{"component": "clause", "props": {"groups": [{"snippet": "8.3.1 The Architect shall have authority to order minor Changes in the Work, within the Scope of the Work, not involving additional cost or an extension of the Project Time Schedule and not inconsistent with the Contract Documents. Such Changes may be effected by Field Order. Such Changes shall be binding on the Owner and \u2587\u2587\u2587\u2587, provided notice and reasonable opportunity to object have been given.", "samples": [{"hash": "27LaQcfauoJ", "uri": "/contracts/27LaQcfauoJ#minor-changes-in-the-work", "label": "Construction Manager at Risk Contract", "score": 25.4681720734, "published": true}, {"hash": "9KFcjvee4Vk", "uri": "/contracts/9KFcjvee4Vk#minor-changes-in-the-work", "label": "Construction Manager at Risk Contract", "score": 25.3586578369, "published": true}], "size": 18, "snippet_links": [{"key": "the-architect-shall", "type": "clause", "offset": [6, 25]}, {"key": "authority-to", "type": "definition", "offset": [31, 43]}, {"key": "scope-of-the-work", "type": "definition", "offset": [88, 105]}, {"key": "additional-cost", "type": "definition", "offset": [121, 136]}, {"key": "project-time-schedule", "type": "definition", "offset": [160, 181]}, {"key": "the-contract-documents", "type": "definition", "offset": [208, 230]}, {"key": "field-order", "type": "definition", "offset": [264, 275]}, {"key": "the-owner", "type": "clause", "offset": [310, 319]}, {"key": "opportunity-to-object", "type": "clause", "offset": [361, 382]}], "hash": "2173bb73dd19badcb1dfedaf52fb3de1", "id": 2}, {"snippet": "If permitted in the agreement between Owner and Architect, the Architect has authority to order minor changes in the Work not involving adjustment in the Contract Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents.", "samples": [{"hash": "fjoAjtffFT8", "uri": "/contracts/fjoAjtffFT8#minor-changes-in-the-work", "label": "Contract for Construction Manager at Risk", "score": 35.8654747009, "published": true}, {"hash": "gPrvgeYb5HK", "uri": "/contracts/gPrvgeYb5HK#minor-changes-in-the-work", "label": "Construction Manager at Risk Contract", "score": 35.7072029114, "published": true}, {"hash": "f9eijEuUTAJ", "uri": "/contracts/f9eijEuUTAJ#minor-changes-in-the-work", "label": "Contract for Construction", "score": 35.1071090698, "published": true}], "size": 68, "snippet_links": [{"key": "agreement-between", "type": "clause", "offset": [20, 37]}, {"key": "the-architect", "type": "clause", "offset": [59, 72]}, {"key": "authority-to", "type": "definition", "offset": [77, 89]}, {"key": "the-contract-sum", "type": "definition", "offset": [150, 166]}, {"key": "the-contract-time", "type": "clause", "offset": [183, 200]}, {"key": "intent-of-the-contract-documents", "type": "clause", "offset": [231, 263]}], "hash": "23cad6be57edbfc2d794c09dea8b9b9b", "id": 1}, {"snippet": "10.3.1 Design Professional may make minor changes in the Work consistent with the intent of the Contract Documents providing such changes do not involve an adjustment in the GMP or Contract Time(s) of performance and do not materially affect or alter the design, quality, or performance. The Design Professional shall promptly inform Owner, in writing, of any such changes, and verify that CM@Risk has recorded such changes on the As-Built Documents.", "samples": [{"hash": "ivW33qkc7KN", "uri": "/contracts/ivW33qkc7KN#minor-changes-in-the-work", "label": "Standard Agreement Between Owner and Cm@risk on the Basis of a Guaranteed Maximum Price", "score": 36.4387613044, "published": true}, {"hash": "hKs3J1ml0WN", "uri": "/contracts/hKs3J1ml0WN#minor-changes-in-the-work", "label": "Construction Manager at Risk Agreement", "score": 