Failure to Make Payment. If the Principal Representative should fail to pay the Construction Manager within twenty-eight (28) days after the date for payment of any amount due in accordance with paragraph 9.5.10, then the Construction Manager may, upon seven (7) additional days written notice to the Principal Representative and the Architect/Engineer, stop the Work until payment of the amount owing has been received.
Appears in 3 contracts
Samples: www.colorado.gov, www.bidnet.com, www.colorado.gov
Failure to Make Payment. If the Principal Representative should fail to pay the Construction Manager within twenty-eight forty five (2845) days after the date for payment of any amount due in accordance with paragraph 9.5.109.5.11, then the Construction Manager may, upon seven (7) additional days written notice to the Principal Representative and the Architect/Engineer, stop the Work until payment of the amount owing has been received.
Appears in 2 contracts
Samples: www.cuanschutz.edu, www.coloradomesa.edu