Common use of Delay Liquidated Damages Clause in Contracts

Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for (i) Delay Liquidated Damages for Subproject 1 is *** U.S. Dollars (U.S.$***), in the aggregate, and (ii) Delay Liquidated Damages for Subproject 2 is *** U.S. Dollars (U.S.$***), in the aggregate.

Appears in 4 contracts

Sources: Fixed Price Separated Turnkey Agreement (Cheniere Energy Inc), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC)

Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for (i) Delay Liquidated Damages for Subproject 1 3 is *** U.S. Dollars (U.S.$***), in the aggregate, and (ii) Delay Liquidated Damages for Subproject 2 4 is *** U.S. Dollars (U.S.$***), in the aggregate.

Appears in 3 contracts

Sources: Lump Sum Turnkey Agreement, Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.)

Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for (i) Delay Liquidated Damages for Subproject 1 is *** U.S. Dollars (U.S.$***), in the aggregate, and (ii) Delay Liquidated Damages for Subproject 2 5 is *** U.S. Dollars (U.S.$***), in the aggregate.

Appears in 1 contract

Sources: Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.)

Delay Liquidated Damages. Subject to Section 20.2C, Contractor’s maximum liability to Owner for (i) Delay Liquidated Damages for Subproject 1 is *** One Hundred Sixty-Six Million U.S. Dollars (U.S.$***U.S.$166,000,000), in the aggregate, and (ii) Delay Liquidated Damages for Subproject 2 is *** Eighty-Three Million U.S. Dollars (U.S.$***U.S.$83,000,000), in the aggregate.

Appears in 1 contract

Sources: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC)