Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-Builder’s job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder shall nevertheless maintain complete documentation of the costs. An executed Release of Liens and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 9 contracts
Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-Builder’s 's job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder shall nevertheless maintain complete documentation of the costs. An executed Release of Liens and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 6 contracts
Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-Builder’s job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder shall nevertheless maintain complete documentation of the costs. An executed Release of Liens ▇▇▇▇▇ and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 6 contracts
Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-BuilderContractor’s job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder Contractor shall nevertheless maintain complete documentation of the costs. An executed Release of Liens ▇▇▇▇▇ and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 4 contracts
Sources: Construction Management Agreement, Construction Management Agreement, Construction Management at Risk Services Agreement
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-Builder’s job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder shall nevertheless maintain complete documentation of the costs. An executed Release of Liens and Claims in the format required by the Contracting Officer CO must accompany each Application for Payment.
Appears in 3 contracts
Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-BuilderConstruction Manager’s job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder Construction Manager shall nevertheless maintain complete documentation of the costs. An executed Release of Liens and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 3 contracts
Sources: Construction Management at Risk Agreement, Construction Management at Risk Agreement, Construction Management at Risk Agreement
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-Builder’s job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Design- Builder shall nevertheless maintain complete documentation of the costs. An executed Release of Liens ▇▇▇▇▇ and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 1 contract
Sources: Design Build Agreement
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-Builder’s 's job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder shall nevertheless maintain complete documentation of the costs. An executed Release of Liens ▇▇▇▇▇ and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 1 contract
Sources: Design Build Agreement
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-BuilderConstruction Manager’s job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder Construction Manager shall nevertheless maintain complete documentation of the costs. An executed Release of Liens ▇▇▇▇▇ and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 1 contract
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-Builder’s Construction Manager's job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder Construction Manager shall nevertheless maintain complete documentation of the costs. An executed Release of Liens and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 1 contract
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-BuilderContractor’s job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder Contractor shall nevertheless maintain complete documentation of the costs. An executed Release of Liens and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 1 contract
Documents Required with Application for Payment. Each Application for Payment shall be accompanied by the Design-Builder’s Contractor 's job cost ledgers in a form satisfactory to the Department, the Subcontractors’ and Suppliers’ Applications for Payment on AIA Documents G702 and G703 or other form acceptable to the Department, and such other supporting documentation as the Department may reasonably request. Each Application for Payment shall include detailed documentation of costs as a condition to approving progress payments, but the Design-Builder Contractor shall nevertheless maintain complete documentation of the costs. An executed Release of Liens and Claims in the format required by the Contracting Officer must accompany each Application for Payment.
Appears in 1 contract
Sources: Construction Services Agreement