Coordination of Work Sample Clauses

Coordination of Work. Licensee shall be responsible for coordination of its Equipment installation work to avoid any interference with existing utilities, substructures, facilities and/or SFMTA transit operations. Licensee shall be the City's point of contact for all Equipment installation and except in case of emergency, all communications concerning Equipment installation shall be through Licensee's field representatives.
AutoNDA by SimpleDocs
Coordination of Work. The Contractor acknowledges that it is essential that all Work on projects and jobs be coordinated, including Work to be provided by Princeton University staff/employees. The Contractor shall be responsible for coordinating the Work of all its employees and Subcontractors as well as any Work to be provided by Princeton University.
Coordination of Work. Contractor shall perform the Work so as to minimize any impact upon the conduct of the business activities of MPTN. Contractor shall schedule the Work subject to the approval of MPTN.
Coordination of Work. The Company shall use its reasonable efforts to minimize the necessity for road cuts, construction and the placement of new Equipment Within the ROW by coordinating its Work and sharing the use of support structures with other existing and new occupants of the ROWs.
Coordination of Work. If the Contractor has one or more crews working in the Village, the Contractor shall also have a designated manager level or above representative in the Village and available as an emergency contact by mobile phone within thirty (30) minutes. The representative shall call and provide their name and cell phone number to the Village prior to the start of work. The representative shall have a complete working knowledge of the specifications of the Work included herein, oversee the work being performed by the Contractor’s crews, and meet weekly with a Village employee to inspect and sign-off on the work performed. In addition, the representative will also have full authority to:
Coordination of Work. Contractor shall be in charge of and responsible for the coordination, scheduling, performance and sequence of all elements of the work unless otherwise stated.
Coordination of Work. The Construction Manager acknowledges and understands that other contractor(s) may perform work on or around the Project. Construction Manager herein agrees to coordinate its work with other contractor(s) on the Project so as to not interfere with the other contractor(s) work and so as to insure that all predecessor work is completed and accepted before the commencement of the Work of the Construction Manager herein on any particular part of phase of the Work. For the purposes of this Agreement, "predecessor work' includes, without limitation, complete dry-in of the particular part or phase of the Project.
AutoNDA by SimpleDocs
Coordination of Work. Consultant shall be in charge of and responsible for the coordination, scheduling, performance and sequence of all elements of the work unless otherwise stated.
Coordination of Work. The Project Site(s) may be occupied and may operate on a twenty-four hour seven day a week schedule. Design-Build Firm shall ensure that the performance of the Work does not impact any ongoing operations at Project(s) site(s), which also includes the delivery of any materials and equipment. Access to and egress from the Project Site(s) shall be coordinated with the Project Manager to minimize interference to regular and emergency operations of the facility. During progress of Work under this Contract, it may be necessary for other Design-Build Firm’s and persons employed by the City to Work in or about the Project. The City reserves the right to put such other Design-Build Firm s to work and to afford such access to the Project site of the Work to be performed hereunder at such times as the City deems proper. If this Contract requires a portion of the Work to be tied into work done under other Contract(s), it will be necessary for Design-build Firm to plan its Work and cooperate with other Design-Build Firm s insofar as possible to prevent any interference and delay. The Design-build Firm shall not impede or interfere with the work of other Design-Build Firms engaged in or about the Work and shall so arrange and conduct its Work that such other Design-Build Firm s may complete their work at the earliest date possible.
Coordination of Work. KsFiberNet shall be responsible for coordination of work to avoid any interference with existing utilities, substructures, facilities and/or operations within the City’s ROW. KsFiberNet shall be the City’s point of contact and all communications shall be through KsFiberNet. KsFiberNet shall be solely responsible for communicating with Kansas One-Call.