Detailed Project Report (DPR) Sample Clauses

Detailed Project Report (DPR). 5.10.1 The Concessionaire shall, within 90 days of date of signing of the Agreement, prepare and submit, for review, comments and approval from the Authority and the Independent Engineer(s), a Detailed Project Report (“DPR”) for the Project. The DPR shall include, but not be limited to, the following:
AutoNDA by SimpleDocs

Related to Detailed Project Report (DPR)

  • Final Project Report Prepare a Final Project Report that addresses, to the extent feasible, comments made by the Grant Manager on the Draft Final Project Report. Submit one (1) reproducible master and an electronic copy of the final. Upload an electronic copy of the final report in pdf format to the FAAST system.

  • Project Reports 1. The Borrower shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 5.08 of the General Conditions and on the basis of the indicators agreed with the Bank. Each Project Report shall cover the period of one calendar semester, and shall be furnished to the Bank not later than one month after the end of the period covered by such report.

  • Project Reports; Completion Report 1. The Recipient shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 2.06 of the Standard Conditions and on the basis of indicators agreed with the World Bank. Each Project Report shall cover the period of one (1) calendar semester, and shall be furnished to the World Bank not later than one (1) month after the end of the period covered by such report.

  • Progress Report 10.1 If required, you shall submit progress reports in connection with the Service (“Report”) on at least a monthly basis, or as we may require. The Report shall include a summary of the activities and accomplishments during the previous reporting period.

  • Project Completion Report At the completion of construction and once a Project is placed in service, the Subrecipient must submit a Project Completion Report that includes the total number of units built and leased, affordable units built and leased, DR-MHP units built and leased, an accomplishment narrative, and the tenants names, demographics and income for each DR-MHP unit.

  • Monthly Progress Reports During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.

  • Monthly Progress Report This report shall include a description of the activities during the reporting period and the activities planned for the ensuing reporting period. The first reporting period consists of the first full month of performance plus any fractional part of the initial month. Thereafter, the reporting period shall consist of each calendar month. The Contractor shall submit a Monthly Progress Report on or before the 15th calendar day following the last day of each reporting period and shall include the following: Title Page: The title page for this report shall include the contract number and title; the type of report and period that it covers; the Contractor’s name, address, telephone number, fax number, and e-mail address; and the date of submission.

  • Detailed Monthly Report Vendor shall electronically provide DIR with a detailed monthly report in the format required by DIR showing the dollar volume of any and all sales under the Contract for the previous calendar month period. Reports are due on the fifteenth (15th) calendar day of the month following the month of the sale. If the 15th calendar day falls on a weekend or state or federal holiday, the report shall be due on the next business day. The monthly report shall include, per transaction: the detailed sales for the period, Customer name, invoice date, invoice number, description, quantity, MSRP or List Price, unit price, extended price, Customer Purchase Order number, contact name, Customer’s complete billing address, the estimated administrative fee for the reporting period, subcontractor name, EPEAT designation (if applicable), configuration (if applicable), contract discount percentage, actual discount percentage, negotiated contract price (if fixed price is offered instead of discount off of MSRP), and other information as required by DIR. Each report must contain all information listed above per transaction or the report will be rejected and returned to the Vendor for correction in accordance with this section. Vendor shall report in a manner required by DIR which is subject to change dependent upon DIR’s business needs. Failure to do so may result in contract termination.

  • Project Reporting During the course of Implementation Services, the NAVITAIRE Hosted Revenue Accounting Services Project Manager will coordinate status reporting with the NAVITAIRE Hosted Reservation Services Project Manager. Following completion of installation of the Hosted Reservation Services, the NAVITAIRE Hosted Revenue Accounting Services Project Manager will provide Customer with status on the remaining Implementation Services for Hosted Revenue Accounting Services as follows; (a) Weekly Project Plan Update and Status Report; (b) Weekly Updated Issues/Resolution List; and (c) Executive Summary.

  • Progress Reports The Recipient shall submit to the OPWC, at the OPWC's request, summary reports detailing the progress of the Project pursuant to this Agreement and any additional reports containing such information as the OPWC may reasonably require.