OASIS Posting. Transmission Provider will maintain on its OASIS a list of all Interconnection Requests. The list will identify, for each Interconnection Request: (i) the maximum summer and winter megawatt electrical output;
Appears in 8 contracts
Sources: Standard Large Generator Interconnection Procedures, Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)
OASIS Posting. Transmission Provider will maintain on its OASIS a list of all Interconnection Requests. The list will identify, for each Interconnection Request: (i) the maximum summer and winter megawatt electrical output; (ii) the location by county and state; (iii) the station or transmission line or lines where the interconnection will be made; (iv) the projected In- Service Date; (v) the status of the Interconnection Request, including Queue Position;
Appears in 4 contracts
Sources: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
OASIS Posting. 3.5.1 Transmission Provider will maintain on its OASIS a list of all Interconnection Requests. The list will identify, for each Interconnection Request: (i) the maximum summer and winter megawatt electrical output;
Appears in 4 contracts
Sources: Large Generator Interconnection Procedures and Agreement, Standard Large Generator Interconnection Procedures (Lgip), Standard Large Generator Interconnection Agreement (Lgia)
OASIS Posting. Transmission Provider will maintain on its OASIS a list of all Interconnection Requests. The list will identify, for each Interconnection Request: (i) the maximum summer and winter megawatt electrical output; (ii) the location by Operating Region;
Appears in 1 contract
Sources: Standard Generator Interconnection Agreement (Sgia)
OASIS Posting. Transmission Provider will maintain on its OASIS a list of all Interconnection Requests. The list will identify, for each Interconnection Request: (i) the maximum summer and winter megawatt electrical output; (ii) the location by county and state;
Appears in 1 contract
Sources: Standard Large Generator Interconnection Agreement (Lgia)
OASIS Posting. Transmission Provider will maintain on its OASIS a list of all Interconnection Requests. The list will identify, for each Interconnection Request: (i) the maximum summer and winter megawatt electrical output; (ii) the location by county and state; (iii) the station or transmission line or lines where the interconnection will be made; (iv) the projected In-Service Date;
Appears in 1 contract
Sources: Standard Large Generator Interconnection Procedures (Lgip)