DOCUMENTS AND SAMPLES AT THE SITE Sample Clauses

DOCUMENTS AND SAMPLES AT THE SITE. 4.11.1 The Contractor shall maintain at the site for the State one record copy of all Drawings, Specifications, Addenda, Change Orders and other modifications, in good order and marked currently to record all changes made during construction, and approved Shop Drawings, Product Data and Samples. These shall be available to the Architect and the State for monthly review prior to approval of Contractor’s monthly application for payment. Prior to substantial completion of the Work, the Contractor shall ensure that one record copy of all Drawings, Specifications, Addenda, Change Orders and other Modifications, in good order and marked currently to record all changes made during construction, and approved Shop Drawings, Product Data and Samples are delivered to the Architect for the State and a duplicate copy shall be delivered to the State for the State’s use.
AutoNDA by SimpleDocs
DOCUMENTS AND SAMPLES AT THE SITE. 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the drawings, Specifications, addenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work.
DOCUMENTS AND SAMPLES AT THE SITE. The Contractor shall maintain at the site for the Owner on copy of the Drawings, Specifications, Addenda, Change Orders and other Modifications, in good order and marked currently to indicate field changes and sections made during construction, and one copy of the approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Architect and shall be delivered to the Architect for submittal to the Owner upon completion of the Work as a record of the Work as constructed.
DOCUMENTS AND SAMPLES AT THE SITE. The Contractor shall make available, at the Project site, the Contract Documents, including Change Orders, Construction Change Directives, and other Modifications, in good order and marked currently to indicate field changes and selections made during construction, and the approved Shop Drawings, Product Data, Samples, and similar required submittals. These shall be in electronic form or paper copy, available to the Architect and Owner, and delivered to the Architect for submittal to the Owner upon completion of the Work as a record of the Work as constructed.
DOCUMENTS AND SAMPLES AT THE SITE. A.3.10.1 The Design-Builder shall maintain at the site for the Owner one record copy of the drawings, specifications, addenda, Change Orders and other Modifications, in good order and marked currently to record field changes and selections made during construction, and one record copy of approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be delivered to the Owner upon completion of the Work.
DOCUMENTS AND SAMPLES AT THE SITE. The Contractor shall make available, at the Project site and updated at least weekly, the Contract Documents, including Change Orders, Construction Change Directives, and other Modifications, in good order and marked currently to indicate field changes and selections made during construction, and otherwise marked to depict the as-built nature and configuration of the Work and the approved Shop Drawings, Product Data, Samples, and similar required submittals. Contractor also shall maintain at the Project site for the Owner and the Architect one current copy of all subcontracts with Subcontractors, RFIs, Requests For Change Proposals and Change Proposals. These shall be in electronic form or paper copy, available to the Architect and the Owner, and delivered to the Architect for submittal to the Owner no later than, and as a condition of, Final Completion of the Work as a record of the Work as constructed.
DOCUMENTS AND SAMPLES AT THE SITE. 3.16.1 The Construction Manager shall:
AutoNDA by SimpleDocs
DOCUMENTS AND SAMPLES AT THE SITE. The Contractor shall maintain at the Site for the Owner one applicable copy of Titles 19 and 24 and a record copy of the Drawings, specifications, Addenda, Change Orders, and other modifications, in good order and marked currently to record changes and selections made during construction. In addition, the Contractor shall maintain at the Site approved Shop Drawings, Engineering Documents, Samples, and similar required submittals.
DOCUMENTS AND SAMPLES AT THE SITE. 3.16.1 Contractor shall maintain at the Site (or such other place as approved by MSG) up-to-date copies of: (a) all contracts entered into by Contractor for the Work (including this Agreement, all purchase orders, and all Subcontracts); (b) all Drawings, Specifications, Construction Change Directives, and Change Orders in good order and marked to record all changes made during construction; (c)
DOCUMENTS AND SAMPLES AT THE SITE. 4.9.1 The Contractor shall maintain at the site for the Owner and Architect one copy of all Drawings, Specifications, Addenda, approved Shop Drawings, Product Data and Samples, Change Orders and other Modifications in good order. These shall be available to the Owner and Architect.