Common use of Claims for Additional Costs Clause in Contracts

Claims for Additional Costs. 11.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, it shall give the Owner and the A/E written notice thereof within twenty-one (21) days after the occurrence of the event giving rise to such claim, but, in any case before proceeding to execute the work considered to give rise to the additional cost or time, except in an emergency endangering life or property in which case the Contractor shall act in accordance with Article 7.2.1. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined as set forth under Article 15. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order.

Appears in 32 contracts

Samples: Agreement, Agreement, assets.system.tamus.edu

AutoNDA by SimpleDocs

Claims for Additional Costs. 11.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, it they shall give the Owner and the A/E written notice thereof within twenty-one (21) days after the occurrence of the event giving rise to such claim, but, in any case before proceeding to execute the work Work considered to give rise to the be additional cost or time, except in an emergency endangering life or property in which case the Contractor shall act in accordance with Article 7.2.1Subsection 7.3. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined as set forth under Article 15. Any change in the Contract Sum resulting from such claim shall be authorized by a Change OrderOrder or a ULCO.

Appears in 3 contracts

Samples: contracts.hhs.texas.gov, contracts.hhs.texas.gov, contracts.hhs.texas.gov

Claims for Additional Costs. 11.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, it they shall give the Owner and the A/E written notice thereof within twenty-one (21) days after the occurrence of the event giving rise to such claim, but, in any case before proceeding to execute the work Work considered to give rise to the be additional cost or time, except in an emergency endangering life or property in which case the Contractor shall act in accordance with Article Subsection 7.2.1. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined as set forth under Article 15. Any change in the Contract Sum resulting from such claim shall be authorized by a Change OrderOrder or a ULCO.

Appears in 1 contract

Samples: s3.glo.texas.gov

Claims for Additional Costs. 11.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, it they shall give the Owner ODR and the A/E written notice thereof within twenty-one (21) days after the occurrence of the event giving rise to such claim, but, in any case before proceeding to execute the work Work considered to give rise to the be additional cost or time, except in an emergency endangering life or property in which case the Contractor shall act in accordance with Article 7.2.1Subsection 8.2.1. No such claim shall be valid unless so made. If the Owner ODR and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined as set forth under Article 15. Any change in the Contract Sum resulting from such claim shall be authorized by a Change OrderOrder or a ULCO.

Appears in 1 contract

Samples: Master Service Agreement

AutoNDA by SimpleDocs

Claims for Additional Costs. 11.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, it shall give the Owner and the A/E written notice thereof within twenty-one (21) days after the occurrence of the event giving rise to such claim, but, in any case before proceeding to execute the work considered to give rise to the additional cost or time, except in an emergency endangering life or property in which case the Contractor shall act in accordance with Article 7.2.1. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined as set forth under Article 15. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order.Article

Appears in 1 contract

Samples: assets.system.tamus.edu