{"component": "clause", "props": {"groups": [{"snippet": "A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project\u2019s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner\u2019s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.", "size": 116, "snippet_links": [{"key": "a-schedule", "type": "clause", "offset": [0, 10]}, {"key": "proposed-activity", "type": "definition", "offset": [22, 39]}, {"key": "milestone-dates", "type": "definition", "offset": [65, 80]}, {"key": "approval-of", "type": "clause", "offset": [97, 108]}, {"key": "pertinent-information", "type": "clause", "offset": [109, 130]}, {"key": "shop-drawings-and-samples", "type": "clause", "offset": [174, 199]}, {"key": "delivery-of-materials", "type": "definition", "offset": [201, 222]}, {"key": "lead-time", "type": "definition", "offset": [251, 260]}, {"key": "the-schedule", "type": "clause", "offset": [354, 366]}, {"key": "number-of-activities", "type": "definition", "offset": [476, 496]}, {"key": "as-required", "type": "clause", "offset": [497, 508]}, {"key": "to-owner", "type": "clause", "offset": [533, 541]}, {"key": "work-and", "type": "clause", "offset": [564, 572]}, {"key": "the-project", "type": "definition", "offset": [580, 591]}, {"key": "critical-path", "type": "clause", "offset": [594, 607]}, {"key": "associated-activities", "type": "definition", "offset": [612, 633]}, {"key": "completion-of-the", "type": "clause", "offset": [734, 751]}, {"key": "overall-project", "type": "clause", "offset": [752, 767]}, {"key": "any-owner", "type": "clause", "offset": [830, 839]}, {"key": "occupancy-requirements", "type": "definition", "offset": [842, 864]}, {"key": "format-of-the", "type": "clause", "offset": [932, 945]}, {"key": "construction-start", "type": "clause", "offset": [1042, 1060]}, {"key": "equipment-installation", "type": "clause", "offset": [1166, 1188]}, {"key": "material-completion-and-occupancy-date", "type": "clause", "offset": [1211, 1249]}, {"key": "final-inspection", "type": "clause", "offset": [1251, 1267]}, {"key": "final-completion-date", "type": "definition", "offset": [1290, 1311]}], "samples": [{"hash": "inDemhgFG9t", "uri": "/contracts/inDemhgFG9t#construction-progress-schedule", "label": "Design Build Contract", "score": 32.3354377747, "published": true}, {"hash": "3VqAAHlhKyp", "uri": "/contracts/3VqAAHlhKyp#construction-progress-schedule", "label": "Construction Contract", "score": 32.1602478027, "published": true}, {"hash": "9ZtIaJScEUw", "uri": "/contracts/9ZtIaJScEUw#construction-progress-schedule", "label": "Design Build Contract", "score": 31.8071269989, "published": true}], "hash": "fd30aa61cea0b79cc2a5e71769fc3ba6", "id": 1}, {"snippet": "Construction Progress Schedule.", "size": 20, "snippet_links": [], "samples": [{"hash": "iRw5lY7fyjK", "uri": "/contracts/iRw5lY7fyjK#construction-progress-schedule", "label": "Design Build Contract", "score": 34.5430831909, "published": true}, {"hash": "2IvsvLuWUB", "uri": "/contracts/2IvsvLuWUB#construction-progress-schedule", "label": "Design Build Contract", "score": 34.5223617554, "published": true}, {"hash": "c53NTyeRv2A", "uri": "/contracts/c53NTyeRv2A#construction-progress-schedule", "label": "Design Build Contract", "score": 33.5207176208, "published": true}], "hash": "1c2c74ddac7c162304ae8c718772ee3c", "id": 2}, {"snippet": "(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring labor, materials, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments or take other remedies under the contract until the Contractor submits at the site; the required schedule.\n(2) Making modifications in drawings and technical (b) The Contractor shall enter the actual progress on the specifications and assisting the Contracting Officer in the preparation of change orders and other contract modifications for issuance by the Contracting Officer;\n(3) Reviewing and making recommendations with respect to - (i) the Contractor\u2019s construction progress schedules; (ii) the Contractor\u2019s shop and detailed drawings; (iii) the machinery, mechanical and other equipment and materials or other articles proposed for use by the Contractor; and, (iv) the Contractor\u2019s price breakdown and progress payment estimates; and,\n(4) Assisting in inspections, signing Certificates of Completion, and making recommendations with respect to acceptance of work completed under the contract. chart as required by the Contracting Officer, and immediately deliver three copies of the annotated schedule to the Contracting Officer. If the Contracting Officer determines, upon the basis of inspection conducted pursuant to the clause entitled Inspection and Acceptance of Construction, herein that the Contractor is not meeting the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the PHA. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of\n4. Other Contracts progress will be regained.", "size": 18, "snippet_links": [{"key": "the-contractor-shall", "type": "clause", "offset": [4, 24]}, {"key": "days-after", "type": "definition", "offset": [38, 48]}, {"key": "period-of-time", "type": "clause", "offset": [95, 109]}, {"key": "contracting-officer", "type": "definition", "offset": [128, 147]}, {"key": "submit-to", "type": "clause", "offset": [161, 170]}, {"key": "of-the-work", "type": "clause", "offset": [423, 434]}, {"key": "and-equipment", "type": "clause", "offset": [474, 487]}, {"key": "the-schedule", "type": "clause", "offset": [490, 502]}, {"key": "form-of", "type": "clause", "offset": [519, 526]}, {"key": "progress-chart", "type": "clause", "offset": [529, 543]}, {"key": "the-percentage", "type": "definition", "offset": [588, 602]}, {"key": "during-the-period", "type": "clause", "offset": [654, 671]}, {"key": "if-the-contractor", "type": "clause", "offset": [673, 690]}, {"key": "to-submit", "type": "definition", "offset": [697, 706]}, {"key": "a-schedule", "type": "clause", "offset": [707, 717]}, {"key": "approval-of-progress-payments", "type": "clause", "offset": [783, 812]}, {"key": "other-remedies", "type": "clause", "offset": [821, 835]}, {"key": "the-site", "type": "clause", "offset": [887, 895]}, {"key": "the-specifications", "type": "clause", "offset": [1025, 1043]}, {"key": "preparation-of-change-orders", "type": "clause", "offset": [1089, 1117]}, {"key": "contract-modifications", "type": "definition", "offset": [1128, 1150]}, {"key": "with-respect-to", "type": "clause", "offset": [1233, 1248]}, {"key": "progress-schedules", "type": "clause", "offset": [1285, 1303]}, {"key": "detailed-drawings", "type": "definition", "offset": [1336, 1353]}, {"key": "equipment-and-materials", "type": "definition", "offset": [1397, 1420]}, {"key": "other-articles", "type": "clause", "offset": [1424, 1438]}, {"key": "by-the-contractor", "type": "clause", "offset": [1456, 1473]}, {"key": "price-breakdown", "type": "clause", "offset": [1502, 1517]}, {"key": "certificates-of-completion", "type": "clause", "offset": [1593, 1619]}, {"key": "work-completed", "type": "clause", "offset": [1678, 1692]}, {"key": "as-required-by", "type": "clause", "offset": [1719, 1733]}, {"key": "copies-of-the", "type": "clause", "offset": [1789, 1802]}, {"key": "schedule-to", "type": "clause", "offset": [1813, 1824]}, {"key": "basis-of", "type": "clause", "offset": [1898, 1906]}, {"key": "pursuant-to-the", "type": "definition", "offset": [1928, 1943]}, {"key": "inspection-and-acceptance-of-construction", "type": "clause", "offset": [1960, 2001]}, {"key": "approved-schedule", "type": "definition", "offset": [2049, 2066]}, {"key": "additional-cost", "type": "definition", "offset": [2208, 2223]}, {"key": "require-the", "type": "clause", "offset": [2286, 2297]}, {"key": "contractor-to", "type": "clause", "offset": [2298, 2311]}, {"key": "number-of-shifts", "type": "clause", "offset": [2325, 2341]}, {"key": "overtime-operations", "type": "clause", "offset": [2343, 2362]}, {"key": "days-of-work", "type": "definition", "offset": [2364, 2376]}, {"key": "construction-plant", "type": "definition", "offset": [2399, 2417]}, {"key": "submit-for-approval", "type": "clause", "offset": [2426, 2445]}, {"key": "schedule-or-schedules", "type": "definition", "offset": [2464, 2485]}, {"key": "rate-of", "type": "clause", "offset": [2575, 2582]}, {"key": "other-contracts", "type": "clause", "offset": [2586, 2601]}], "samples": [{"hash": "4mqeaXhk4wE", "uri": "/contracts/4mqeaXhk4wE#construction-progress-schedule", "label": "Contract for