30.8774375916, "published": true}, {"hash": "s3N2DRFsFf", "uri": "/contracts/s3N2DRFsFf#minor-changes-in-the-work", "label": "Construction Manager at Risk Agreement", "score": 24.1718006134, "published": true}], "size": 14, "snippet_links": [{"key": "consistent-with-the", "type": "clause", "offset": [62, 81]}, {"key": "intent-of-the-contract-documents", "type": "clause", "offset": [82, 114]}, {"key": "the-design-professional", "type": "clause", "offset": [288, 311]}, {"key": "in-writing", "type": "clause", "offset": [341, 351]}], "hash": "90d37a201c16400af618c156f8ed9b2c", "id": 5}, {"snippet": "Owner shall have Owner to order minor changes in the work not involving an adjustment in the Contract Price or an extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes shall be effected by written order and shall be binding on \u2587\u2587\u2587\u2587. \u2587\u2587\u2587\u2587 shall carry out such written orders promptly.", "samples": [{"hash": "czTfJAP8C9W", "uri": "/contracts/czTfJAP8C9W#minor-changes-in-the-work", "label": "Construction Contract", "score": 29.6528186798, "published": true}, {"hash": "1zOoSMk2CCj", "uri": "/contracts/1zOoSMk2CCj#minor-changes-in-the-work", "label": "Construction Manager at Risk Construction Agreement", "score": 28.5770339966, "published": true}, {"hash": "3ZW37gmplcQ", "uri": "/contracts/3ZW37gmplcQ#minor-changes-in-the-work", "label": "Construction Contract", "score": 28.4894371033, "published": true}], "size": 17, "snippet_links": [{"key": "adjustment-in-the-contract-price", "type": "clause", "offset": [75, 107]}, {"key": "the-contract-time", "type": "clause", "offset": [127, 144]}, {"key": "intent-of-the-contract-documents", "type": "clause", "offset": [175, 207]}, {"key": "written-orders", "type": "clause", "offset": [313, 327]}], "hash": "0a432f831dd6089c2fb6653d4d0ae2a0", "id": 4}, {"snippet": "8.4.1 The Design Builder shall have authority to make minor changes in the Construction Documents and construction consistent with the intent of the Contract Documents when such minor changes do not involve adjustment in the Contract Sum or extension of the Contract Time. The Design Builder shall promptly inform the Owner, in writing, of minor changes in the Construction Documents and construction.", "samples": [{"hash": "crLFEHsFM8h", "uri": "/contracts/crLFEHsFM8h#minor-changes-in-the-work", "label": "Design Build Agreement (Great Plains Ethanol LLC)", "score": 19.0, "published": true}, {"hash": "3Qt7YLRQOc", "uri": "/contracts/3Qt7YLRQOc#minor-changes-in-the-work", "label": "Design Build Agreement (Great Plains Ethanol LLC)", "score": 18.0, "published": true}, {"hash": "l0Sum2TMaX3", "uri": "/contracts/l0Sum2TMaX3#minor-changes-in-the-work", "label": "Design Build Agreement (Great Plains Ethanol LLC)", "score": 17.0, "published": true}], "size": 12, "snippet_links": [{"key": "the-design", "type": "clause", "offset": [6, 16]}, {"key": "authority-to", "type": "definition", "offset": [36, 48]}, {"key": "changes-in", "type": "definition", "offset": [60, 70]}, {"key": "the-construction-documents", "type": "clause", "offset": [71, 97]}, {"key": "consistent-with-the", "type": "clause", "offset": [115, 134]}, {"key": "intent-of-the-contract-documents", "type": "clause", "offset": [135, 167]}, {"key": "the-contract-sum", "type": "definition", "offset": [221, 237]}, {"key": "the-contract-time", "type": "clause", "offset": [254, 271]}, {"key": "the-owner", "type": "clause", "offset": [314, 323]}, {"key": "in-writing", "type": "clause", "offset": [325, 335]}], "hash": "34265099d780129b94fed6fbbdad0cc0", "id": 6}, {"snippet": "8.4.1 Minor changes in the Work do not involve an adjustment to the GMP Contract Sum or extension of the Contract Time and do not materially and adversely affect the Work, including the