Detailed Schedule Sample Clauses

Detailed Schedule. If requested by Tervita, the Contractor shall submit a detailed schedule of the Work. Such detailed schedule by the Contractor shall be in a form acceptable to Tervita, and shall indicate key delivery dates and interrelationships with the work of others. The Contractor’s detailed schedule shall be monitored and updated by the Contractor when requested by Tervita. If the Contractor is not making sufficient progress in the performance of the Work and thereby is causing or threatening to cause delay in the general progress of the Project, the Contractor will be in Default under this Agreement.
AutoNDA by SimpleDocs
Detailed Schedule. Although the City does not have the right to approve Licensee's schedule, Licensee shall, upon request, provide the City with a detailed and accurate schedule of their operations, understanding that the schedule is always subject to change. If the City has a permitted event or construction that is taking place in its infrastructure that will be affected by Licnesee's schedule, then the City has the right to deny Licensee the right to use the Premises to the extent that the conflict exists.
Detailed Schedule. Within seven (7) days of the issuance of a Notice to Proceed for Design and Preconstruction Phase, the Design-Builder shall submit to the Department for its approval an updated schedule of the Design and Preconstruction Phase as well as the Construction Phase of the Project (the “Project Schedule”). Such schedule shall include a schedule for submittals that is reasonably acceptable to the Department. During the Preconstruction Phase, the Design-Builder shall monitor the Project’s progress and promptly notify the Department of any
Detailed Schedule. .1 Deadline: No later than ten [10] working days following award.
Detailed Schedule. Description of task Deliverables and Deadlines Payable Fee - up to EUR xxx o up to EUR xxxx
Detailed Schedule. Note, approximate schedule included for example purposes only. Actual schedule will be determined in collaboration between BS&A Project Manager, and Customer, following contract execution. Task Responsible Parties (Bold is Primary) Start Duration Initiation Activities Conduct Kick-off Meeting BS&A and City 1 month post signing 1 day Review Project Scope and Project Management Process BS&A 1 month post signing 1 day Establish Project Meeting Schedule BS&A and City 1 month post signing 1 day Assemble BS&A Project Team BS&A 1.5 months post signing 1 day Assemble City Project Team City 1.5 months post signing 1 day Create Initial Project Timeline BS&A & City 1.5 months post signing 1 day IT and Data Conversion Activities Meet with City IT Staff to review Hardware Configurations BS&A and City 5 months pre go-live 1 day Extract Preliminary Data from current System BS&A and City 5 months pre go-live 1 week Conduct Data Mapping and Develop Data Conversion Routines BS&A 5 months pre go-live 1 month Conduct Review of Converted Data with City BS&A and City 4 months pre go-live Approx 1 day Install Programs BS&A 4 months pre go-live 1 day Knowledge Transfer Conduct On-site Process Review Meeting BS&A and City 3 months pre go-live 2 days Conduct Analysis of Current Forms BS&A and City 3 months pre go-live 1 day Conduct Review of Required Reports BS&A and City 3 months pre go-live 1 day Conduct Analysis of System Interface Requirements BS&A and City 3 months pre go-live 1 day Develop Best Practices Recommendation BS&A 3 months pre go-live 1 day Approve Recommendations City 3 months pre go-live 1 day Provide Consulting and Assistance with Chart of Account Redesign BS&A 3 months pre go-live 1 day Create System Specification Document BS&A 3 months pre go-live 3 days Implementation Create Forms BS&A 0-2 months pre go-live 2 days Create Reports BS&A 0-2 months pre go-live 2 days Conduct Acceptance Testing City 0-2 months pre go-live 2 days Conduct Final Data Extraction City 1 week pre go-live 2 days Convert Final Data BS&A 1 week pre go-live 2 days On-site Set-up for Users and Configuration Items BS&A 0-1 month pre go-live 4 days Training On-site Training BS&A and City 0-2 months pre go-live Varies Post-Project Activities Conduct Post Project Review & Assessment BS&A and City 1 month post go-live Varies Conduct Post Implementation Follow Up Training BS&A and City XXX XXX ID Task Name Duration Predecessor Finish Resource Names Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 28 Esta...