Services", "score": 33.3975372314, "published": true}, {"hash": "3mnD5IcaYND", "uri": "/contracts/3mnD5IcaYND#construction-progress-schedule", "label": "Contract for Services", "score": 33.3948020935, "published": true}, {"hash": "eVTCxpeWFvw", "uri": "/contracts/eVTCxpeWFvw#construction-progress-schedule", "label": "Contract for Services", "score": 32.570854187, "published": true}], "hash": "e850384a015036c4c528ae0654bd3b0b", "id": 3}, {"snippet": "7.3.1 The A/E shall review the Construction Progress Schedule for conformance with the Contract Documents, provide a copy of the Construction Progress Schedule and schedule of submittals to the Contracting Authority and Owner.\n7.3.1.1 If the Project is administered using the State\u2019s web-based project management software, the A/E shall receive initial and updated schedules from the Contractor, and forward them to the Contracting Authority and Owner, through the \u201cSchedule Approvals\u201d business process.\n7.3.2 The A/E shall periodically inform the Contracting Authority and Owner of the need to update the Project Schedule as required to show current conditions, including conformance to the Construction Progress Schedule, as updated from time to time.\n7.3.2.1 If such conditions indicate that Milestone completion dates shown on the Project Schedule may not be met, the A/E shall recommend corrective action to the Contracting Authority and Owner and carry out the directions of the Contracting Authority so that the Milestone completion dates may be met, unless the Contracting Authority and Owner agree in writing to revise the Milestone completion dates.", "size": 15, "snippet_links": [{"key": "the-construction", "type": "clause", "offset": [27, 43]}, {"key": "the-contract-documents", "type": "clause", "offset": [83, 105]}, {"key": "a-copy-of-the", "type": "clause", "offset": [115, 128]}, {"key": "schedule-of-submittals", "type": "clause", "offset": [164, 186]}, {"key": "authority-and", "type": "clause", "offset": [206, 219]}, {"key": "the-project", "type": "definition", "offset": [238, 249]}, {"key": "the-state", "type": "clause", "offset": [272, 281]}, {"key": "project-management-software", "type": "clause", "offset": [294, 321]}, {"key": "updated-schedules", "type": "clause", "offset": [357, 374]}, {"key": "the-contractor", "type": "definition", "offset": [380, 394]}, {"key": "business-process", "type": "definition", "offset": [486, 502]}, {"key": "project-schedule", "type": "definition", "offset": [606, 622]}, {"key": "as-required", "type": "clause", "offset": [623, 634]}, {"key": "current-conditions", "type": "clause", "offset": [643, 661]}, {"key": "from-time-to-time", "type": "clause", "offset": [735, 752]}, {"key": "milestone-completion-dates", "type": "clause", "offset": [795, 821]}, {"key": "corrective-action", "type": "definition", "offset": [892, 909]}, {"key": "in-writing", "type": "definition", "offset": [1107, 1117]}], "samples": [{"hash": "ln4b64APq5S", "uri": "/contracts/ln4b64APq5S#construction-progress-schedule", "label": "Professional Services", "score": 30.4815349579, "published": true}, {"hash": "l0F6p7yqdCQ", "uri": "/contracts/l0F6p7yqdCQ#construction-progress-schedule", "label": "Architect/Engineer Agreement", "score": 28.5770339966, "published": true}, {"hash": "79mpjJszpPR", "uri": "/contracts/79mpjJszpPR#construction-progress-schedule", "label": "Architect/Engineer Agreement", "score": 28.5770339966, "published": true}], "hash": "fc736e025d73309525c9dd877ecb9d3c", "id": 4}, {"snippet": "Within ten (10) days of the Notice to Proceed, the Contractor shall submit to the Engineer a Preliminary Progress Schedule (\u201cPPS\u201d) and a Near Term Schedule (\u201cNTS\u201d) in the form and with the content required by the Specifications. Within forty- five (45) days of the Notice to Proceed, the Contractor shall submit to the Engineer the Overall Project Schedule (\u201cOPS\u201d) as required in the Specifications.", "size": 12, "snippet_links": [{"key": "the-notice-to-proceed", "type": "clause", "offset": [24, 45]}, {"key": "the-contractor-shall", "type": "clause", "offset": [47, 67]}, {"key": "submit-to", "type": "clause", "offset": [68, 77]}, {"key": "the-engineer", "type": "definition", "offset": [78, 