Common use of Damages for delay Clause in Contracts

Damages for delay. Subject to the provisions of Clause 11.4, if COD does not occur prior to the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Construction Performance Security for delay of each day until COD is achieved. In the event that Construction Works is not completed within [270 (two hundred and seventy)] days from the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Authority shall be entitled to terminate this Agreement.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Damages for delay. Subject to the provisions of Clause 11.4, if COD does not occur prior to the Scheduled Schedule Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Construction Performance Security for delay of each day until COD is achieved. In the event that Construction Works is not completed within [270 (two hundred and seventy)] days from the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Authority shall be entitled to terminate this Agreement.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Damages for delay. Subject to the provisions of Clause 11.4, if COD does not occur prior to the Scheduled Schedule Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Construction Performance Security for delay of each day until COD is achieved. In the event that Construction Works is not completed within [270 (two hundred and seventy)] days from the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Authority shall be entitled to terminate this Agreement.

Appears in 1 contract

Samples: Concession Agreement