Common use of Delays during construction Clause in Contracts

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 123 contracts

Sources: Contract Agreement, Construction Contract, Engineering Procurement and Construction Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 37 contracts

Sources: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 27 contracts

Sources: Engineering Procurement and Construction (Epc) Agreement, Contract Agreement, Contract Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.3.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway is not likely to be achieved completed by the end of the Scheduled Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 18 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones within the time period stipulated in Schedule-I or the Authority’s Authority Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Railway Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Authority Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 8 contracts

Sources: Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement, Engineering, Procurement and Construction (Epc) Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 8 contracts

Sources: Construction Contract, Construction Contract, Engineering Procurement and Construction (Epc) Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones within the time period stipulated in Schedule - I or the Authority’s Authority Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Authority Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 8 contracts

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Authority‟s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Authority‟s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 6 contracts

Sources: Engineering, Procurement and Construction Agreement, Construction Contract, Epc Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), in 12.3.2 if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of the Construction Works is such that Completion of the Project Highway is not likely to be achieved completed by the end of the Scheduled Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 4 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.3.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion commissioning of the Project Highway XXX Ropeway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Sources: Model Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), in the event the Contractor does not achieve any of the Project Milestones or the Authority’s 's Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s 's Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Sources: Construction Contract, Construction Contract, Construction Contract

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones within the time period stipulated in Schedule - I or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Railway Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Project Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Project Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), 10.3.2 in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Employer's Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway Works is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Employer's Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Sources: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.2.2, in if the event the Contractor Implementation Agency does not achieve any of the Project Milestones or the Authority’s Engineer Project Consultant or the Authority shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway is not likely to be achieved completed by the end of the Scheduled Completion Date, it shall notify the same Implementation Agency to the Contractorthis effect, and the Contractor Implementation Agency shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer Authority and the Project Consultant in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 3 contracts

Sources: Development, Operation and Maintenance Agreement, Development, Operation and Maintenance Agreement, Development, Operation and Maintenance Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), 10.3.2 in the event the Contractor does not achieve any of the Project Milestones or the AuthorityEmployer’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway Works is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the AuthorityEmployer’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Sources: Demonstration Agreement, Epc Agreement, Contract Agreement for Design and Construction

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.3.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Engineer Independent Expert shall have reasonably determined that the rate of progress of Construction Works is such that Completion completion of the Project Highway Storage Facility is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer Independent Expert in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 3 contracts

Sources: Concession Agreement, Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway [Six-Laning] is not likely to be achieved by the end of the Scheduled Completion [Six-Laning] Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 2 contracts

Sources: Model Concession Agreement, Model Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)14.5.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway completion is not likely to be achieved by the end of the Scheduled Project Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 2 contracts

Sources: Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.3.2, in if the event the Contractor Concessionaire does not achieve any of the project milestones set forth in the Project Milestones Facility Completion Schedule or the Authority’s Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway is they are not likely to be achieved completed within the time specified by the end of the Scheduled Completion DateEngineer, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Datecompletion.

Appears in 2 contracts

Sources: Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway Foot track is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 2 contracts

Sources: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones within the time period stipulated in Schedule - I or the Authority’s Authority Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Railway Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Authority Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 2 contracts

Sources: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones within the time period stipulated in Schedule I or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 2 contracts

Sources: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.. 48

Appears in 2 contracts

Sources: Draft Contract Agreement, Contract Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion implementation of the Project Highway is not likely to be achieved by the end of the Scheduled Project Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 2 contracts

Sources: Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway Six-Laning is not likely to be achieved by the end of the Scheduled Completion Six-Laning Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 2 contracts