90]}, {"key": "progress-schedule", "type": "definition", "offset": [105, 122]}, {"key": "the-content", "type": "clause", "offset": [185, 196]}, {"key": "required-by", "type": "definition", "offset": [197, 208]}, {"key": "the-specifications", "type": "clause", "offset": [209, 227]}, {"key": "overall-project-schedule", "type": "clause", "offset": [332, 356]}, {"key": "as-required", "type": "clause", "offset": [365, 376]}], "samples": [{"hash": "ko3RMY7Kdrx", "uri": "/contracts/ko3RMY7Kdrx#construction-progress-schedule", "label": "Contract for Water Main Relocation", "score": 27.5790557861, "published": true}, {"hash": "1V3wPBhiSLf", "uri": "/contracts/1V3wPBhiSLf#construction-progress-schedule", "label": "Contract Agreement", "score": 27.4640655518, "published": true}, {"hash": "9Vk1rAk0ogm", "uri": "/contracts/9Vk1rAk0ogm#construction-progress-schedule", "label": "Contract Agreement", "score": 27.045173645, "published": true}], "hash": "95f3e8ccc762735a87bcd854f3956313", "id": 5}, {"snippet": "A schedule, as more fully defined in Paragraph2.1.5.2, prepared by the CM/GC (based, in part, upon the Owner\u201fs Program and the Design Professional\u201fs Preliminary Design and Construction Schedule), indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion, Occupancy and Final Completion.", "size": 7, "snippet_links": [{"key": "a-schedule", "type": "clause", "offset": [0, 10]}, {"key": "prepared-by", "type": "definition", "offset": [55, 66]}, {"key": "the-design", "type": "clause", "offset": [123, 133]}, {"key": "preliminary-design-and-construction-schedule", "type": "clause", "offset": [149, 193]}, {"key": "proposed-activity", "type": "definition", "offset": [207, 224]}, {"key": "milestone-dates", "type": "definition", "offset": [250, 265]}, {"key": "approval-of", "type": "clause", "offset": [282, 293]}, {"key": "pertinent-information", "type": "clause", "offset": [294, 315]}, {"key": "shop-drawings-and-samples", "type": "clause", "offset": [359, 384]}, {"key": "delivery-of-materials", "type": "definition", "offset": [386, 407]}, {"key": "lead-time", "type": "definition", "offset": [436, 445]}, {"key": "material-completion", "type": "clause", "offset": [483, 502]}, {"key": "final-completion", "type": "definition", "offset": [518, 534]}], "samples": [{"hash": "aI9vzMdcJRF", "uri": "/contracts/aI9vzMdcJRF#construction-progress-schedule", "label": "Construction Management Agreement", "score": 24.4682445526, "published": true}, {"hash": "aRmY9wQgNDS", "uri": "/contracts/aRmY9wQgNDS#construction-progress-schedule", "label": "Construction Management Agreement", "score": 22.7344284058, "published": true}], "hash": "c10ef44be3869a1146c69b1a7e40d3d8", "id": 6}, {"snippet": "Construction Progress Schedule prepared in accordance with this Contract including the dates assumed by CMR for the Design Professional\u2019s completion of Construction Documents necessary to effect the Program.", "size": 5, "snippet_links": [{"key": "in-accordance-with", "type": "definition", "offset": [40, 58]}, {"key": "this-contract", "type": "definition", "offset": [59, 72]}, {"key": "the-design-professional", "type": "clause", "offset": [112, 135]}, {"key": "construction-documents", "type": "clause", "offset": [152, 174]}, {"key": "the-program", "type": "clause", "offset": [195, 206]}], "samples": [{"hash": "dcVkcRWRe42", "uri": "/contracts/dcVkcRWRe42#construction-progress-schedule", "label": "Construction Management at Risk Agreement", "score": 25.043806076, "published": true}, {"hash": "erckkXgDV3N", "uri": "/contracts/erckkXgDV3N#construction-progress-schedule", "label": "Construction Management at Risk Agreement", "score": 23.5968513489, "published": true}, {"hash": "3bBfY84wYGA", "uri": "/contracts/3bBfY84wYGA#construction-progress-schedule", "label": "Construction Management at Risk Agreement", "score": 23.5968513489, "published": true}], "hash": "543907611f5a675848b40623fd2bff9c", "id": 7}, {"snippet": "6.5.1 If the Estimated Construction Cost for the Project is $500,000 or more, the Contractor shall prepare and maintain a resource-loaded Construction Progress Schedule using the critical-path method of scheduling that provides the following