{"component": "clause", "props": {"groups": [{"snippet": "7.1 Changes to the Work may be accomplished by preparation of and execution of a change order or construction change directive. Change orders or construction change directives will be preceded by a change proposal request initiated by the Architect. The Construction Manager shall provide prices and details within 30 days of receipt of a change proposal request, and the Architect shall forward the completed change proposal request to the Owner within 15 days after receipt of the information provided by the Construction Manager.\n7.2 For the purposes of this Agreement, a change order is a written document prepared by the Architect, and executed by the Owner, Construction Manager, and Architect, setting out in detail the specific change in the Work, the dollar amount of any adjustment to the GMP, if any, and any adjustment to the contract time.\n7.3 For the purposes of this Agreement, a construction change directive is a written document prepared by the Architect and executed by the Owner, which serves to change the work and provides for any proposed adjustment in the GMP or contract time. A construction change directive shall be used in the event the parties to this Agreement cannot reach an agreement on the terms of a change order.\n7.3.1 Upon request of the Owner or the Architect, the Construction Manager shall, without any increase in the GMP, submit to the Architect within 15 days, in such form as the Architect may require, an accurate written estimate of the cost of any proposed Work set forth in the construction change directive.\n7.3.2 The estimate shall indicate the quantity and unit cost of each item of materials, and the number of hours of work and hourly rate for each class of labor, as well as the description and amounts of all other cost chargeable under the terms of this subparagraph. Unit labor costs for the installation of each item of materials shall be shown if required by the Architect. The Construction Manager shall promptly revise and resubmit such estimate if the Architect determines that it is not in compliance with the requirement of this Article, or that it contains errors of fact or mathematical errors. If required by the Architect, in order to establish the exact cost of new work added or of previously required work omitted, the Construction Manager shall obtain and furnish to the Architect bona fide proposals from recognized suppliers for furnishing any material included in such Work. Such estimates shall be furnished promptly so as to occasion no delay in the Work, and shall be furnished at the Construction Manager\u2019s expense. The Construction Manager shall state in the estimate any extension of time required for the completion of the Work if the change or extra work is ordered. Notwithstanding any other provision of this Agreement, and without limitation, the Construction Manager shall obtain and maintain: (i) documentation that clearly identifies, and permits evaluation by School Board of, the \u2587\u2587\u2587\u2587 up on change orders; (ii) supporting documentation for change orders that reports detailed and specific amounts for labor, materials and equipment charges; and (iii) supporting documentation showing labor burden percentages, if applicable and if specifically provided for in writing by School Board.\n7.3.3 If the construction change directive provides for an adjustment to the Contract Sum, the adjustment shall be based on one of the following methods, as selected by the Owner.\n(a) By unit prices stated in the Contract Documents or otherwise mutually agreed upon.\n(b) By cost and percentages estimated by the Construction Manager as define in this subparagraph and accepted by the Owner. The Construction Manager\u2019s estimate shall become a fixed price which shall not be changed by any variation in the actual cost of executing the Work covered by the change.\n(c) By actual cost determined after the Work covered by the change is completed, plus percentage.\n(d) By submission to a Court, which shall determine the fair value of the work covered by the change. As used in this subparagraph, \u201ccost\u201d shall mean the estimated or actual net increase or decrease in cost to the Construction Manager, subcontractor, or sub-subcontractor for performing the work covered by the change, including actual payments for materials, equipment rentals, expendable items, wages and associated benefits to workmen and to supervisors employed full time at the site, insurance bonds and other provable direct costs, but not including any administrative, accounting, or other indirect or overhead costs, or any wages or benefits of supervisory personnel not assigned full time to the site, or any amount of profit or fee to the Construction Manager, subcontractor or sub- subcontractor. As used in this subparagraph, \u201cpercentage\u201d shall mean an allowance to be added to or subtracted