, {"key": "to-issue", "type": "clause", "offset": [644, 652]}, {"key": "in-writing", "type": "clause", "offset": [724, 734]}, {"key": "facility-shall", "type": "clause", "offset": [855, 869]}, {"key": "date-of", "type": "clause", "offset": [912, 919]}], "hash": "2bbb69c4966fda7b5b3b571960d15d20", "id": 9}, {"size": 1, "snippet": "27.3.1 Subject to GCC Clause 27.4 (Partial Acceptance) below, Operational Acceptance shall occur in respect of the System, when\n(a) the Operational Acceptance Tests, as specified in the Technical Requirements, and/or SCC and/or the Agreed and Finalized Project Plan have been successfully completed; or\n(b) the Operational Acceptance Tests have not been successfully completed or have not been carried out for reasons that are attributable to the Purchaser within the period from the date of Installation or any other agreed-upon period as specified in GCC Clause\n27.2.2 above; or", "samples": [{"hash": "dUsFmrVUMpH", "uri": "/contracts/dUsFmrVUMpH#operational-acceptance", "label": "Contract for Procurement of Electronic Health Record Software", "score": 32.0753892293, "published": true}], "snippet_links": [{"key": "subject-to", "type": "definition", "offset": [7, 17]}, {"key": "partial-acceptance", "type": "definition", "offset": [35, 53]}, {"key": "in-respect-of", "type": "clause", "offset": [97, 110]}, {"key": "the-system", "type": "definition", "offset": [111, 121]}, {"key": "operational-acceptance-tests", "type": "definition", "offset": [136, 164]}, {"key": "as-specified", "type": "clause", "offset": [166, 178]}, {"key": "technical-requirements", "type": "definition", "offset": [186, 208]}, {"key": "agreed-and", "type": "definition", "offset": [232, 242]}, {"key": "project-plan", "type": "clause", "offset": [253, 265]}, {"key": "successfully-completed", "type": "definition", "offset": [276, 298]}, {"key": "the-purchaser", "type": "definition", "offset": [443, 456]}, {"key": "period-from", "type": "definition", "offset": [468, 479]}, {"key": "date-of-installation", "type": "definition", "offset": [484, 504]}], "hash": "058cf2a22698ad0d64fe6e626c4f7563", "id": 10}], "next_curs": "Cl8SWWoVc35sYXdpbnNpZGVyY29udHJhY3RzcjsLEhZDbGF1c2VTbmlwcGV0R3JvdXBfdjU2Ih9vcGVyYXRpb25hbC1hY2NlcHRhbmNlIzAwMDAwMDBhDKIBAmVuGAAgAA==", "clause": {"size": 24, "children": [["", ""], ["general-provisions-applicable-to-plans-and-programs", "General Provisions Applicable to Plans and Programs"], ["definitions", "Definitions"], ["transfer-of-assigning-lenders-participation-in-advances", "Transfer of Assigning Lender\u2019s Participation in Advances"], ["confirmations", "Confirmations"]], "parents": [["fraud-and-corruption", "Fraud and Corruption"], ["rights-obligations-and-responsibilities", "Rights, Obligations and Responsibilities"], ["ownership", "Ownership"], ["subject-of-the-agreement", "Subject of the Agreement"], ["definition-of-terms", "Definition of Terms"]], "title": "Operational Acceptance", "id": "operational-acceptance", "related": [["final-acceptance", "Final Acceptance", "Final Acceptance"], ["additional-acceptable-uses-of-student-data", "Additional Acceptable Uses of Student Data", "Additional Acceptable Uses of Student Data"], ["order-acceptance", "Order Acceptance", "Order Acceptance"], ["product-acceptance", "PRODUCT ACCEPTANCE", "PRODUCT ACCEPTANCE"], ["contract-acceptance", "CONTRACT ACCEPTANCE", "CONTRACT ACCEPTANCE"]], "related_snippets": [], "updated": "2025-07-07T12:37:53+00:00", "also_ask": [], "drafting_tip": null, "explanation": "The Operational Acceptance clause defines the process and criteria by which a delivered product, system, or service is formally accepted as meeting the agreed operational requirements. Typically, this involves the customer conducting tests or reviews to ensure the deliverable functions correctly in its intended environment, such as verifying software performance or equipment reliability under real-world conditions. This clause ensures that the supplier's obligations are clearly met before final acceptance, reducing the risk of disputes and ensuring the product is fit for its intended use."}, "json": true, "cursor": ""}}