Date of Final Completion Sample Clauses

Date of Final Completion. Contractor shall achieve Substantial Completion of the Work under this Contract within ( ) consecutive calendar days ("Contract Time") from the date of Substantial Completion, subject to adjustments of this Contract Time as provided in the Contract Documents.
AutoNDA by SimpleDocs
Date of Final Completion. The Contractor shall achieve Final Completion of its Work on the Project, as defined in the General Conditions, within 30 calendar days of the Date of Substantial Completion (“Date of Final Completion”). Final Completion shall mean that the Work is complete in accordance with the Contract Documents and the Contractor has submitted to the Owner or Engineer all documents required to be submitted to the Owner or Engineer for final payment.
Date of Final Completion. The date certified by the Owner/Architect as the date upon which the Work is completely finished, which event shall be achieved by the Contractor within the time period specified in Schedule of Completion. Work consisting of the completion of punch-list items, submission of O&M Manuals, any and all other Contract requirements being completed by the Contractor.
Date of Final Completion. The Date of Final Completion of the Work is: [ ] or within [ ] ([ ]) Days after the Date of Substantial Completion, subject to adjustments as provided for in the Contract Documents. This Amendment is entered into as of [ ]. EXHIBIT C-LEED RESPONSIBILITIES
Date of Final Completion. When the Contractor believes that his work is completed, he shall request that the Engineer and the Owner inspect the work and certify its completion. The Engineer and the Owner will respond promptly to such a request. The date of final completion of the work or any designated portion thereof is the date on which, after the Engineer and the Owner certifies that construction has been completed in accordance with the contract documents, the Owner accepts the work.
Date of Final Completion or “Final Completion”: The date upon which all Work has been completed to HFH’s satisfaction and is certified by HFH to be at Final Completion.
Date of Final Completion. The Date of Final Completion of the Work is: [ _] N/A or within [ ] sixty ([ _]) (60) Calendar Days after the Date of Substantial Completion, subject to adjustments as provided for in the Contract Documents. This Amendment is entered into as of [ ].March 24, 2015. ATTEST: OWNER: [ _]University of Washington BY: PRINT NAME [ ]Xxxxxxx Xxxxxxx PRINT TITLE [ ]Director, Capital Projects ATTEST: CONTRACTOR: [ ]Northwest Construction Company BY: PRINT NAME [ ]Xxx Xxxxxx PRINT TITLE [ ]Vice President
AutoNDA by SimpleDocs
Date of Final Completion. The date when Architect and Owner find all the work of the Contract documents acceptable and the Contract fully performed.
Date of Final Completion. The Date of Final Completion of the Work is: [ ] or within [ ] Days after the Date of Substantial Completion, subject to adjustments as provided for in the Contract Documents. This Amendment will become effective when all parties have signed it. The date of this Amendment will be the date this Amendment is signed by the last party to sign it (as indicated by the date associated with that party’s signature.) FOR THE UNIVERSITY SYSTEM OF NEW HAMPSHIRE OWNER CONSTRUCTION MANAGER «Name Title Campus» «Name Title Company» Date: Date: OWNER «Name Title Campus» Date: OWNER Xxxxxxxxx X. Xxxxxxxxxx Vice Chancellor for Financial Affairs & Treasurer University System of New Hampshire» Date:

Related to Date of Final Completion

  • DATE OF COMPLETION The Developer must ensure that the Developer’s Works reach Completion on or before the date or milestone referred to in clause 1 of Schedule 3 of this document.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: (Check one of the following boxes.) [ « » ] The date of this Agreement. [ « » ] A date set forth in a notice to proceed issued by the Owner. [ « » ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.) « » If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.

  • TIME OF COMPLETION The Owner shall issue a Notice to Proceed identifying the date for commencement of the Work. The commencement date shall be 10 or more days after the date the notice is issued. The Contractor shall achieve substantial completion of the Work within _____________________ (____) calendar days after the commencement date, as such completion date may be extended by approved Change Orders. The time set forth for completion of the Work is an essential element of the Contract.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.

  • TIME OF COMMENCEMENT AND COMPLETION 2.1 The Contractor shall commence the Work upon the date established in the Notice to Proceed.

  • Service Commencement Date The date the Transmission Provider begins to provide service pursuant to the terms of an executed Service Agreement, or the date the Transmission Provider begins to provide service in accordance with Section 15.3 or Section 29.1 under the Tariff.

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved.

Time is Money Join Law Insider Premium to draft better contracts faster.