Contractor Delay. If the Contractor is delayed in the performance of the Work by an act, error or omission of a Contractor Person, or by an event for which the Contractor is not expressly given relief under the Contract (“Contractor Delay”), then the Contractor will not be entitled to, nor will the Contractor make any claim for an adjustment of the Contract Price, reimbursement or payment from BC Hydro for any costs incurred by the Contractor or an extension of the time for the performance of the Work, in either case, as a result of a Contractor Delay.
Appears in 1 contract
Sources: Civil Works Contract
Contractor Delay. If the Contractor is delayed in the performance of the Work by an act, error its own acts or omission of a Contractor Personomissions, or by an event the acts or omissions of a Person for which whom the Contractor is not expressly given relief under the Contract in law responsible (“Contractor Delay”), then the Contractor will not be entitled to, nor will the Contractor make any claim for an adjustment of the Contract Price, reimbursement or payment from BC Hydro for any costs incurred by the Contractor or an extension of the time for the performance of the Work, in either case, as a result of a Contractor Delaysuch delay.
Appears in 1 contract
Sources: Main Civil Works Contract