Common use of For Work Stoppage Clause in Contracts

For Work Stoppage. The Work is stopped for sixty (60) consecutive Days, through no act or fault of Contractor, any Subcontractor, or any employee or agent of Contractor or any Subcontractor, due to issuance of an order of a court or other public authority other than City having jurisdiction or due to an act of government, such as a declaration of a national emergency making material unavailable. This provision shall not apply to any work stoppage resulting from the City’s issuance of a suspension notice issued either for cause or for convenience.‌

Appears in 16 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

For Work Stoppage. The Work is stopped for sixty (60) consecutive Days, through no act or fault of Contractor, any Subcontractor, or any employee or agent of Contractor or any Subcontractor, due to issuance of an order of a court or other public authority other than City having jurisdiction or due to an act of government, such as a declaration of a national emergency making material unavailable. This provision shall not apply to any work stoppage resulting from the City’s issuance of a suspension notice issued either for cause or for convenience.‌convenience.

Appears in 4 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

For Work Stoppage. The Work is stopped for sixty (60) consecutive Days, through no act or fault of Contractor, any Subcontractor, or any employee or agent of Contractor or any Subcontractor, due to issuance of an order of a court or other public authority other than City having jurisdiction or due to an act of government, such as a declaration of a national emergency making material unavailable. This provision shall not apply to any work stoppage resulting from the City’s issuance of a suspension notice issued either for cause or for convenience.‌.

Appears in 4 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

For Work Stoppage. The Work is stopped for sixty (60) consecutive Daysdays, through no act or fault of ContractorCONTRACTOR, any Subcontractor, or any employee or agent of Contractor CONTRACTOR or any Subcontractor, due to issuance of an order of a court or other public authority authority, other than City CITY, having jurisdiction or due to an act of government, such as a declaration of a national emergency making material unavailable. This provision shall not apply to any work stoppage resulting from the City’s issuance of a suspension notice issued either for cause or for convenience.‌.

Appears in 1 contract

Samples: Construction Agreement

For Work Stoppage. The Work is stopped for sixty (60) consecutive Days, through no act or fault of Contractor, any Subcontractor, or any employee or agent of Contractor or any Subcontractor, due to issuance of an order of a court or other public authority other than City District having jurisdiction or due to an act of government, such as a declaration of a national emergency making material unavailable. This provision shall not apply to any work stoppage resulting from the City’s issuance of a suspension notice issued either for cause or for convenience.‌.

Appears in 1 contract

Samples: Oceano Community Services

AutoNDA by SimpleDocs

For Work Stoppage. The Work is stopped for sixty thirty (6030) consecutive Days, through no act or fault of ContractorDBE, any Subcontractor, or any employee or agent of Contractor DBE or any Subcontractor, due to issuance of an order of a court or other public authority other than City having jurisdiction or due to an act of government, such as a declaration of a national emergency making material unavailablerequiring the work to stop. This provision shall not apply to any work stoppage resulting from the City’s issuance of a suspension notice issued either for cause or for convenience.‌forconvenience.

Appears in 1 contract

Samples: Design Build Contract

For Work Stoppage. The Work is stopped for sixty (60) consecutive Days, through no act or fault of ContractorDBE, any Subcontractor, or any employee or agent of Contractor DBE or any Subcontractor, due to issuance of an order of a court or other public authority other than City having jurisdiction or due to an act of government, such as a declaration of a national emergency making material unavailable. This provision shall not apply to any work stoppage resulting from the City’s issuance of a suspension notice issued either for cause or for convenience.‌convenience.

Appears in 1 contract

Samples: Design Build Contract