No Time Extensions Sample Clauses

No Time Extensions. Except as otherwise specifically provided in Section 13, TxDOT shall have no obligation to extend a Completion Deadline and DB Contractor shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of the Project by the applicable Completion Deadlines for any reason.
AutoNDA by SimpleDocs
No Time Extensions. ‌ Except as otherwise specifically provided in Section 13, IFA shall have no obligation to extend a Completion Deadline and Design-Build Contractor shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance by the applicable Completion Deadlines for any reason.‌
No Time Extensions. Except as otherwise specifically provided in this Contract, Owner has no obligation to extend the Scheduled Substantial Completion Date, and Contractor shall not be relieved of its obligation to achieve Substantial Completion for any reason.
No Time Extensions. Except as otherwise specifically provided in this Contract, Owner has no obligation to extend the Contract Time(s), and Contractor shall not be relieved of its obligation to achieve completion within the Contract Time(s) for any reason.
No Time Extensions. Except in the instances where a specified product is not commercially available, the Project Schedule shall not be adjusted as a result of any circumstance relating to a proposed Substitution.
No Time Extensions. Except as otherwise specifically provided in Section 13, TxDOT shall have no obligation to extend a Completion Deadline and Developer shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance by the applicable Completion Deadlines for any reason.
No Time Extensions. Except as otherwise specifically provided in Section 12, TxDOT shall have no obligation to extend a Completion Deadline and Developer shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of each Phase of the Project and complete the Bridge Demolition Work by the applicable Completion Deadlines for any reason.
AutoNDA by SimpleDocs
No Time Extensions. Except as otherwise specifically provided in Section 20 (Relief & Compensation) and Section 21 (Construction Phase Change Orders), the Department shall have no obligation to extend any Completion Deadline and the Progressive Contractor shall not be relieved of its obligation to perform the Construction Work in accordance with each Baseline Pricing Package Schedule, and to achieve the Completion Deadlines for any reason.
No Time Extensions. Except as otherwise specifically provided in this Contract, the County has no obligation to extend the Scheduled Substantial Completion Date, and Contractor shall not be relieved of its obligation to achieve Substantial Completion for any reason.
No Time Extensions. Except as otherwise specifically provided in Article 19, Department shall have no obligation to extend the Substantial Completion, and Contractor shall not be relieved of its obligation to achieve Substantial Completion by the Substantial Completion Date for any reason.