from the cost in lieu of overhead and profit and of any other expense which is not included in the cost of the Work covered by the change, as defined above. Percentage for the Construction Manager, a subcontractor, a sub-subcontractor or any other lower tier subcontractors for any work performed by their own forces shall be a maximum of 15% of any net increase, and 5% of any net decrease when the decrease results in a reduction of overhead requirements. The maximum percentage of 15% as applied to subcontractors shall be a cumulative percentage, inclusive of sub-contractor, sub-subcontractors and other subordinate contracting parties. In the event the Construction Manager does not perform any of the Work with its own forces, the percentage for the Construction manager shall be the same percentage increase or decrease as the Construction Manager Fee set out in paragraph 3.10.5 above.\n7.4 When in the reasonable judgment of the Architect a series of construction change directives or change orders effect a single change, percentage shall be calculated on the cumulative net increase or decrease in cost, if any.\n7.5 Notwithstanding the inclusion of unit prices in the Contract Documents, it shall be the Owner\u2019s option to require the cost of any change to be determined by one of the other methods stated in 7.3.", "size": 19, "snippet_links": [{"key": "preparation-of", "type": "clause", "offset": [47, 61]}, {"key": "a-change-order", "type": "clause", "offset": [79, 93]}, {"key": "change-orders", "type": "clause", "offset": [128, 141]}, {"key": "construction-change-directives", "type": "clause", "offset": [145, 175]}, {"key": "change-proposal-request", "type": "definition", "offset": [198, 221]}, {"key": "the-construction-manager", "type": "clause", "offset": [250, 274]}, {"key": "receipt-of-a", "type": "clause", "offset": [326, 338]}, {"key": "the-architect-shall", "type": "clause", "offset": [368, 387]}, {"key": "after-receipt-of", "type": "clause", "offset": [462, 478]}, {"key": "information-provided-by", "type": "clause", "offset": [483, 506]}, {"key": "for-the-purposes-of-this-agreement", "type": "clause", "offset": [537, 571]}, {"key": "written-document", "type": "definition", "offset": [593, 609]}, {"key": "prepared-by", "type": "definition", "offset": [610, 621]}, {"key": "by-the-owner", "type": "clause", "offset": [650, 662]}, {"key": "setting-out", "type": "clause", "offset": [701, 712]}, {"key": "in-detail", "type": "clause", "offset": [713, 722]}, {"key": "change-in-the-work", "type": "definition", "offset": [736, 754]}, {"key": "dollar-amount", "type": "clause", "offset": [760, 773]}, {"key": "adjustment-to", "type": "clause", "offset": [781, 794]}, {"key": "the-contract-time", "type": "clause", "offset": [834, 851]}, {"key": "proposed-adjustment", "type": "definition", "offset": [1053, 1072]}, {"key": "the-parties-to-this-agreement", "type": "clause", "offset": [1161, 1190]}, {"key": "an-agreement", "type": "clause", "offset": [1204, 1216]}, {"key": "terms-of", "type": "definition", "offset": [1224, 1232]}, {"key": "upon-request", "type": "definition", "offset": [1255, 1267]}, {"key": "of-the-owner", "type": "clause", "offset": [1268, 1280]}, {"key": "submit-to", "type": "clause", "offset": [1364, 1373]}, {"key": "written-estimate", "type": "clause", "offset": [1459, 1475]}, {"key": "proposed-work", "type": "definition", "offset": [1495, 1508]}, {"key": "the-estimate", "type": "clause", "offset": [1563, 1575]}, {"key": "unit-cost", "type": "clause", "offset": [1608, 1617]}, {"key": "hours-of-work-and", "type": "clause", "offset": [1663, 1680]}, {"key": "hourly-rate", "type": "clause", "offset": [1681, 1692]}, {"key": "class-of", "type": "definition", "offset": [1702, 1710]}, {"key": "the-description", "type": "clause", "offset": [1729, 1744]}, {"key": "other-cost", "type": "clause", "offset": [1764, 1774]}, {"key": "labor-costs", "type": "clause", "offset": [1829, 1840]}, {"key": "installation-of", "type": "clause", "offset": [1849, 1864]}, {"key": "required-by", "type": "definition", "offset": [1906, 1917]}, {"key": "revise-and-resubmit", "type": "clause", "offset": [1973, 1992]}, {"key": "the-requirement", "type": "clause", "offset": [2069, 2084]}, {"key": "this-article", "type": "definition", "offset": [2088, 2100]}, {"key": "to-establish", "type": "clause", "offset": [2200, 2212]}, {"key": "new-work", "type": "definition", "offset": [2231, 2239]}, {"key": "required-work", "type": "definition", "offset": [2263, 2276]}, {"key": "furnish-to", "type": "clause", "offset": [2328, 2338]}, {"key": "bona-fide", "type": "definition", "offset": [2353, 2362]}, {"key": "no-delay", "type": "clause", "offset": [2511, 2519]}, {"key": "time-required", "type": "clause", "offset": [2665, 2678]}, {"key": "completion-of-the-work", "type": "definition", "offset": [2687, 2709]}, {"key": "extra-work", "type": "definition", "offset": [2727, 