Equipment Procurement. If responsibility for construction of the TIF is borne by the TSP, then the TSP shall commence design of the TIF and procure necessary equipment within a reasonable time after all of the following conditions are satisfied:
Appears in 12 contracts
Samples: Interconnection Agreement, Ercot Standard Generation Interconnection Agreement, Generation Interconnection Agreement
Equipment Procurement. If responsibility for construction of the TIF is borne by the TSP, then the TSP shall commence design of the TIF and procure necessary equipment within a reasonable time after all of the following conditions are satisfied:: The TSP has completed the Facilities Study pursuant to the Facilities Study Agreement;
Appears in 2 contracts
Samples: Interconnection Agreement, Interconnection Agreement