Delays during construction. If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achieved, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion Schedule.
Appears in 6 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones Milestone or the Independent Engineer Monitor[s] shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achievedachieved by the Project Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer Monitor[s] in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Project Milestone or Project Completion Date indicated in Project Completion Scheduleas the case may be.
Appears in 4 contracts
Sources: Public Private Partnership Agreement, Public Private Partnership Agreement, Public Private Partnership Agreement
Delays during construction. 13.4.1 If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall Construction Supervisorshall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achieved, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer Construction Supervisor in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion Schedule.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achieved, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion Schedule.
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of or Construction Works is such that the Project Milestone [Four-Laning] is not likely to be achievedachieved by the Schedules Four-Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (( fifteen) days of such noticenotice , by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion ScheduleDate.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones Milestone or the Independent Engineer Expert shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achievedcompleted by the Project Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer Expert in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Project Milestone or Project Completion Date indicated in Project Completion Scheduleas the case may be.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achievedachieved by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion ScheduleDate.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire Concessionaire, does not achieve any of the Project Milestones or the Independent Engineer Consultant shall have reasonably determined that the rate of progress of Construction Works works is such that the Project Milestone is not likely to be achievedachieved by the Scheduled Project Date, it shall notify the Concessionaire to this effect, effect and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer Consultant in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion ScheduleDate.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. 13.4.1 If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achieved, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion Schedule.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones Milestone or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achievedachieved by the Project Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Project Milestone or Project Completion Date indicated in Project Completion Scheduleas the case may be.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones project milestones or the Independent Engineer Supervision Committee shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achievedcompleted by the Scheduled Completion Date or Scheduled Phase Completion Date, as the case may be, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer Supervision Committee in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion ScheduleDate.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone completion is not likely to be achievedachieved by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion ScheduleDate.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer Engineer-in-charge of the Authority shall have reasonably determined that the rate of progress of Construction Works is such that the Project Milestone is not likely to be achievedcompleted by the Scheduled Completion Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer Engineer-in- charge in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion ScheduleDate.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones or the Independent Engineer shall have reasonably determined that the rate of progress of or Construction Works is such that the Project Milestone Four-Laning is not likely to be achievedachieved by the Scheduled Four-Laning Date, it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (( fifteen) days of such noticenotice , by a communication inform the Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled Completion Date indicated in Project Completion ScheduleDate.
Appears in 1 contract
Sources: Concession Agreement
Delays during construction. If the Concessionaire does not achieve any of the Project Milestones project milestones or the Independent Engineer Supervision Committee shall have reasonably determined that the rate of progress of Construction Works ConstructionWorks is such that the Project Milestone is not likely to be achieved, completed by the Scheduled Completion Date it shall notify the Concessionaire to this effect, and the Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Independent Engineer Supervision Committee in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Scheduled theProject Completion Date indicated in Project Completion ScheduleDate.
Appears in 1 contract
Sources: Concession Agreement