2737]}, {"key": "other-provision-of-this-agreement", "type": "clause", "offset": [2770, 2803]}, {"key": "without-limitation", "type": "clause", "offset": [2809, 2827]}, {"key": "board-of", "type": "definition", "offset": [2957, 2965]}, {"key": "the-\u2587", "type": "clause", "offset": [2967, 2972]}, {"key": "supporting-documentation", "type": "definition", "offset": [3002, 3026]}, {"key": "for-change", "type": "clause", "offset": [3027, 3037]}, {"key": "equipment-charges", "type": "definition", "offset": [3113, 3130]}, {"key": "labor-burden", "type": "clause", "offset": [3175, 3187]}, {"key": "if-applicable", "type": "clause", "offset": [3201, 3214]}, {"key": "in-writing", "type": "definition", "offset": [3248, 3258]}, {"key": "the-contract-sum", "type": "clause", "offset": [3349, 3365]}, {"key": "the-adjustment", "type": "clause", "offset": [3367, 3381]}, {"key": "based-on", "type": "definition", "offset": [3391, 3399]}, {"key": "as-selected", "type": "definition", "offset": [3430, 3441]}, {"key": "unit-prices", "type": "definition", "offset": [3463, 3474]}, {"key": "the-contract-documents", "type": "clause", "offset": [3485, 3507]}, {"key": "mutually-agreed", "type": "definition", "offset": [3521, 3536]}, {"key": "accepted-by", "type": "definition", "offset": [3644, 3655]}, {"key": "fixed-price", "type": "clause", "offset": [3718, 3729]}, {"key": "actual-cost", "type": "definition", "offset": [3781, 3792]}, {"key": "covered-by", "type": "definition", "offset": [3815, 3825]}, {"key": "determine-the", "type": "clause", "offset": [3978, 3991]}, {"key": "fair-value", "type": "definition", "offset": [3992, 4002]}, {"key": "increase-or-decrease", "type": "clause", "offset": [4114, 4134]}, {"key": "performing-the-work", "type": "clause", "offset": [4212, 4231]}, {"key": "payments-for", "type": "clause", "offset": [4272, 4284]}, {"key": "equipment-rentals", "type": "clause", "offset": [4296, 4313]}, {"key": "expendable-items", "type": "definition", "offset": [4315, 4331]}, {"key": "wages-and", "type": "clause", "offset": [4333, 4342]}, {"key": "the-site", "type": "clause", "offset": [4415, 4423]}, {"key": "insurance-bonds", "type": "clause", "offset": [4425, 4440]}, {"key": "direct-costs", "type": "definition", "offset": [4460, 4472]}, {"key": "overhead-costs", "type": "definition", "offset": [4545, 4559]}, {"key": "benefits-of", "type": "clause", "offset": [4577, 4588]}, {"key": "supervisory-personnel", "type": "clause", "offset": [4589, 4610]}, {"key": "profit-or-fee", "type": "clause", "offset": [4664, 4677]}, {"key": "to-be-added", "type": "clause", "offset": [4811, 4822]}, {"key": "in-lieu-of", "type": "clause", "offset": [4854, 4864]}, {"key": "overhead-and-profit", "type": "clause", "offset": [4865, 4884]}, {"key": "other-expense", "type": "clause", "offset": [4896, 4909]}, {"key": "not-included", "type": "clause", "offset": [4919, 4931]}, {"key": "the-cost-of-the-work", "type": "clause", "offset": [4935, 4955]}, {"key": "defined-above", "type": "clause", "offset": [4982, 4995]}, {"key": "a-subcontractor", "type": "definition", "offset": [5038, 5053]}, {"key": "performed-by", "type": "clause", "offset": [5127, 5139]}, {"key": "own-forces", "type": "definition", "offset": [5146, 5156]}, {"key": "net-decrease", "type": "definition", "offset": [5218, 5230]}, {"key": "reduction-of", "type": "clause", "offset": [5262, 5274]}, {"key": "maximum-percentage", "type": "definition", "offset": [5302, 5320]}, {"key": "as-applied", "type": "definition", "offset": [5328, 5338]}, {"key": "cumulative-percentage", "type": "definition", "offset": [5368, 5389]}, {"key": "inclusive-of", "type": "clause", "offset": [5391, 5403]}, {"key": "contracting-parties", "type": "definition", "offset": [5461, 5480]}, {"key": "the-percentage", "type": "definition", "offset": [5574, 5588]}, {"key": "percentage-increase", "type": "definition", "offset": [5636, 5655]}, {"key": "construction-manager-fee", "type": "clause", "offset": [5675, 5699]}, {"key": "set-out", "type": "definition", "offset": [5700, 5707]}, {"key": "the-cumulative", "type": "clause", "offset": [5906, 5920]}, {"key": "notwithstanding-the", "type": "definition", "offset": [5967, 5986]}, {"key": "inclusion-of", "type": "clause", "offset": [5987, 5999]}, {"key": "option-to", "type": "clause", "offset": [6063, 6072]}, {"key": "require-the", "type": "clause", "offset": [6073, 6084]}, {"key": "to-be-determined", "type": "definition", "offset": [6104, 6120]}, {"key": "other-methods", "type": "clause", "offset": [6135, 6148]}], "samples": [{"hash": "l6awvUnFg4C", "uri": "/contracts/l6awvUnFg4C#changes-to-the-work", "label": "Construction Management Agreement", "score": 19.0, "published": true}, {"hash": "j5D87xjtcOr", "uri": "/contracts/j5D87xjtcOr#changes-to-the-work", "label": "Construction Management Agreement", "score": 19.0, "published": true}, {"hash": "il7PSd5nioA", "uri": "/contracts/il7PSd5nioA#changes-to-the-work", "label": "Construction Management Agreement", "score": 19.0, "published": true}], "hash": "e7930c6fe1eff1eee7845d046078002e", "id": 1}, {"snippet": "The Consultant shall prepare all reasonable changes to Construction Documents as required for the successful completion of the Project as requested by the State, and shall notify the State of additional services, if any, required by the State\u2019s request.", "size": 13, "snippet_links": [{"key": "the-consultant-shall", "type": "clause", "offset": [0, 20]}, {"key": "changes-to-construction-documents", "type": "clause", "offset": [44, 77]}, {"key": "as-required", "type": "clause", "offset": [78, 89]}, {"key": "completion-of-the-project", "type": "clause", "offset": [109, 134]}, {"key": "by-the-state", "type": "clause", "offset": [148, 160]}, {"key": "notify-the", "type": "clause", "offset": [172, 182]}, {"key": "state-of", "type": "definition", "offset": [183, 191]}, {"key": "additional-services", "type": "definition", "offset": [192, 211]}, {"key": "required-by", "type": "definition", "offset": [221, 232]}], "samples": [{"hash": "cXjaSb48jtY", "uri": "/contracts/cXjaSb48jtY#changes-to-the-work", "label": "State/Designer Basic Services Agreement", "score": 34.9723892212, "published": true}, {"hash": "aEGHPGVvG6y", "uri": "/contracts/aEGHPGVvG6y#changes-to-the-work", "label": "State/Designer Basic Services Agreement", "score": 34.800994873, "published": true}, {"hash": "kd7qpRIX8WY", "uri": "/contracts/kd7qpRIX8WY#changes-to-the-work", "label": "State/Designer Basic Services Agreement", "score": 32.0892105103, "published": true}], "hash": "b528036c1af7519caee8b58583135310", "id": 2}, {"snippet": "Company may at any time, in writing, direct or authorize Contractor to make changes to the Work within the general scope of this Agreement. All such changes must be agreed upon and authorized in writing by each Party before Contractor\u2019s implementation thereof. Company shall not be required to make any payment for any change that is not authorized in writing. If any change is performed by Contractor without such written authorization, Company may take the same actions and exercise the same rights and remedies with respect to such change that it would have with respect to any of the Work as though such change were in fact authorized.", "size": 10, "snippet_links": [{"key": "at-any-time", "type": "clause", "offset": [12, 23]}, {"key": "in-writing", "type": "definition", "offset": [25, 35]}, {"key": "contractor-to", "type": "clause", "offset": [57, 70]}, {"key": "make-changes", "type": "clause", "offset": [71, 83]}, {"key": "general-scope-of-this-agreement", "type": "clause", "offset": [107, 138]}, {"key": "by-each-party", "type": "clause", "offset": [203, 216]}, {"key": "payment-for", "type": "clause", "offset": [303, 314]}, {"key": "any-change", "type": "definition", "offset": [315, 325]}, {"key": "by-contractor", "type": "clause", "offset": [388, 401]}, {"key": "written-authorization", "type": "definition", "offset": [415, 436]}, {"key": "and-exercise", "type": "clause", "offset": [472, 484]}, {"key": "rights-and-remedies", "type": "definition", "offset": [494, 513]}, {"key": "with-respect-to", "type": "clause", "offset": [514, 529]}, {"key": "of-the-work", "type": "clause", "offset": [581, 592]}], "samples": [{"hash": "87y1BntQxxk", "uri": "/contracts/87y1BntQxxk#changes-to-the-work", "label": "Standard Services Agreement", "score": 35.2143707275, "published": true}, {"hash": "f9j1PZ19I5C", "uri": "/contracts/f9j1PZ19I5C#changes-to-the-work", "label": "Standard Services Agreement", "score": 34.9977798462, "published": true}, {"hash": "hipSAIWWXOS", "uri": "/contracts/hipSAIWWXOS#changes-to-the-work", "label": "Standard Services Agreement", "score": 33.9030532837, "published": true}], "hash": "0457753c898a7ce6b15c233a03b67d96", "id": 3}, {"snippet": "(a) District may, at any time, by written order, make unilateral changes in the Work. Such changes include, but are not limited to, changes:\n(1) in the Specifications or Plans;\n(2) in the sequence, method, or manner of performance of the Work;\n(3) in the District-furnished facilities, equipment, materials, services or site; or\n(4) directing acceleration of the Work.\n(b) If such changes cause an increase or decrease in Lessor's cost of, or time required for, performance of this Facilities Lease, the District shall order a Change Order. Such Change Orders shall be funded utilizing the District Contingency.