Final Inspection Requirements Sample Clauses
The Final Inspection Requirements clause sets out the conditions and procedures for a formal review of work or goods before acceptance. Typically, it details who conducts the inspection, what standards or criteria must be met, and the timeframe for completion. For example, it may require the buyer to inspect delivered products within a certain number of days and notify the seller of any defects. This clause ensures that the receiving party has an opportunity to verify compliance with contract specifications before final acceptance, thereby reducing the risk of disputes over quality or performance.
Final Inspection Requirements. 20.3.3.1 Before calling for final inspection, Developer shall determine that the following have been performed:
20.3.3.1.1 The Work has been completed.
20.3.3.1.2 All life safety items are completed and in working order.
20.3.3.1.3 Mechanical and electrical Work are complete and tested, fixtures are in place, connected, and ready for tryout.
20.3.3.1.4 Electrical circuits scheduled in panels and disconnect switches labeled.
20.3.3.1. 5 Painting and special finishes complete.
Final Inspection Requirements. 20.3.3.1 Before calling for final inspection, Developer shall determine that the following have been performed:
20.3.3.1.1 The Work has been completed.
20.3.3.1.2 All life safety items are completed and in working order.
20.3.3.1.3 Mechanical and electrical Work, including, without limitation,, security system, data, fire alarm, are complete and tested, fixtures are in place, connected, and ready for tryout.
20.3.3.1.4 Electrical circuits scheduled in panels and disconnect switches labeled.
20.3.3.1.5 Painting and special finishes complete.
20.3.3.1.6 Doors complete with hardware, cleaned of protective film, relieved of sticking or binding, and in working order.
20.3.3.1.7 Tops and bottoms of doors sealed.
20.3.3.1.8 Floors waxed and polished as specified.
20.3.3.1.9 Broken glass replaced and glass cleaned.
20.3.3.1.10 Grounds cleared of Developer’s equipment, raked clean of debris, and trash removed from Site.
20.3.3.1.11 Work cleaned, free of stains, scratches, and other foreign matter, damaged and broken material replaced.
20.3.3.1.12 Finished and decorative work shall have marks, dirt, and superfluous labels removed.
20.3.3.1.13 Final cleanup, as provided herein.
Final Inspection Requirements. 20.3.3.1 Before calling for final inspection, Developer shall determine that the following have been performed:
20.3.3.1.1 The Work has been completed.
20.3.3.1.2 All life safety items are completed and in working order.
20.3.3.1.3 Mechanical and electrical Work, including, without limitation, security system, data, fire alarm, are complete and tested, fixtures are in place, connected, and ready for tryout.
20.3.3.1.4 Electrical circuits scheduled in panels and disconnect switches labeled.
20.3.3.1.5 Replace filters of operating equipment.
20.3.3.1.6 Painting and special finishes complete.
20.3.3.1.7 Doors complete with hardware, cleaned of protective film, relieved of sticking or binding, and in working order.
20.3.3.1.8 Tops and bottoms of doors sealed.
20.3.3.1.9 Floors waxed and polished as specified.
20.3.3.1.10 Carpeted and soft surfaces vacuumed.
20.3.3.1.11 Broken glass replaced and interior and exterior glass and all surfaces exposed to view cleaned.
20.3.3.1.12 Equipment and fixtures cleaned to a sanitary condition.
20.3.3.1.13 Grounds cleared of Developer’s equipment, raked clean of debris, and remove waste and surplus materials, rubbish, and construction facilities from the Site and surrounding areas.
20.3.3.1.14 Site cleaned, paved areas swept, and clean landscaped surfaces raked.
20.3.3.1.15 Roofs, gutters, down spouts, and drainage systems cleaned of debris.
20.3.3.1.16 Work cleaned, free of stains, scratches, and other foreign matter, damaged and broken material replaced.
20.3.3.1.17 Temporary labels, tape, stains, and foreign substances removed, transparent and glossy surfaces polished,
20.3.3.1.18 Finished and decorative work shall have marks, dirt, and superfluous labels removed.
20.3.3.1.19 Final cleanup, as provided herein.
Final Inspection Requirements. 20.3.3.1. Before calling for final inspection, Contractor shall determine that the following have been performed:
20.3.3.1.1. The Work has been completed.
20.3.3.1.2. All life safety items are completed and in working order.
20.3.3.1.3. Mechanical and electrical Work are complete and tested, fixtures are in place, connected, and ready for tryout.
20.3.3.1.4. Electrical circuits scheduled in panels and disconnect switches labeled.
20.3.3.1.5. Painting and special finishes complete.
20.3.3.1.6. Doors complete with hardware, cleaned of protective film, relieved of sticking or binding, and in working order.
20.3.3.1.7. Tops and bottoms of doors sealed. 20.3.3.1.8. Floors waxed and polished as specified. 20.3.3.1.
Final Inspection Requirements. Before calling for final inspection, Contractor shall determine that the following have been performed: The Work has been completed. All life safety items are completed and in working order. Mechanical and electrical Work are complete and tested, fixtures are in place, connected, and ready for tryout. Electrical circuits scheduled in panels and disconnect switches labeled. Painting and special finishes complete. Doors complete with hardware, cleaned of protective film, relieved of sticking or binding, and in working order. Tops and bottoms of doors sealed. Floors waxed and polished as specified. Broken glass replaced and glass cleaned. Grounds cleared of Contractor’s equipment, raked clean of debris, and trash removed from Site. Work cleaned, free of stains, scratches, and other foreign matter, of damaged and broken material replaced. Finished and decorative work shall have marks, dirt, and superfluous labels removed. Final cleanup, as provided herein.
Final Inspection Requirements. (i) Before calling for final inspection, Design/Builder shall determine that the following have been performed:
(1) The Work has been completed.
(2) All life safety items are completed and in working order.
(3) Electrical Work is complete and tested, fixtures are in place, connected, and ready for tryout.
(4) Electrical circuits scheduled in panels and disconnect switches labeled.