information:\n6.5.1.1 a graphic presentation of the sequence of the Work for the Project in the media and format required for the Project;\n6.5.1.2 identification of each stage of the Work and any Milestone dates;\n6.5.1.3 identification of activities and durations for review and approval of Shop Drawings and other action submittals, fabrication and review of mock-up Work, product review and procurement, fabrication, shop inspection, and delivery, including, but not limited to, lead time, coordination drawing delivery, Substantial Completion, Punch List, Punch List Correction, Project close-out requirements, occupancy requirements, and Contract Completion, and occupancy requirements;\n6.5.1.4 identification of disruptions and shutdowns due to other operations;\n6.5.1.5 identification of the critical path of the Work;\n6.5.1.6 identification of the crew size and total resource hours for each activity in the schedule; and\n6.5.1.7 the Contractor\u2019s signature and date indicating approval.\n6.5.2 The Contractor shall develop the Construction Progress Schedule using commercially available, personal computer software that is acceptable to the Contracting Authority and shall submit all baseline and updated schedules to the A/E in the schedules\u2019 native electronic format.\n6.5.3 The Construction Progress Schedule shall not exceed the time limits current under the Contract Documents, shall provide for reasonable, efficient, and economical execution of the Project, and shall relate to the entire Project to the extent required by the Contract Documents.\n6.5.4 The Contractor shall use the Construction Progress Schedule to plan, organize, and execute the Project, record and report actual performance and progress, and show how it plans to coordinate and complete all remaining Work within applicable Milestones. The Project participants shall use the Construction Progress Schedule as a tool for scheduling and reporting sequenced progress of the Work. The Contractor shall provide a clear graphics legend and other data including, but not limited to, Milestone dates, constraints, and other items required by the Project, the A/E, the Contracting Authority, and the Owner. Each submission shall show the Contracting Authority\u2019s Project number and Project name, and provide a signature approval and date line for the Contractor.\n6.5.5 The Contractor shall provide in each schedule: Activity identification and description for each activity broken down to a maximum duration that is appropriate for the activity, responsibility of the Contractor, Contractor\u2019s resources and crew size for each activity, provide early start, early finish, late start, late finish dates. Each schedule shall show predecessor activities and successor activities for each activity, entry free float, total float, and percentage of completion, and identify the appropriate predecessors and successors for all related activities.\n6.5.6 The Construction Progress Schedule shall show all submittal dates, review and approval durations for coordination drawing preparationdrawings, Shop DrawingsDrawings, other action submittals, and mock-up review and approval durationsWork.\n6.5.7 The Contractor shall submit the initial and all updates of the Construction Progress Schedule in graphic and tabular form to the A/E. With each monthly schedule update, the Contractor shall include a list of all changes to the previously approved baseline schedule or monthly updated schedule.\n6.5.7.1 Upon receipt ofAfter receiving the Construction Progress Schedule, the A/E shall review and submit a copy of the Construction Progress Schedule to the Contracting Authority and the Owner for review and acceptance, or reject it, and return it to the Contractor with recommendations for revisions.\n6.5.7.2 If the Project is administered using OAKS CIthe State\u2019s web-based project management software, the Contractor shall create, approve, and submit the initial and all updates of the Construction Progress Schedule to the A/E, the, Contracting Authority, and the Owner through the \u201cSchedule Approvals\u201d business process.