\n(c) A change pursuant to this Section 15.01 may begin in the form of a CCD and will result in the form of a Change Order which will set forth the additional, deleted or otherwise changed Work to be done or the method by which the change and cost adjustment, if any, will be determined, and the time of completion of the Work. Upon receipt of a written CCD using the form supplied in these Contract Documents, Lessor shall proceed with the ordered Work. If ordered in writing by the Architect and approved by District, Lessor shall proceed with the Work so ordered prior to actual receipt of a Change Order. A Change Order executed by Contractor and approved by both the Architect and District is an executed Contract Change Order as that term is used throughout this Section. Under no circumstances shall a verbal direction constitute a basis for proceeding with a Change Order. A change to the contract that involves adding time or cost, shall be approved if, and only if, the item is related to unforeseen conditions or owner directed changes. Substitutions are considered change orders and, if DSA approval is required, are to be approved by DSA prior to fabrication or use. All associated costs with a Contractor driven substitution will be at the expense of the Lessor, including DSA fees, Architect fees, Engineering fees, etc.", "size": 8, "snippet_links": [{"key": "at-any-time", "type": "clause", "offset": [18, 29]}, {"key": "written-order", "type": "definition", "offset": [34, 47]}, {"key": "changes-in-the-work", "type": "clause", "offset": [65, 84]}, {"key": "not-limited", "type": "clause", "offset": [116, 127]}, {"key": "the-specifications", "type": "clause", "offset": [148, 166]}, {"key": "performance-of-the-work", "type": "clause", "offset": [219, 242]}, {"key": "the-district", "type": "clause", "offset": [251, 263]}, {"key": "acceleration-of-the-work", "type": "clause", "offset": [343, 367]}, {"key": "increase-or-decrease", "type": "clause", "offset": [398, 418]}, {"key": "cost-of", "type": "definition", "offset": [431, 438]}, {"key": "time-required", "type": "clause", "offset": [443, 456]}, {"key": "this-facilities-lease", "type": "clause", "offset": [477, 498]}, {"key": "district-shall", "type": "clause", "offset": [504, 518]}, {"key": "a-change-order", "type": "clause", "offset": [525, 539]}, {"key": "change-orders", "type": "clause", "offset": [546, 559]}, {"key": "district-contingency", "type": "clause", "offset": [590, 610]}, {"key": "pursuant-to", "type": "definition", "offset": [625, 636]}, {"key": "form-of", "type": "clause", "offset": [673, 680]}, {"key": "work-to-be-done", "type": "clause", "offset": [799, 814]}, {"key": "the-method", "type": "definition", "offset": [818, 828]}, {"key": "cost-adjustment", "type": "clause", "offset": [853, 868]}, {"key": "completion-of-the-work", "type": "definition", "offset": [914, 936]}, {"key": "upon-receipt-of-a", "type": "clause", "offset": [938, 955]}, {"key": "contract-documents", "type": "definition", "offset": [1001, 1019]}, {"key": "ordered-work", "type": "definition", "offset": [1051, 1063]}, {"key": "in-writing", "type": "definition", "offset": [1076, 1086]}, {"key": "the-architect", "type": "definition", "offset": [1090, 1103]}, {"key": "by-district", "type": "clause", "offset": [1117, 1128]}, {"key": "so-ordered", "type": "clause", "offset": [1165, 1175]}, {"key": "prior-to", "type": "definition", "offset": [1176, 1184]}, {"key": "actual-receipt", "type": "clause", "offset": [1185, 1199]}, {"key": "by-contractor", "type": "clause", "offset": [1243, 1256]}, {"key": "contract-change-order", "type": "definition", "offset": [1320, 1341]}, {"key": "no-circumstances", "type": "clause", "offset": [1394, 1410]}, {"key": "change-to", "type": "clause", "offset": [1493, 1502]}, {"key": "the-contract", "type": "clause", "offset": [1503, 1515]}, {"key": "related-to", "type": "definition", "offset": [1598, 1608]}, {"key": "unforeseen-conditions", "type": "definition", "offset": [1609, 1630]}, {"key": "directed-changes", "type": "clause", "offset": [1640, 1656]}, {"key": "associated-costs", "type": "clause", "offset": [1794, 1810]}, {"key": "a-contractor", "type": "clause", "offset": [1816, 1828]}, {"key": "the-lessor", "type": "clause", "offset": [1875, 1885]}, {"key": "dsa-fees", "type": "clause", "offset": [1897, 1905]}, {"key": "engineering-fees", "type": "clause", "offset": [1923, 1939]}], "samples": [{"hash": "hWpXerYI1Np", "uri": "/contracts/hWpXerYI1Np#changes-to-the-work", "label": "Facilities Lease", "score": 35.3465423584, "published": true}, {"hash": "ipxpyHFzzBc", "uri": "/contracts/ipxpyHFzzBc#changes-to-the-work", "label": "Facilities Lease", "score": 35.2945327759, "published": true}, {"hash": "9T3h30On9rf", "uri": "/contracts/9T3h30On9rf#changes-to-the-work", "label": "Facilities Lease", "score": 33.4408912659, "published": true}], "hash": "14ea04eb8a4d2d4ab547eb5909a25b89", "id": 4}, {"snippet": "The Publisher agrees to allow the Author to makes changes in the Work, at the final proof stage, costing up to an amount of Two Hundred Fifty dollars ($250), other than for corrections of compositor's errors. Should the cost of such alterations exceed this sum, the balance will be charged to the Author's royalty account, provided, also, however, that the Publisher shall promptly furnish to the Author an itemized statement of such additional expenses, and shall make available the corrected proofs for inspection by the