Sources: Concession Agreement, Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.2.1, in if the event the Contractor Developer does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion completion of the Project Highway construction work is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same Developer to the Contractorthis effect, and the Contractor Developer shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Development Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway Two-Laning is not likely Hkely to be achieved by the end of the Scheduled Completion Two-Laning Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)7 .3, in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Project Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion DateConstruction Period, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Project Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Epc Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones or the Authority’s AUTHORITY’S/GMDAs Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway PROJECT is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s AUTHORITY’S/GMDAs Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Engineering Procurement and Construction Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones within the time period stipulated in Schedule - I or the Authority’s Authority Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the DFCCIL Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Authority Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Engineering, Procurement and Construction (Epc) Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Project Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Project Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway Four-Laning with paved shoulders is not likely to be achieved by the end of the Scheduled Completion Four-Laning with paved shoulders Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), 10.3.2 in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Employer‟s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway Works is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Employer‟s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Epc Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway Intermediate-laning/Two-Laning is not likely to be achieved by the end of the Scheduled Completion Intermediate-laning/Two-Laning Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Authority‟s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Authority‟s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Engineering Procurement and Construction Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway Two- Laning is not likely to be achieved by the end of the Scheduled Completion Two - Laning Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), 10.3.2 in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Epc Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)11.3.2, in the event the Contractor Concessionaire does not achieve any of the Project Milestones within the time period stipulated in Schedule-H or the Authority’s Authority‟s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Railway Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the ContractorConcessionaire, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Authority‟s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii10.3.(ii), in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Engineering Procurement and Construction Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Draft Agreement for RFP for Beautification of Streets

Delays during construction. Without prejudice to the provisions of provisionsof Clause 10.3 (ii), in the event the Contractor does Contractordoes not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably havereasonably determined that the rate of progress of Works is such that Completion of the ofthe Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall itshall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable fifteen)daysofsuchnotice,byacommunicationinformtheAuthority’sEngineerinreasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Datetheperiodwithinwhichitshallachievethe ProjectCompletionDate.

Appears in 1 contract

Sources: Construction Contract

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones within the time period stipulated in Schedule I or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Railway Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Engineering, Procurement and Construction (Epc) Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.3.2, in the event if the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer Engineer-in charge shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway is not likely to be achieved completed by the end of the Scheduled Completion Date, it shall notify the same Contractor to the Contractorthis effect, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer Engineer-in-charge in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion DateCOD.

Appears in 1 contract

Sources: Contract Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway Two- Laning is not likely to be achieved by the end of the Scheduled Completion Two-Laning Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway Two-Laning is not likely to be achieved by the end of the Scheduled Completion Two-Laning Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)11.3.2, in the event the Contractor Concessionaire does not achieve any of the Project Milestones within the time period stipulated in Schedule-H or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Railway Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the ContractorConcessionaire, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii), in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Engineer shall have reasonably reasona- ▇▇▇ determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Construction Contract

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.4.2, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Independent Engineer shall have reasonably determined that the rate of progress of Construction Works is such that Completion of the Project Highway Heliport is not likely to be achieved completed by the end of the Scheduled Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Independent Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones or the Authority’s Authority‟s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Authority‟s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Epc Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)12.6.1, in if the event the Contractor Concessionaire does not achieve any of the Project Milestones or the Authority’s Engineer Independent Expert shall have reasonably determined that the rate of progress of Construction Works is such that Completion completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same Concessionaire to the Contractorthis effect, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer Independent Expert in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Milestone or Project Completion Date, as the case may be.

Appears in 1 contract

Sources: Model Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)11.3.2, in the event the Contractor Concessionaire does not achieve any of the Project Milestones within the time period stipulated in Schedule -H or the Authority’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the ContractorConcessionaire, and the Contractor Concessionaire shall, within 15 (fifteen) days of such notice, by a communication inform the Authority’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Concession Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones within the time period stipulated in Schedule - I or the AuthoritySPV’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Railway Project Highway is not likely to be achieved by the end of the Scheduled Completion Date, it shall may notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the AuthoritySPV’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Epc Agreement

Delays during construction. Without prejudice to the provisions of Clause 10.3 (ii)10.3.2, in the event the Contractor does not achieve any of the Project Milestones or the AuthorityEmployer’s Engineer shall have reasonably determined that the rate of progress of Works is such that Completion of the Project Highway Works is not likely to be achieved by the end of the Scheduled Completion Date, it shall notify the same to the Contractor, and the Contractor shall, within 15 (fifteen) days of such notice, by a communication inform the AuthorityEmployer’s Engineer in reasonable detail about the steps it proposes to take to expedite progress and the period within which it shall achieve the Project Completion Date.

Appears in 1 contract

Sources: Epc Contract