design, quality, performance and workmanship required by the Contract Documents. Design-Builder may make minor changes in the Work consistent with the intent of the Contract Documents, provided, however, prior to making any such change, Design-Builder must inform Owner, in writing, of any such changes and, if approved by the Owner record such changes on the record documents maintained by Design-Builder.", "samples": [{"hash": "8ocvWQ43LTs", "uri": "/contracts/8ocvWQ43LTs#minor-changes-in-the-work", "label": "Contract for Design Build Services", "score": 29.6894207001, "published": true}, {"hash": "buCjQXxL7Ap", "uri": "/contracts/buCjQXxL7Ap#minor-changes-in-the-work", "label": "Design Build Services Contract", "score": 28.0935344696, "published": true}, {"hash": "krmHatE10HK", "uri": "/contracts/krmHatE10HK#minor-changes-in-the-work", "label": "Contract for Design Build Services", "score": 27.2285270691, "published": true}], "size": 17, "snippet_links": [{"key": "adjustment-to", "type": "clause", "offset": [50, 63]}, {"key": "contract-sum", "type": "clause", "offset": [72, 84]}, {"key": "the-contract-time", "type": "clause", "offset": [101, 118]}, {"key": "adversely-affect", "type": "definition", "offset": [145, 161]}, {"key": "the-design", "type": "clause", "offset": [182, 192]}, {"key": "required-by", "type": "definition", "offset": [231, 242]}, {"key": "consistent-with-the", "type": "clause", "offset": [317, 336]}, {"key": "intent-of-the-contract-documents", "type": "clause", "offset": [337, 369]}, {"key": "prior-to", "type": "clause", "offset": [390, 398]}, {"key": "in-writing", "type": "clause", "offset": [457, 467]}, {"key": "by-the-owner", "type": "clause", "offset": [506, 518]}, {"key": "record-documents", "type": "definition", "offset": [546, 562]}], "hash": "a843245ce840788fe94eeaa5aacea287", "id": 3}, {"snippet": "The Architect/Engineer, after notifying the Owner, shall be authorized to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Minor changes shall be effected by written order, and shall be binding on the Owner and the Contractor. The Contractor shall carry out such written orders promptly. These written orders shall not be deemed to change or impact the Contract Sum or the Contract Time. Contractor shall have no Claim for any minor change ordered to the Work under this Paragraph 7.3 unless the Contractor submits its change proposal, prior to complying with the minor change ordered and in no event later than ten (10) working days from the date the minor change was ordered, to the Owner for approval.", "samples": [{"hash": "9MIH8LpcpQU", "uri": "/contracts/9MIH8LpcpQU#minor-changes-in-the-work", "label": "Contract 6582 Overhead Electric Distribution Work", "score": 32.398399353, "published": true}, {"hash": "iXcImdzYzqu", "uri": "/contracts/iXcImdzYzqu#minor-changes-in-the-work", "label": "Construction Contract", "score": 30.8627357483, "published": true}, {"hash": "3TltqFr4WfL", "uri": "/contracts/3TltqFr4WfL#minor-changes-in-the-work", "label": "Construction Contract", "score": 29.7157783508, "published": true}], "size": 11, "snippet_links": [{"key": "the-architect", "type": "clause", "offset": [0, 13]}, {"key": "the-contract-sum", "type": "definition", "offset": [137, 153]}, {"key": "the-contract-time", "type": "clause", "offset": [173, 190]}, {"key": "intent-of-the-contract-documents", "type": "clause", "offset": [221, 253]}, {"key": "and-the-contractor", "type": "clause", "offset": [339, 357]}, {"key": "the-contractor-shall", "type": "clause", "offset": [359, 379]}, {"key": "written-orders", "type": "clause", "offset": [395, 409]}, {"key": "no-claim", "type": "definition", "offset": [542, 550]}, {"key": "change-proposal", "type": "definition", "offset": [651, 