\n6.5.8 The Construction Progress Schedule shall be managed using early start dates and early finish dates. The Contractor shallmust exhaust existing float before claiming additional time for a Change Order, or show that it is not possible to use float to cover the time requirements of the Change Order.", "size": 5, "snippet_links": [{"key": "estimated-construction-cost", "type": "definition", "offset": [13, 40]}, {"key": "method-of", "type": "definition", "offset": [193, 202]}, {"key": "work-for", "type": "definition", "offset": [309, 317]}, {"key": "the-media", "type": "clause", "offset": [333, 342]}, {"key": "work-and", "type": "clause", "offset": [424, 432]}, {"key": "milestone-dates", "type": "definition", "offset": [437, 452]}, {"key": "of-activities", "type": "clause", "offset": [477, 490]}, {"key": "approval-of", "type": "clause", "offset": [520, 531]}, {"key": "shop-drawings", "type": "clause", "offset": [532, 545]}, {"key": "action-submittals", "type": "definition", "offset": [556, 573]}, {"key": "review-of", "type": "clause", "offset": [591, 600]}, {"key": "product-review", "type": "definition", "offset": [615, 629]}, {"key": "shop-inspection", "type": "definition", "offset": [660, 675]}, {"key": "and-delivery", "type": "clause", "offset": [677, 689]}, {"key": "not-limited", "type": "clause", "offset": [706, 717]}, {"key": "lead-time", "type": "definition", "offset": [722, 731]}, {"key": "substantial-completion", "type": "clause", "offset": [764, 786]}, {"key": "punch-list", "type": "clause", "offset": [788, 798]}, {"key": "project-close", "type": "clause", "offset": [823, 836]}, {"key": "occupancy-requirements", "type": "definition", "offset": [855, 877]}, {"key": "contract-completion", "type": "definition", "offset": [883, 902]}, {"key": "other-operations", "type": "clause", "offset": [991, 1007]}, {"key": "critical-path", "type": "clause", "offset": [1039, 1052]}, {"key": "crew-size", "type": "clause", "offset": [1096, 1105]}, {"key": "signature-and-date", "type": "definition", "offset": [1195, 1213]}, {"key": "the-construction", "type": "clause", "offset": [1270, 1286]}, {"key": "commercially-available", "type": "definition", "offset": [1311, 1333]}, {"key": "computer-software", "type": "definition", "offset": [1344, 1361]}, {"key": "authority-and", "type": "clause", "offset": [1400, 1413]}, {"key": "updated-schedules", "type": "clause", "offset": [1444, 1461]}, {"key": "the-schedules", "type": "clause", "offset": [1476, 1489]}, {"key": "electronic-format", "type": "clause", "offset": [1498, 1515]}, {"key": "time-limits", "type": "clause", "offset": [1579, 1590]}, {"key": "the-contract-documents", "type": "clause", "offset": [1605, 1627]}, {"key": "provide-for", "type": "clause", "offset": [1635, 1646]}, {"key": "execution-of-the-project", "type": "clause", "offset": [1685, 1709]}, {"key": "relate-to", "type": "definition", "offset": [1721, 1730]}, {"key": "to-the-extent", "type": "clause", "offset": [1750, 1763]}, {"key": "required-by", "type": "definition", "offset": [1764, 1775]}, {"key": "schedule-to", "type": "clause", "offset": [1857, 1868]}, {"key": "performance-and-progress", "type": "clause", "offset": [1935, 1959]}, {"key": "remaining-work", "type": "clause", "offset": [2014, 2028]}, {"key": "project-participants", "type": "clause", "offset": [2063, 2083]}, {"key": "progress-of-the-work", "type": "clause", "offset": [2178, 2198]}, {"key": "provide-a", "type": "definition", "offset": [2221, 2230]}, {"key": "other-data", "type": "definition", "offset": [2257, 2267]}, {"key": "items-required", "type": "clause", "offset": [2339, 2353]}, {"key": "the-owner", "type": "definition", "offset": [2410, 2419]}, {"key": "project-number", "type": "clause", "offset": [2476, 2490]}, {"key": "project-name", "type": "definition", "offset": [2495, 2507]}, {"key": "signature-approval", "type": "clause", "offset": [2523, 2541]}, {"key": "for-the-contractor", "type": "clause", "offset": [2556, 2574]}, {"key": "and-description", "type": "clause", "offset": [2653, 2668]}, {"key": "maximum-duration", "type": "definition", "offset": [2704, 2720]}, {"key": "the-activity", "type": "clause", "offset": [2745, 2757]}, {"key": "responsibility-of-the-contractor", "type": "clause", "offset": [2759, 2791]}, {"key": "early-start", "type": "clause", "offset": [2857, 