Early Commissioning Sample Clauses

Early Commissioning. The WPD shall be permitted for full commissioning as well as part commissioning of the Project even prior to the Scheduled Commissioning Date, subject to availability of transmission connectivity and Long-Term Access (LTA). Early commissioning of the Project will be allowed solely at the risk and cost of the WPD, and SECI shall purchase the energy from such early commissioned Project at the PPA tariff, only in case the Discom agrees to purchase power from the Project at an earlier date, and at the PPA tariff plus trading margin. In cases of early (part or full) commissioning, the WPD shall be required to intimate SECI its proposed date of early commissioning not later than 60 days prior to the proposed commissioning date. SECI shall respond to the WPD not later than 30 days from receipt of the above intimation, regarding its acceptance or refusal to purchase such power from the proposed early commissioning date. In case SECI does not agree to purchase such energy, early part/full commissioning of the Project shall still be allowed and the WPD will be free to sell such energy to a third party; subject to operationalization of LTA, until SCD or the date of commencement of procurement of power from the Project as notified by SECI, whichever is earlier. COD of the Project under the PPA will be declared from the date of commencement of procurement of energy from the Project by SECI.
AutoNDA by SimpleDocs
Early Commissioning. The SPD shall be permitted for full commissioning as well as part commissioning of the Project even prior to the SCD. In cases of early part-commissioning, till the SCD, the procurer may purchase the generation @ 75% (seventy-five per cent) of the PPA tariff. However, in case the entire capacity is commissioned prior to the scheduled commissioning date, the procurer may purchase the generation at PPA Tariff.
Early Commissioning. The BESSD shall be permitted for full commissioning as well as partcommissioning of the Project even prior to the Scheduled Commissioning Date. Early commissioning of the Project will be allowed solely at the risk and cost of the BESSD, and GUVNL may purchase the XXXX capacity from such early commissionedProject at BESPA tariff. Such intimation for early commissioning shall be provided to GUVNL at least 15 days before the proposed early commissioning date as per the Commissioning Procedure. In case there is no response provided by GUVNL within 7 days from the receipt of such intimation, such early commissioned capacity shall be deemed to have been rejected by GUVNL. In case GUVNL does not agree to purchase such capacity, early part/full commissioning of the Project shall still be allowed and the BESSD will be free to sell such capacity to a third party at its own risk and cost; until SCD or the date of commencement of procurement of XXXX Capacity notified by GUVNL, whichever is earlier. In such cases, a Provisional Commissioning Certificate will be issued to BESSD for period up to SCD or date of commencement of Storage Capacity Procurement (whichever is earlier), along with a NOC for sale of Storage Capacity to 3rd Party for such period. UCOD/COD of the Project under the BESPA will be the date on which the commissioning certificate is issued upon successful commissioning of the part/full capacity of the Project. Subject to the provisions of this Agreement, in case of earlycommissioning, if BESSD sells any capacity to a third party, the BESSD will have to again demonstrate 100% of Contracted Capacity (as per the Commissioning Procedure) to the Procurer from the date of commencement of off-take of capacity by the Procurer.
Early Commissioning. The HPD shall be permitted for full commissioning as well as part commissioning of the Project even prior to the Scheduled Commissioning Date, subject to availability of transmission connectivity and Long-Term Access (LTA). Early commissioning of the Project will be allowed solely at the risk and cost of the HPD, and SECI shall purchase the energy from such early commissioned Project at the PPA tariff, only in the case Discom agrees to purchase power from the Project at an earlier date, and at the PPA tariff plus trading margin. Such intimation for early commissioning shall be provided to SECI at least 60 days prior to the proposed early commissioning date. In case there is no response provided by SECI within 30 days from the receipt of such intimation, such early commissioned capacity shall be deemed to have been refused by SECI. In case SECI does not agree to purchase such energy, early part/full commissioning of the Project shall still be allowed and the HPD will be free to sell such energy to a third party; subject to operationalization of LTA, until SCD or the date of commencement of procurement of power from the Project as notified by SECI, whichever is earlier. In such cases a Provisional Commissioning Certificate will be issued to SPD for period up to SCD or date of commencement of Power Procurement (whichever is earlier), along with a NOC for sale of Power to 3rd Party for such period. COD of the Project under the PPA will be declared from the date of commencement of procurement of energy from the Project by SECI.