Author. The Author agrees to correct and return, no later than ten (10) days after the receipt thereof, proofs provided by the Publisher. The Author agrees to deliver to the Publisher final revised copy satisfactory to the Publisher in content and form.", "size": 8, "snippet_links": [{"key": "the-author", "type": "definition", "offset": [30, 40]}, {"key": "changes-in-the-work", "type": "clause", "offset": [50, 69]}, {"key": "the-final", "type": "clause", "offset": [74, 83]}, {"key": "cost-of", "type": "definition", "offset": [220, 227]}, {"key": "balance-will-be-charged", "type": "clause", "offset": [266, 289]}, {"key": "royalty-account", "type": "definition", "offset": [306, 321]}, {"key": "furnish-to", "type": "clause", "offset": [382, 392]}, {"key": "statement-of", "type": "clause", "offset": [416, 428]}, {"key": "additional-expenses", "type": "definition", "offset": [434, 453]}, {"key": "make-available", "type": "definition", "offset": [465, 479]}, {"key": "for-inspection", "type": "clause", "offset": [501, 515]}, {"key": "and-return", "type": "clause", "offset": [560, 570]}, {"key": "days-after", "type": "definition", "offset": [595, 605]}, {"key": "deliver-to", "type": "definition", "offset": [682, 692]}], "samples": [{"hash": "il7nteLrF72", "uri": "/contracts/il7nteLrF72#changes-to-the-work", "label": "Publication Agreement & Copyright License", "score": 24.5263519287, "published": true}, {"hash": "3o8vpHRtLt3", "uri": "/contracts/3o8vpHRtLt3#changes-to-the-work", "label": "Publishing Agreement", "score": 24.1704311371, "published": true}, {"hash": "lGfS0kCFUBJ", "uri": "/contracts/lGfS0kCFUBJ#changes-to-the-work", "label": "Publishing Agreement", "score": 19.0, "published": true}], "hash": "c8ef8771497ec2b5d1341a4facb2835f", "id": 5}, {"snippet": "The District may, by written order, make Changes to the Work, issue additional instructions and to add to or delete from the Work. No Change may be made without the prior written approval and direction of the District. Adjustments of the Contract Price or the Contract Time on account of a Change authorized hereunder will only be made by written Change Order duly executed by the Contractor and the District Representative. Adjustments to the Contract Price for authorized Changes shall be limited to the actual costs of labor and materials necessary to complete the Change plus a \u2587\u2587\u2587\u2587-up of fifteen percent (15%) of the actual costs of labor and materials; it being agreed that the \u2587\u2587\u2587\u2587-up represents all compensation due the Contractor for profit, overhead/administrative costs and impacts of an authorized Change.", "size": 7, "snippet_links": [{"key": "written-order", "type": "definition", "offset": [21, 34]}, {"key": "make-changes", "type": "clause", "offset": [36, 48]}, {"key": "additional-instructions", "type": "clause", "offset": [68, 91]}, {"key": "add-to", "type": "clause", "offset": [99, 105]}, {"key": "no-change", "type": "definition", "offset": [131, 140]}, {"key": "prior-written-approval", "type": "definition", "offset": [165, 187]}, {"key": "of-the-district", "type": "clause", "offset": [202, 217]}, {"key": "the-contract-time", "type": "clause", "offset": [256, 273]}, {"key": "a-change", "type": "clause", "offset": [288, 296]}, {"key": "written-change-order", "type": "clause", "offset": [339, 359]}, {"key": "the-contractor-and-the", "type": "clause", "offset": [377, 399]}, {"key": "district-representative", "type": "definition", "offset": [400, 423]}, {"key": "adjustments-to-the-contract-price", "type": "clause", "offset": [425, 458]}, {"key": "authorized-changes", "type": "clause", "offset": [463, 481]}, {"key": "costs-of", "type": "definition", "offset": [513, 521]}, {"key": "labor-and-materials", "type": "clause", "offset": [522, 541]}, {"key": "complete-the", "type": "clause", "offset": [555, 567]}, {"key": "a-\u2587", "type": "clause", "offset": [580, 583]}, {"key": "agreed-that", "type": "clause", "offset": [668, 679]}, {"key": "the-\u2587", "type": "clause", "offset": [680, 685]}, {"key": "compensation-due", "type": "clause", "offset": [707, 723]}, {"key": "for-profit", "type": "definition", "offset": [739, 749]}, {"key": "administrative-costs", "type": "clause", "offset": [760, 780]}], "samples": [{"hash": "kzmyPi0Icix", "uri": "/contracts/kzmyPi0Icix#changes-to-the-work", "label": "Contract for Labor and Materials", "score": 24.3073234558, "published": true}, {"hash": "kpsNGQ92hSZ", "uri": "/contracts/kpsNGQ92hSZ#changes-to-the-work", "label": "Contract for Labor and Materials", "score": 24.3073234558, "published": true}, {"hash": "k8DGfbj43ku", "uri": "/contracts/k8DGfbj43ku#changes-to-the-work", "label": "Contract for Labor and Materials", "score": 23.1177272797, "published": true}], "hash": "f86dad82627d4dcb8668e531799107f9", "id": 6}, {"snippet": "A. When Architect establishes that the method of valuation for Changes in the Work will be net cost plus a