Detailed Schedule. Within seven (7) days of the issuance of a Notice to Proceed for Preconstruction Phase, the Contractor shall submit to the Department for its approval a schedule of Project. Such schedule shall include a schedule for submittals that is reasonably acceptable to the Program Manager.
AutoNDA by SimpleDocs
Detailed Schedule. The Contractor shall furnish the Agency a cost break-down for all contract lump sum items. Cost break-down tables shall be submitted to the Agency Representative for acceptance within fifteen (15) days after award of Contract. Cost break-down tables will be approved, in writing, by the Agency Representative before any partial payment will be made for the applicable items involved. The Contractor shall determine the quantities required to complete the Work shown on the Plans. The quantities and their values shall be included in the cost break-downs submitted to the Agency Representative for approval. The Contractor shall be responsible for the accuracy of the quantities and values used in the cost break-downs submitted for approval. The sum of the amounts for the line items of work listed in each cost break-down table for each lump sum item shall be equal to the contract lump sum price bid. Overhead and profit shall be included in each individual line item of work listed in a cost break-down table. No adjustment in compensation will be made in the contract lump sum prices due to differences between the quantities shown in the cost break-downs furnished by the Contractor and the quantities required to complete the Work as shown on the plans and as specified in the Special Provisions. Individual line item values in the approved cost break-down tables will be used to determine partial payments during the progress of the Work and as the basis for calculating an adjustment in compensation for the contract lump sum items due to changes in line items of work ordered by the Engineer. When the total of ordered changes to line items of work increases or decreases the lump sum price bid by more than twenty-five percent , the adjustment in compensation for the applicable lump sum item will be determined in the same manner specified for increases and decreases in the total pay quantity of an item of work in Section 3 of the Standard Specifications and the Special Provisions.
Detailed Schedule. Developer and City shall jointly meet and agree, in good faith, on a detailed construction schedule so that the Project and the improvements to be constructed in accordance with this Agreement, as well as the other components of the Xxxxxxxx Square Project are coordinated in timing and phasing. It is the intent of the Developer to instruct the architects to proceed on said construction documents for the Hotel as soon as requested by City and prior to City achieving all conditions precedent set forth in Sections 1.06 and 1.07. In consideration of Developer proceeding forward with the plans to develop the Hotel prior to such time as the City has fulfilled all of its obligations and the conditions precedent set forth in Sections 1.06 and 1.07 above, the City agrees to reimburse Developer for Developer's out of pocket costs and expenses incurred in connection with proceeding with the development of the design and construction documents for the Hotel, as well as all other costs and expenses incurred in connection with advancing the proposed development of the Hotel in the event the City fails to timely fulfill its obligations under Sections 1.06 or 1.07 hereof due to reasons other than a Developer Event of Default. However, any such reimbursement shall be limited to the sum of One Hundred Thousand Dollars ($100,000), unless the City issues a "Notice to Proceed" to Developer requesting that it proceed to prepare construction documents for the Hotel, in which case the reimbursement obligation shall increase by Four Hundred Thousand Dollars ($400,000) for a total of Five Hundred Thousand Dollars ($500,000). The parties further acknowledge that in the event the City is unable to meet the Project Schedule set forth above, the Developer and the City will agree to extend the Project Schedule on a day for a day basis; however, the parties recognize that it is not economically feasible for the Developer to open the Hotel in the months of October through February and, therefore, in certain instances delays by the City may require extensions to the Project Schedule greater than a day for day extension.
Detailed Schedule. A detailed schedule (the “Detailed Schedule”) shall be developed and maintained by Bacthera its Affiliates and/or subcontractors and revised and updated not less than monthly or as otherwise agreed by the Parties. The Detailed Schedule shall include all applicable milestones with respect to the construction, completion and commissioning of the Facility. The Detailed Schedule shall incorporate and be consistent with the milestones and milestone dates above. The Key Deliverables shall be achieved per the dates provided in Section 5.2 and the Key Milestones shall be achieved per the dates provided in Section 5.3. Bacthera shall cooperate with Seres in coordinating the execution of the Detailed Schedule. Bacthera its Affiliates and/or subcontractors shall incorporate all reasonable changes to the Detailed Schedule from Seres, after approval from JSC. Bacthera, its Affiliates and/or subcontractors will resubmit the Detailed Schedule for Seres’s review within [***] days of receipt of such comments from Seres.