Early Commissioning. The Power Producer shall be permitted for full commissioning as well as part commissioning of the Project even prior to the SCOD ) subject to availability of transmission connectivity and Long Term Access (LTA). In cases of early part-commissioning, till SCOD, TPL-D shall reserve the right to purchase the generation till SCOD, at 75% (seventy-five per cent) of the tariff as per clause 5.2 of this PPA. However, in case the entire capacity is commissioned prior to SCOD, TPL may purchase the generation at the Tariff as per clause 5.2.
Early Commissioning. Early commissioning of the Project will be allowed solely at the risk and cost of the HPD, and SECI shall purchase the energy from such early commissioned Project at the PPA tariff, only in the case Discom agrees to purchase power from the Project at an earlier date, and at the PPA tariff plus trading margin. Such intimation for early commissioning shall be provided to SECI at least 60 days before the proposed early commissioning date. In case there is no response provided by SECI within 30 days from the receipt of such intimation, such early commissioned capacity shall be deemed to have been rejected by SECI.
Early Commissioning. The SPD shall be permitted for full commissioning as well as part commissioning of the Project even prior to the Scheduled Commissioning Date, subject to availability of transmission connectivity and Long-Term Access (LTA). Early commissioning of the Project will be allowed solely at the risk and cost of the SPD, and SECI shall purchase the energy from such early commissioned Project at the 75% (seventy-five percent) of the PPA tariff, only in the case Discom agrees to purchase power from the Project at an earlier date, and at 75% of the PPA tariff plus trading margin. Such intimation for early commissioning shall be provided to SECI at least 15 days before the proposed early commissioning date. In case there is no response provided by SECI within 7 days from the receipt of such intimation, such early commissioned capacity shall be deemed to have been rejected by SECI. In case SECI does not agree to purchase such energy, early part/full commissioning of the Project shall still be allowed and the SPD will be free to sell such energy to a third party; subject to operationalization of LTA, until SCD or the date of commencement of procurement of power from the Project as notified by SECI, whichever is earlier. UCOD/COD of the Project under the PPA will be the date on which the commissioning certificate is issued upon successful commissioning of the part/full capacity of the Project.
AutoNDA by SimpleDocs
Early Commissioning. The SPD shall be permitted for full commissioning as well as part commissioning of the Project even prior to the Scheduled Commissioning Date, subject to availability of transmission connectivity and General Network Access (GNA). Early commissioning of the Project will be allowed solely at the risk and cost of the SPD, and SECI shall purchase the energy from such early commissioned Project at the 75% (seventy-five percent) of the PPA tariff, only in the case Discom agrees to purchase power from the Project at an earlier date, and at 75% of the PPA tariff plus trading margin. However, in case the entire capacity is commissioned prior to SCD, SECI may purchase the generation at PPA Tariff, only in the case the Discom agrees to purchase power from the Project at an earlier date, and at the PPA tariff plus trading margin. While calculating the above value of 75% of the PPA tariff, the digits after 2 decimal places will be ignored. For eg., in case the value of 75% of the PPA tariff is calculated as 2.4567/kWh, the tariff applicable for purchase in case of early commissioning will be read as Rs. 2.45/kWh. Such intimation for early commissioning shall be provided to SECI at least 15 days before the proposed early commissioning date. In case there is no response provided by SECI within 7 days from the receipt of such intimation, such early commissioned capacity shall be deemed to have been rejected by SECI. In case SECI does not agree to purchase such energy, early part/full commissioning of the Project shall still be allowed and the SPD will be free to sell such energy to a third party; subject to operationalization of GNA, until SCD or the date of commencement of procurement of power from the Project as notified by SECI, whichever is earlier. In such cases, a Provisional Commissioning Certificate will be issued to SPD for period up to SCD or date of commencement of Power Procurement (whichever is earlier), along with a NOC for sale of Power to 3rd Party for such period. UCOD/COD of the Project under the PPA will be the date on which the commissioning certificate is issued upon successful commissioning of the part/full capacity of the Project.
Early Commissioning. The Power Producer shall be permitted for full commissioning as well as part commissioning of the Project even prior to the SCSD, subject to the availability of transmission connectivity and long term access (LTA). In case of early part commissioning, the Procurer may purchase the generation at the PPA tariff.
Early Commissioning. The Power Producer shall be permitted for full commissioning as well as part commissioning of the Project even prior to the SCOD (Schedule Commercial Operation Date). In cases of early part- commissioning, till SCOD, GUVNL shall reserve the right to purchase the generation till SCOD, as per Schedule 4. However, in case the entire capacity is commissioned prior to SCOD, GUVNL may purchase the energy supplied during the Peak Hours and Off-Peak Hours respectively as specified under Schedule 4.