Common use of Construction Cost Adjustment Clause in Contracts

Construction Cost Adjustment. Contracting Officer, as provided in B5.21, B5.212, B5.251, B5.252, and B5.253, shall adjust Specified Road construction cost estimates in the Schedule of Items and show the adjustments as credits or debits to Timber Sale Account in the month when the road segment is accepted. B5.251 Variation in Quantities. (a) This Item applies only to differences between quantities shown in the Schedule of Items and measured quantities actually constructed and accepted that are not covered under B5.252 or B5.253. Only changes in quantities where other than contract quantity or lump sum is specified in the Schedule of Items are subject to this Item.

Appears in 19 contracts

Samples: Service Timber Sale Contract, Service Timber Sale Contract, Service Timber Sale Contract

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.