2868]}, {"key": "late-start", "type": "clause", "offset": [2884, 2894]}, {"key": "free-float", "type": "definition", "offset": [3013, 3023]}, {"key": "total-float", "type": "definition", "offset": [3025, 3036]}, {"key": "percentage-of-completion", "type": "clause", "offset": [3042, 3066]}, {"key": "predecessors-and-successors", "type": "clause", "offset": [3097, 3124]}, {"key": "related-activities", "type": "clause", "offset": [3133, 3151]}, {"key": "monthly-schedule-update", "type": "clause", "offset": [3547, 3570]}, {"key": "a-list", "type": "definition", "offset": [3601, 3607]}, {"key": "all-changes-to-the", "type": "clause", "offset": [3611, 3629]}, {"key": "baseline-schedule", "type": "definition", "offset": [3650, 3667]}, {"key": "upon-receipt", "type": "definition", "offset": [3705, 3717]}, {"key": "a-copy-of-the", "type": "clause", "offset": [3804, 3817]}, {"key": "review-and-acceptance", "type": "clause", "offset": [3896, 3917]}, {"key": "and-return", "type": "clause", "offset": [3933, 3943]}, {"key": "to-the-contractor", "type": "clause", "offset": [3947, 3964]}, {"key": "recommendations-for", "type": "clause", "offset": [3970, 3989]}, {"key": "project-management-software", "type": "clause", "offset": [4075, 4102]}, {"key": "business-process", "type": "definition", "offset": [4306, 4322]}, {"key": "additional-time", "type": "clause", "offset": [4494, 4509]}, {"key": "a-change-order", "type": "clause", "offset": [4514, 4528]}, {"key": "the-change-order", "type": "clause", "offset": [4609, 4625]}], "samples": [{"hash": "1PNm5gDHSBJ", "uri": "/contracts/1PNm5gDHSBJ#construction-progress-schedule", "label": "General Contracting Agreement", "score": 25.2812423706, "published": true}, {"hash": "1GLPTG1ji9e", "uri": "/contracts/1GLPTG1ji9e#construction-progress-schedule", "label": "Standard Requirements for Public Facility Construction", "score": 23.1409988403, "published": true}], "hash": "8bcc51365d3cf51aae6d683cafb3a81c", "id": 8}, {"snippet": "Prior to or at the preconstruction conference and before beginning work on the Project, the Consultant shall submit to the project engineer a Construction Progress Schedule giving a satisfactory schedule of operations that provides for completion of the work within the contract time. The contractor shall have copies of the schedule available at the preconstruction conference.\na. If the Consultant\u2019s operations are affected by changes in the plans or amount of work, or if the Consultant has failed to comply with the approved schedule, or if requested by the engineer, the Consultant shall submit a revised Construction Progress Schedule for approval. This revised schedule shall show how the Consultant proposes to prosecute the balance of the work. If the engineer requests a revised schedule, the Consultant shall submit the revised schedule within 14 calendar days after the date of request or progress payments may be withheld.\nb. The approved Construction Progress Schedule will be used as the basis of establishing the controlling item of work, charging contract time and as a check on the progress of the work. The Construction Progress Schedule shall show only one controlling item of work for each contract day. If the Construction Progress Schedule has not been approved prior to the issuance of the Notice to Proceed, the engineer will establish the controlling work item and charge contract time accordingly.", "size": 2, "snippet_links": [{"key": "preconstruction-conference", "type": "clause", "offset": [19, 45]}, {"key": "work-on", "type": "definition", "offset": [67, 74]}, {"key": "the-project", "type": "definition", "offset": [75, 86]}, {"key": "the-consultant-shall", "type": "clause", "offset": [88, 108]}, {"key": "submit-to", "type": "clause", "offset": [109, 118]}, {"key": "project-engineer", "type": "definition", "offset": [123, 139]}, {"key": "schedule-of-operations", "type": "clause", "offset": [195, 217]}, {"key": "completion-of-the-work", "type": "definition", "offset": [236, 258]}, {"key": "the-contract-time", "type": "clause", "offset": [266, 283]}, {"key": "the-contractor-shall", "type": "clause", "offset": [285, 305]}, {"key": "the-schedule", "type": "clause", "offset": [321, 