percentage fee in accordance with General Conditions, our percentage fee will be:", "size": 7, "snippet_links": [{"key": "method-of-valuation", "type": "definition", "offset": [39, 58]}, {"key": "changes-in-the-work", "type": "clause", "offset": [63, 82]}, {"key": "cost-plus", "type": "clause", "offset": [95, 104]}, {"key": "percentage-fee", "type": "definition", "offset": [107, 121]}, {"key": "in-accordance-with", "type": "definition", "offset": [122, 140]}, {"key": "general-conditions", "type": "definition", "offset": [141, 159]}], "samples": [{"hash": "8sYJc5nD875", "uri": "/contracts/8sYJc5nD875#changes-to-the-work", "label": "Bid Form", "score": 27.4047336578, "published": true}, {"hash": "1Td2Nw2VcPL", "uri": "/contracts/1Td2Nw2VcPL#changes-to-the-work", "label": "Bid Form", "score": 23.6160163879, "published": true}], "hash": "240ede251871b378b208bf3e588cedb2", "id": 7}, {"snippet": "Siemens shall deliver and/or perform the Work in accordance with the Applicable Laws in effect on the Effective Date. No change will be made to the scope of Work unless \u2587\u2587\u2587\u2587\u2587 and Siemens agree in writing to the change and any resulting price, schedule or other contractual modifications associated therewith. If any change to any law, rule, regulation, order, code, standard or requirement impacts Siemens\u2019 obligations or performance under this Agreement, Siemens may request a change order for an equitable adjustment in the price and time of performance.", "size": 6, "snippet_links": [{"key": "the-work", "type": "definition", "offset": [37, 45]}, {"key": "in-accordance-with", "type": "definition", "offset": [46, 64]}, {"key": "on-the-effective-date", "type": "clause", "offset": [95, 116]}, {"key": "no-change", "type": "definition", "offset": [118, 127]}, {"key": "the-scope-of-work", "type": "clause", "offset": [144, 161]}, {"key": "in-writing", "type": "definition", "offset": [193, 203]}, {"key": "resulting-price", "type": "definition", "offset": [226, 241]}, {"key": "change-to", "type": "clause", "offset": [316, 325]}, {"key": "performance-under-this-agreement", "type": "definition", "offset": [422, 454]}, {"key": "a-change-order", "type": "clause", "offset": [476, 490]}, {"key": "equitable-adjustment", "type": "definition", "offset": [498, 518]}, {"key": "the-price", "type": "clause", "offset": [522, 531]}, {"key": "time-of-performance", "type": "clause", "offset": [536, 555]}], "samples": [{"hash": "fcGtxp7mezT", "uri": "/contracts/fcGtxp7mezT#changes-to-the-work", "label": "Standard Terms and Conditions", "score": 33.8723602295, "published": true}, {"hash": "kvW9eZCtagk", "uri": "/contracts/kvW9eZCtagk#changes-to-the-work", "label": "Standard Terms and Conditions", "score": 27.3915119171, "published": true}, {"hash": "6pLS2Mm7DD0", "uri": "/contracts/6pLS2Mm7DD0#changes-to-the-work", "label": "Standard Terms and Conditions", "score": 27.3915119171, "published": true}], "hash": "075ebd9403a8633e866b1c6bd0385cba", "id": 8}, {"snippet": "The City and TriMet recognize and acknowledge that there may be changes required to the plans and specifications during construction. \u2022 TriMet and the City agree to make timely responses as appropriate and required to keep the work progressing.", "size": 5, "snippet_links": [{"key": "the-city", "type": "clause", "offset": [0, 8]}, {"key": "plans-and-specifications", "type": "clause", "offset": [88, 112]}, {"key": "during-construction", "type": "clause", "offset": [113, 132]}, {"key": "agree-to", "type": "clause", "offset": [156, 164]}, {"key": "timely-responses", "type": "clause", "offset": [170, 186]}, {"key": "the-work", "type": "definition", "offset": [223, 231]}], "samples": [{"hash": "Fbdmq3V09h", "uri": "/contracts/Fbdmq3V09h#changes-to-the-work", "label": "Intergovernmental Agreement", "score": 31.4451351166, "published": true}, {"hash": "hIMk9wuyQ8y", "uri": "/contracts/hIMk9wuyQ8y#changes-to-the-work", "label": "Intergovernmental Agreement", "score": 30.4476718903, "published": true}, {"hash": "5dvDExNnNyf", "uri": "/contracts/5dvDExNnNyf#changes-to-the-work", "label": "Intergovernmental Agreement", "score": 29.7688045502, "published": true}], "hash": "74c88aa9d50320646a6a58a2210dcc62", "id": 9}, {"snippet": "Subcontractor may be required by Contractor, without invalidating this Agreement or the applicable Statement of Work, to make changes to the Work within the general scope of the Statement of Work. The Contract Price and schedule shall only be adjusted accordingly by written agreement with the Contractor (a \u201cChange Order\u201d). Upon Contractor\u2019s issuance of a Change Order, Subcontractor shall promptly perform the Work as altered by the Change Order. Subcontractor shall give Contractor written notice, including a complete detailed breakdown, of any request to change the schedule or Contract Price within three (3) days of any Change Order. Subcontractor\u2019s failure to provide such written