Changes to Guaranteed Project Cost Sample Clauses

Changes to Guaranteed Project Cost. 4.1. As indicated in the Master Facilities Lease, the Parties may add or remove specific scopes of work from the Project. Based on these change(s), the Parties may agree to a reduction or increase in the Guaranteed Project Cost. If a cost impact or a change is agreed to by the Parties, it shall be reflected as a reduction or increase in the Tenant Improvement Payments and paid upon the payment request from the Developer when the work is performed, or deducted from the next payment request from the Developer, as applicable.
Changes to Guaranteed Project Cost. 5.1. As indicated in the Facilities Lease, the Parties may add or remove specific scopes of work from the Project. Based on these change(s), the Parties may agree to a reduction or increase in the Guaranteed Project EXHIBITS to Master Facilities Lease: Page 6 [District] – [Project]

Related to Changes to Guaranteed Project Cost

  • Project Cost Overruns In the event that the Recipient determines that the moneys granted pursuant to Section II hereof, together with the Local Subdivision Contribution, are insufficient to pay in full the costs of the Project, the Recipient may make a request for supplemental assistance to its District Committee. The Recipient must demonstrate that such funding is necessary for the completion of the Project and the cost overrun was the result of circumstances beyond the Recipient's control, that it could not have been avoided with the exercise of due care, and that such circumstances could not have been anticipated at the time of the Recipient's initial application. Should the District Committee approve such request the action shall be recorded in the District Committee's official meeting minutes and provided to the OPWC Director for the execution of an amendment to this Agreement.

  • Project Cost An updated cost spreadsheet reflecting the current forecasted cost vs. the latest approved budget vs. the baseline budget should be included in this section. One way to track project cost is to show: (1) Baseline Budget, (2) Latest Approved Budget, (3) Current Forecasted Cost Estimate, (4) Expenditures or Commitments to Date, and (5) Variance between Current Forecasted Cost and Latest Approved Budget. Line items should include all significant cost centers, such as prior costs, right-of-way, preliminary engineering, environmental mitigation, general engineering consultant, section design contracts, construction administration, utilities, construction packages, force accounts/task orders, wrap-up insurance, construction contingencies, management contingencies, and other contingencies. The line items can be broken-up in enough detail such that specific areas of cost change can be sufficiently tracked and future improvements made to the overall cost estimating methodology. A Program Total line should be included at the bottom of the spreadsheet. Narratives, tables, and/or graphs should accompany the updated cost spreadsheet, basically detailing the current cost status, reasons for cost deviations, impacts of cost overruns, and efforts to mitigate cost overruns. The following information should be provided:

  • Project Costs A. If the Program shown on Attachment A is receiving federal-aid funds for the project, the LPA is allocated the funds through the MPO as written in their fiscally constrained TIP. Any adjustments (positive or negative) to the dollar amount listed in the TIP are hereby considered adjustments to the contract between the LPA and INDOT, as the MPO must maintain fiscal constraint for all projects listed. Federal funds made available to the LPA by INDOT will be used to pay % of the eligible Project costs. The maximum amount of federal-aid funds allocated to the Project is $ . OR

  • Construction Contract; Cost Budget Prior to execution of a construction contract, Tenant shall submit a copy of the proposed contract with the Contractor for the construction of the Tenant Improvements, including the general conditions with Contractor (the “Contract”) to Landlord for its approval, which approval shall not be unreasonably withheld, conditioned or delayed. Following execution of the Contract and prior to commencement of construction, Tenant shall provide Landlord with a fully executed copy of the Contract for Landlord’s records. Prior to the commencement of the construction of the Tenant Improvements, and after Tenant has accepted all bids and proposals for the Tenant Improvements, Tenant shall provide Landlord with a detailed breakdown, by trade, for all of Tenant’s Agents, of the final estimated costs to be incurred or which have been incurred in connection with the design and construction of the Tenant Improvements to be performed by or at the direction of Tenant or the Contractor (the “Construction Budget”), which costs shall include, but not be limited to, the costs of the Architect’s and Engineers’ fees and the Landlord Coordination Fee. The amount, if any, by which the total costs set forth in the Construction Budget exceed the amount of the Tenant Improvement Allowance is referred to herein as the “Over Allowance Amount”. In the event that an Over-Allowance Amount exists, then prior to the commencement of construction of the Tenant Improvements, Tenant shall supply Landlord with cash in an amount equal to the Over-Allowance Amount. The Over-Allowance Amount shall be disbursed by Landlord prior to the disbursement of any of the then remaining portion of the Tenant Improvement Allowance, and such disbursement shall be pursuant to the same procedure as the Tenant Improvement Allowance. In the event that, after the total costs set forth in the Construction Budget have been delivered by Tenant to Landlord, the costs relating to the design and construction of the Tenant Improvements shall change, any additional costs for such design and construction in excess of the total costs set forth in the Construction Budget shall be added to the Over-Allowance Amount and the total costs set forth in the Construction Budget, and such additional costs shall be paid by Tenant to Landlord immediately as an addition to the Over-Allowance Amount or at Landlord’s option, Tenant shall make payments for such additional costs out of its own funds, but Tenant shall continue to provide Landlord with the documents described in items (i), (ii), (iii) and (iv) of Section 2.2.2.1 of this Tenant Work Letter, above, for Landlord’s approval, prior to Tenant paying such costs. All Tenant Improvements paid for by the Over-Allowance Amount shall be deemed Landlord’s property under the terms of the Lease.

