Construction Timing. Unless otherwise mutually agreed to between the Parties, Interconnection Customer shall select the In-Service Date, Initial Synchronization Date, and target Commercial Operation Date. Such dates shall be set forth in Appendix B, Milestones.
Appears in 2 contracts
Sources: Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia)
Construction Timing. Unless otherwise mutually agreed to between the Parties, Interconnection Customer shall select the In-Service Date, Initial Synchronization Date, and target Commercial Operation Date. Such dates shall be set forth in Appendix B, Milestones. At the same time, Interconnection Customer shall also indicate whether it elects to exercise the Option to Build set forth in Article 5.1.3 below.
Appears in 2 contracts
Sources: Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia)
Construction Timing. Unless otherwise mutually agreed to between the Parties, Interconnection Customer shall select the In-Service Date, Initial Synchronization Date, and target Commercial Operation Date. Such dates shall be set forth in Appendix B, Milestones. At the same time, Interconnection Customer shall indicate whether it elects to exercise the Option to Build set forth in Article 5.1.3 below.
Appears in 1 contract
Sources: Standard Generator Interconnection Agreement (Sgia)