666]}, {"key": "prior-to", "type": "clause", "offset": [668, 676]}, {"key": "complying-with", "type": "clause", "offset": [677, 691]}, {"key": "in-no-event", "type": "clause", "offset": [721, 732]}, {"key": "working-days", "type": "clause", "offset": [753, 765]}, {"key": "for-approval", "type": "definition", "offset": [823, 835]}], "hash": "6818109a639b35a5453239c670e07b3d", "id": 7}, {"snippet": "County shall have the authority to order minor changes in the work not involving an adjustment in the Contract Price or an extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes shall be effected by written order and shall be binding on D- BE. D-BE shall carry out such written orders promptly.", "samples": [{"hash": "6OAQXsPvM5M", "uri": "/contracts/6OAQXsPvM5M#minor-changes-in-the-work", "label": "Contract for Facility Accessibility Improvements", "score": 34.2723770142, "published": true}, {"hash": "RkrGttHCgY", "uri": "/contracts/RkrGttHCgY#minor-changes-in-the-work", "label": "Construction Contract", "score": 33.6247406006, "published": true}, {"hash": "61o4lA6uDDO", "uri": "/contracts/61o4lA6uDDO#minor-changes-in-the-work", "label": "Construction Contract", "score": 32.7881202698, "published": true}], "size": 8, "snippet_links": [{"key": "county-shall", "type": "clause", "offset": [0, 12]}, {"key": "authority-to", "type": "definition", "offset": [22, 34]}, {"key": "adjustment-in-the-contract-price", "type": "clause", "offset": [84, 116]}, {"key": "the-contract-time", "type": "clause", "offset": [136, 153]}, {"key": "intent-of-the-contract-documents", "type": "clause", "offset": [184, 216]}, {"key": "written-orders", "type": "clause", "offset": [323, 337]}], "hash": "4090a0bec3952cab7375006d8df2f6a1", "id": 10}, {"snippet": "The Design Professional has authority to order minor changes in the Work not involving adjustment in the Contract Sum or extension of the Contract Time and not inconsistent with the Contract Documents; provided that the CM/GC agrees and confirms that costs associated with the changes are minor. Such changes will be affected by written order signed by the Design Professional and shall be binding on the Owner and CM/GC. CM/GC shall carry out such written orders promptly.", "samples": [{"hash": "i7TjP7UtTu8", "uri": "/contracts/i7TjP7UtTu8#minor-changes-in-the-work", "label": "Construction Manager / General Contractor Agreement", "score": 35.9679260254, "published": true}, {"hash": "jIVugF9A806", "uri": "/contracts/jIVugF9A806#minor-changes-in-the-work", "label": "Construction Manager / General Contractor Agreement", "score": 35.7838783264, "published": true}, {"hash": "2lbgoHLBPcR", "uri": "/contracts/2lbgoHLBPcR#minor-changes-in-the-work", "label": "Construction Manager / General Contractor Agreement", "score": 35.4806213379, "published": true}], "size": 8, "snippet_links": [{"key": "the-design-professional", "type": "clause", "offset": [0, 23]}, {"key": "authority-to", "type": "definition", "offset": [28, 40]}, {"key": "the-contract-sum", "type": "definition", "offset": [101, 117]}, {"key": "the-contract-time", "type": "clause", "offset": [134, 151]}, {"key": "the-contract-documents", "type": "definition", "offset": [178, 200]}, {"key": "provided-that", "type": "definition", "offset": [202, 215]}, {"key": "associated-with", "type": "definition", "offset": [257, 272]}, {"key": "affected-by", "type": "definition", "offset": [317, 328]}, {"key": "signed-by-the", "type": "clause", "offset": [343, 356]}, {"key": "the-owner", "type": "clause", "offset": [401, 410]}, {"key": "written-orders", "type": "clause", "offset": [449, 463]}], "hash": "bef62a3aaa3fa883bc5955ae9f79cf6c", "id": 8}, {"snippet": "The Engineer will have authority to order minor changes in the Work not involving an extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes shall be included in a Change Order. The Contractor shall carry out such orders promptly.", "samples": [{"hash": "7qyWHqZCIVm", "uri": "/contracts/7qyWHqZCIVm#minor-changes-in-the-work", "label": "Bid Specifications and Standard Agreement for Construction Services", "score": 35.6206436157, "published": true}, {"hash": "4KHSzKbuVXZ", "uri": "/contracts/4KHSzKbuVXZ#minor-changes-in-the-work", "label": "Bid Specifications and Standard Agreement for Traffic Signal Construction", "score": 35.2782287598, "published": true}, {"hash": "9YfNJRpuo5p", "uri": "/contracts/9YfNJRpuo5p#minor-changes-in-the-work", "label": "Bid Specifications and Standard Agreement", "score": 34.9461517334, "published": true}], "size": 8, "snippet_links": [{"key": "the-engineer", "type": "definition", "offset": [0, 12]}, {"key": "authority-to", "type": "definition", "offset": [23, 35]}, {"key": "the-contract-time", "type": "clause", "offset": [98, 115]}, {"key": "intent-of-the-contract-documents", "type": "clause", "offset": [146, 178]}, {"key": "a-change-order", "type": "clause", "offset": [214, 228]}, {"key": "the-contractor-shall", "type": "clause", "offset": [230, 250]}], "hash": "a1e92f9c0925cb3a0dd3e3178f98f09a", "id": 9}], "next_curs": "CmISXGoVc35sYXdpbnNpZGVyY29udHJhY3Rzcj4LEhZDbGF1c2VTbmlwcGV0R3JvdXBfdjU2IiJtaW5vci1jaGFuZ2VzLWluLXRoZS13b3JrIzAwMDAwMDBhDKIBAmVuGAAgAA==", "clause": {"size": 322, "children": [["", ""], ["oral-modification", "ORAL MODIFICATION"], ["disputes-and-claims", "DISPUTES AND CLAIMS"], ["assignment", "ASSIGNMENT"], ["schedule-of-values", "Schedule of Values"]], "title": "MINOR CHANGES IN THE WORK", "parents": [["changes-in-the-work", "Changes in the Work"], ["miscellaneous-provisions", "Miscellaneous Provisions"], ["contingent-assignment-of-subcontracts", "CONTINGENT ASSIGNMENT OF SUBCONTRACTS"], ["owners-right-to-clean-up", "OWNER\u2019S RIGHT TO CLEAN UP"], ["changes", "Changes"]], "id": "minor-changes-in-the-work", "related": [["changes-in-the-work", "Changes in the Work", "Changes in the Work"], ["changes-in-work", "Changes in Work", "Changes in Work"], ["minor-changes", "Minor Changes", "Minor Changes"], ["changes-in-writing", "Changes in Writing", "Changes in Writing"], ["termination-for-changes-in-budget-or-law", "Termination for Changes in Budget or Law", "Termination for Changes in Budget or Law"]], "related_snippets": [], "updated": "2025-07-24T04:27:57+00:00", "also_ask": ["What limits should be set on the scope and value of permissible minor changes?", "How can the clause ensure contractor compensation for cumulative minor changes?", "What drafting language best protects against disputes over what constitutes a 'minor' change?", "How do courts typically interpret 'minor changes' in construction contracts?", "What negotiation leverage does this clause provide to owners versus contractors?"], "drafting_tip": "Define 'minor changes' precisely to avoid ambiguity; specify approval procedures to ensure control; clarify cost implications to prevent disputes.", "explanation": "The \"Minor Changes in the Work\" clause allows the project owner or architect to make small adjustments to the scope or details of the construction work without requiring a formal change order or renegotiation of the contract. Typically, these changes are limited in scope, do not significantly affect the contract price or completion time, and might include things like minor material substitutions or slight modifications to installation methods. This clause streamlines the process for handling insignificant modifications, ensuring that the project can proceed efficiently without unnecessary administrative delays."}, "json": true, "cursor": ""}}