notice shall waive any such claim to adjust the schedule or Contract Price. If Contractor and Subcontractor do not agree on the amount of a requested change to the Contract Price, it is agreed that the Subcontractor shall be entitled to an amount equal to Subcontractor\u2019s actual costs plus fifteen percent (15%) for reasonable overhead and profits. Subcontractor acknowledges that Contractor\u2019s signing of labor and materials slips shall be for verification purposes only, and shall not be construed as approval of Subcontractor\u2019s request for adjustment.", "size": 4, "snippet_links": [{"key": "by-contractor", "type": "clause", "offset": [30, 43]}, {"key": "without-invalidating", "type": "clause", "offset": [45, 65]}, {"key": "agreement-or", "type": "definition", "offset": [71, 83]}, {"key": "the-applicable", "type": "clause", "offset": [84, 98]}, {"key": "statement-of-work", "type": "clause", "offset": [99, 116]}, {"key": "make-changes", "type": "clause", "offset": [121, 133]}, {"key": "the-statement", "type": "clause", "offset": [174, 187]}, {"key": "price-and-schedule", "type": "clause", "offset": [210, 228]}, {"key": "by-written-agreement", "type": "clause", "offset": [264, 284]}, {"key": "the-contractor", "type": "definition", "offset": [290, 304]}, {"key": "a-change-order", "type": "clause", "offset": [355, 369]}, {"key": "subcontractor-shall", "type": "clause", "offset": [371, 390]}, {"key": "the-change-order", "type": "clause", "offset": [431, 447]}, {"key": "written-notice", "type": "definition", "offset": [485, 499]}, {"key": "the-schedule", "type": "clause", "offset": [567, 579]}, {"key": "any-change", "type": "definition", "offset": [623, 633]}, {"key": "failure-to-provide", "type": "clause", "offset": [657, 675]}, {"key": "contractor-and-subcontractor", "type": "clause", "offset": [768, 796]}, {"key": "do-not-agree", "type": "clause", "offset": [797, 809]}, {"key": "change-to", "type": "clause", "offset": [839, 848]}, {"key": "it-is-agreed-that", "type": "clause", "offset": [869, 886]}, {"key": "the-subcontractor", "type": "clause", "offset": [887, 904]}, {"key": "equal-to", "type": "definition", "offset": [936, 944]}, {"key": "actual-costs", "type": "definition", "offset": [961, 973]}, {"key": "signing-of", "type": "clause", "offset": [1083, 1093]}, {"key": "labor-and-materials", "type": "clause", "offset": [1094, 1113]}, {"key": "approval-of", "type": "clause", "offset": [1191, 1202]}, {"key": "request-for", "type": "definition", "offset": [1219, 1230]}], "samples": [{"hash": "jS0olj7122U", "uri": "/contracts/jS0olj7122U#changes-to-the-work", "label": "Master Subcontractor Agreement", "score": 29.9166221619, "published": true}, {"hash": "OpkpYDvMo4", "uri": "/contracts/OpkpYDvMo4#changes-to-the-work", "label": "Master Subcontractor Agreement", "score": 26.2594985962, "published": true}, {"hash": "gcEnqwK2nYo", "uri": "/contracts/gcEnqwK2nYo#changes-to-the-work", "label": "Master Subcontractor Agreement", "score": 23.0786781311, "published": true}], "hash": "c7734c14def3bfcfb821898c84c7f451", "id": 10}], "next_curs": "ClwSVmoVc35sYXdpbnNpZGVyY29udHJhY3RzcjgLEhZDbGF1c2VTbmlwcGV0R3JvdXBfdjU2IhxjaGFuZ2VzLXRvLXRoZS13b3JrIzAwMDAwMDBhDKIBAmVuGAAgAA==", "clause": {"title": "Changes to the Work", "children": [["", ""], ["change-orders", "Change Orders"], ["contractor-claims", "Contractor Claims"], ["unit-price-work", "Unit Price Work"], ["form-and-execution-of-change-orders", "Form and Execution of Change Orders"]], "size": 156, "parents": [["construction-phase", "Construction Phase"], ["full-agreement", "Full Agreement"], ["contract-forms", "Contract Forms"], ["challenges-to-transaction", "Challenges to Transaction"], ["time-of-performance", "Time of Performance"]], "id": "changes-to-the-work", "related": [["changes-to-the-website", "Changes to the Website", "Changes to the Website"], ["changes-to-the-terms", "Changes to the Terms", "Changes to the Terms"], ["changes-to-the-parties", "Changes to the Parties", "Changes to the Parties"], ["changes-to-the-contract", "CHANGES TO THE CONTRACT", "CHANGES TO THE CONTRACT"], ["changes-to-the-terms-of-use", "Changes to the Terms of Use", "Changes to the Terms of Use"]], "related_snippets": [], "updated": "2025-07-26T06:21:28+00:00", "also_ask": [], "drafting_tip": null, "explanation": "The \"Changes to the Work\" clause defines the process by which modifications to the scope, nature, or details of the contracted work can be made after the agreement is in effect. Typically, this clause outlines who has the authority to request changes, the procedure for documenting and approving such changes, and how adjustments to cost, schedule, or deliverables will be handled. Its core function is to provide a structured mechanism for managing alterations to the original agreement, ensuring that both parties have clarity and mutual consent regarding any deviations from the initial work plan."}, "json": true, "cursor": ""}}