  • Total Project Cost The total cost of the Project is $3,407,752, of which (i) Grantee is contributing $1,670,252 toward the Project as shown in the Budget (the “Matching Funds”), and (ii) $1,737,500 shall be provided by the Grant. The total estimated cost of the Project is based upon the Budget. To the extent that the actual cost of the Project exceeds $3,407,752, Grantee shall be solely responsible for such excess. Grantee shall monitor the Budget and submit an amended Budget to Triumph in the event that (a) the total cost of the Project increases or decreases by greater than five percent (5%), (b) total the Budget increases or decreases by greater than five percent (5%), (c) the Budget increases or decreases by greater than five percent (5%) within a particular Budget category, and/or (d) Grantee’s portion of the Matching funds decreases by greater than five percent (5%). If Grantee proposes an increase or decrease by greater than five percent (5%) as described above as compared to the most recently approved Budget, such proposal shall be submitted to Triumph in writing along with a proposed amended Budget, and Triumph shall have the right to approve or disapprove both the proposed Budget category increase or decrease and the proposed amended Budget. Triumph shall have fifteen (15) days from the receipt of a proposed amended Budget to notify Grantee of its approval or disapproval. If Triumph fails to approve or disapprove the proposed Budget category increase or decrease and/or the proposed amended Budget within such fifteen (15) day period, the proposed Budget category increase or decrease and/or the amended Budget, as applicable, shall be deemed approved as submitted. If Grantee fails to obtain Triumph's approval or deemed approval, that failure shall be sufficient cause for nonpayment by Triumph as provided in Section 4.2(f). Using the Grant, its own funds, and funds from other grants (including, but not limited to, the Matching Funds), Grantee agrees to bear the entire cost and expense of the Project, including but not limited to, all costs and all expenses in excess of the total estimated cost of the Project, it being expressly understood and agreed that the Grant shall operate only to pay, on and subject to the terms and conditions set forth herein, a portion of the costs and expenses of the Project. Furthermore, Grantee agrees to spend all of the Matching Funds as contemplated in the Grant Application, and agrees that its failure to do so shall be deemed a material breach of this Agreement.

  • Notice to Proceed - Site Improvements The Recipient shall not commence, or cause to be commenced, any site improvements or other work on the Land until the Director has issued a Notice to Proceed to the Recipient. Such Notice to Proceed will not be issued until the Director is assured that the Recipient has complied with all requirements for the approval of a grant under Revised Code Sections 164.20 through 164.27 and has completed any land acquisition required by the Project. A Notice to Proceed shall be required for all Project prime contractors or direct procurement initiated by the Recipient following execution of this Agreement.

  • Construction Budget The total amount indicated by the District for the Project plus all other costs, including design, construction, administration, financing, and all other costs.

  • Tenant Improvement Allowance Items Except as otherwise set forth in this Tenant Work Letter, the Tenant Improvement Allowance shall be disbursed by Landlord only for the following items and costs (collectively the “Tenant Improvement Allowance Items”):

  • Cost Overruns The Borrower shall ensure that all cost-overruns over the estimated construction costs of the Project as certified by a quantity surveyor or the Architect or as ascertained by the Lender as and when they occur shall be funded by the Borrower’s own equity;

  • Disbursement of the Tenant Improvement Allowance Except as otherwise set forth in this Tenant Work Letter, the Tenant Improvement Allowance shall be disbursed by Landlord (each of which disbursement shall be made pursuant to Landlord’s standard disbursement process), only for the following items and costs (collectively, the “Tenant Improvement Allowance Items”):