333]}, {"key": "available-at", "type": "definition", "offset": [334, 346]}, {"key": "affected-by", "type": "definition", "offset": [417, 428]}, {"key": "changes-in", "type": "clause", "offset": [429, 439]}, {"key": "the-plans", "type": "clause", "offset": [440, 449]}, {"key": "amount-of-work", "type": "clause", "offset": [453, 467]}, {"key": "comply-with-the", "type": "clause", "offset": [504, 519]}, {"key": "approved-schedule", "type": "definition", "offset": [520, 537]}, {"key": "requested-by", "type": "definition", "offset": [545, 557]}, {"key": "the-engineer", "type": "definition", "offset": [558, 570]}, {"key": "for-approval", "type": "definition", "offset": [641, 653]}, {"key": "revised-schedule", "type": "definition", "offset": [660, 676]}, {"key": "balance-of-the", "type": "clause", "offset": [733, 747]}, {"key": "days-after", "type": "definition", "offset": [867, 877]}, {"key": "date-of-request", "type": "definition", "offset": [882, 897]}, {"key": "payments-may-be", "type": "clause", "offset": [910, 925]}, {"key": "basis-of", "type": "clause", "offset": [1003, 1011]}, {"key": "item-of-work", "type": "definition", "offset": [1041, 1053]}, {"key": "progress-of-the-work", "type": "clause", "offset": [1100, 1120]}, {"key": "the-construction", "type": "clause", "offset": [1122, 1138]}, {"key": "work-for", "type": "definition", "offset": [1197, 1205]}, {"key": "contract-day", "type": "definition", "offset": [1211, 1223]}, {"key": "the-notice-to-proceed", "type": "clause", "offset": [1310, 1331]}, {"key": "work-item", "type": "definition", "offset": [1377, 1386]}], "samples": [{"hash": "eldmPD9M2ZX", "uri": "/contracts/eldmPD9M2ZX#construction-progress-schedule", "label": "Contract for Services", "score": 35.9208908081, "published": true}, {"hash": "atm8qjTa3Cd", "uri": "/contracts/atm8qjTa3Cd#construction-progress-schedule", "label": "Contract for Services", "score": 35.7326316833, "published": true}], "hash": "b42b57a0fd03a41a1953d6d57f1904a2", "id": 9}, {"snippet": "This Section includes administrative and procedural requirements for the preparation, submittal, and maintenance of the progress schedule, reporting progress of the Work, and Contract Time adjustments, including the following:", "size": 2, "snippet_links": [{"key": "section-includes", "type": "clause", "offset": [5, 21]}, {"key": "requirements-for-the", "type": "clause", "offset": [52, 72]}, {"key": "the-progress-schedule", "type": "clause", "offset": [116, 137]}, {"key": "progress-of-the-work", "type": "clause", "offset": [149, 169]}, {"key": "contract-time", "type": "definition", "offset": [175, 188]}], "samples": [{"hash": "kzhx5Muz8Qu", "uri": "/contracts/kzhx5Muz8Qu#construction-progress-schedule", "label": "Construction Contract", "score": 32.3956604004, "published": true}, {"hash": "hx31ggYjx7z", "uri": "/contracts/hx31ggYjx7z#construction-progress-schedule", "label": "Construction Contract", "score": 29.2404918671, "published": true}], "hash": "1b7c3bd41e87fd24c28af079f6f3b795", "id": 10}], "next_curs": "CmcSYWoVc35sYXdpbnNpZGVyY29udHJhY3RzckMLEhZDbGF1c2VTbmlwcGV0R3JvdXBfdjU2Iidjb25zdHJ1Y3Rpb24tcHJvZ3Jlc3Mtc2NoZWR1bGUjMDAwMDAwMGEMogECZW4YACAA", "clause": {"size": 196, "parents": [["documents", "Documents"], ["full-agreement", "Full Agreement"], ["contractors-federal-employment-verification-certification", "Contractor\u2019s Federal Employment Verification Certification"], ["contract-forms", "Contract Forms"], ["responsibility-for-completion", "Responsibility for Completion"]], "title": "Construction Progress Schedule", "children": [["", ""], ["workforce", "workforce"], ["completion-date", "Completion date"], ["the-contractor", "The Contractor"], ["gmp-proposal-review-meeting", "GMP Proposal Review Meeting"]], "id": "construction-progress-schedule", "related": [["progress-schedule", "PROGRESS SCHEDULE", "PROGRESS SCHEDULE"], ["construction-schedule", "Construction Schedule", "Construction Schedule"], ["construction-plans", "Construction Plans", "Construction Plans"], ["construction-budget", "Construction Budget", "Construction Budget"], ["construction-etc", "Construction, Etc", "Construction, Etc"]], "related_snippets": [], "updated": "2025-07-26T06:21:18+00:00"}, "json": true, "cursor": ""}}