Metering Equipment. Metering equipment shall be electronic tri-vector meters of accuracy 0.2 % required for the Project (both main and check meters). The main meter shall be installed and owned by the Company, whereas the check meter shall be installed and owned by the ...
Appears in 4 contracts
Samples: Power Purchase Agreement, prms.karnataka.gov.in, karunadu.karnataka.gov.in
Metering Equipment. Metering The metering equipment shall be electronic tri-vector trivector meters of accuracy 0.2 class 0.2% required for the Project (both main and check meters). The main meter shall be installed and owned by the Company, whereas the where as check meter meters shall be installed and owned by …….ESCOM. Dedicated core of both CT‟s and PT‟s of required accuracy shall be made available by the ...Company to
Appears in 2 contracts
Samples: Co Generation, Biomass
Metering Equipment. Metering equipment shall be electronic tri-vector trivector meters of accuracy class 0.2 % required for the Project (both main and check meters). The main meter shall be installed and owned by the Company, whereas the check meter meters shall be installed and owned by the ...
Appears in 1 contract
Samples: prms.karnataka.gov.in
Metering Equipment. Metering The metering equipment shall be electronic tri-tri vector meters of having accuracy 0.2 % class of 0.2S. required for the Project (both main and check meters). The main meter shall be installed and owned by the Company, whereas the check meter meters shall be installed and owned by …….ESCOM. Dedicated core of both CT’s and PT’s of required accuracy shall be made available by the ...Company to
Appears in 1 contract
Samples: Generation Power Projects
Metering Equipment. Metering equipment shall be electronic tri-vector meters having accuracy class of accuracy 0.2 % 0.2S required for the Project (both main and check meters). The main meter shall be installed and owned by the Company, whereas the check meter meters shall be installed and owned by the ...the
Appears in 1 contract
Samples: Wind Mill Power Projects
Metering Equipment. Metering equipment shall be electronic tri-vector trivector meters of accuracy 0.2 class 0.2% required for the Project (both main and check meters). The main meter shall be installed and owned by the Company, whereas the check meter meters shall be installed and owned by the ...the
Appears in 1 contract
Samples: Windmill
Metering Equipment. Metering equipment shall be electronic tri-vector meters having accuracy class of accuracy 0.2 % required for the Project (both main and check meters). The main meter shall be installed and owned by the Company, whereas the check meter shall be installed and owned by the ...
Appears in 1 contract
Samples: Power Purchase Agreement