Extended Overhead Cost Clause Samples
Extended Overhead Cost. Cost incurred by Contractor in event Contract Time is extended beyond completion date set for entire Work, and District caused time extension is sole-and- controlling cause of such extension. Only costs incurred by Contractor on project work site are eligible to be classified as Extended Overhead Costs, and only if Contractor satisfies pertinent requirements set out in this specification. Such Costs: Limited to direct daily costs associated with temporary facilities on project site and supervision assigned full-time to Project site. Actual or alleged off-site costs associated with time extensions shall be deemed fully compensated by percentage mark-ups in Change Order Section that is part of this Contract, if any, or as negotiated between parties.