Certificates of Substantial Completion Sample Clauses

Certificates of Substantial Completion. Certificates of Substantial Completion signed by the Contractor, Inspector and Borrower.
AutoNDA by SimpleDocs
Certificates of Substantial Completion. The City shall issue a certificate of substantial completion at such time that the Public Project Improvements are sufficiently complete in accordance with the applicable construction specifications so that the Public Project Improvements are functional and can be utilized for their intended use (herein “Substantial Completion”); provided that, the City has received all required approvals, licenses, and other documents from any other governmental authority having jurisdiction over the Public Project Improvements. Developer shall send City not less than ten (10) days’ advance notice of Substantial Completion of the Public Project Improvements. City shall provide Developer with a detailed written notice of the reasons for objection to the Substantial Completion of the Public Project Improvements within such ten (10) day period. In the event no objections are received by Developer, Substantial Completion shall be deemed to have occurred on the date of Substantial Completion set forth in the Developer’s notice provided as set forth above. In the event objections are made by the City, Developer shall proceed to correct the deficiency in accordance with the Developer Public Project Plans and the foregoing procedure shall be repeated until the deficiency is corrected and the City approves the Substantial Completion in accordance with the foregoing procedure. Upon request of Developer, City shall provide verification in writing of Substantial Completion.
Certificates of Substantial Completion. In connection with each Sub-Loan, Lender shall have received payment applications from the Contractor, Inspector and Borrower for all Work performed to date.
Certificates of Substantial Completion. Any determination by the Consultant and the Design/Builder of Substantial Completion shall not be binding on the Village, and the ultimate determination of Substantial Completion shall rest with the Village and shall be evidenced by the Village’s executing and returning to the Design/Builder its Certificate(s) of Substantial Completion (or Notice of Partial Substantial Completion, as applicable).
Certificates of Substantial Completion. 62 18.13 Compliance.....................................................62 18.14 Lien Waivers, etc..............................................62 18.15
Certificates of Substantial Completion. Lender shall have received Certificates of Substantial Completion from the Contractor, Inspector and Borrower for all Work performed to date.
Certificates of Substantial Completion. Certificates of Substantial Completion will be issued individually for the Starbucks Development, the Panera Development and the South Parcel Development, upon Purchaser’s satisfaction of the requirements set forth in Section 3.1.3 as they apply to each individual parcel. Each such Certificate of Completion will apply to all common elements that may be utilized in connection with the Starbucks Development, the Panera Development and or the South Parcel Development, as the case may be, including, without limitation, shared utility lines and equipment, storm water detention and drainage facilities, common access roads, aisles and paths, and common signage.
AutoNDA by SimpleDocs
Certificates of Substantial Completion 

Related to Certificates of Substantial Completion

  • Certificate of Substantial Completion The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the City when construction is sufficiently complete, in accordance with the Contract Documents, so the City of Roanoke, Virginia (City or Owner) can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents. ITB NO.: PROJECT: CONTRACTOR: PROJECT OR DESIGNATED PORTION SHALL INCLUDE: . The Work or portion thereof designated above performed under this Contract has been reviewed and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is hereby established as . The City will assume possession thereof at a.m./p.m. on that date. A list of items ("punch list"), prepared by the A/E and/or Director, Department of Public Works, to be completed or corrected by the Contractor, is attached hereto. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. The Contractor will complete any portion of the Work that is not substantially complete and will complete or correct the work on the punch list in accordance with the Contract Documents. The establishment of a date of substantial completion and/or the acceptance of the Work or designated portion thereof does not relieve the Contractor of any responsibility for any faulty materials or workmanship or operate to relieve the Contractor or its Surety from any obligation under the Contract with the City or the Performance Bond or Labor and Material Payment Bond. This Certificate is subject to the terms and conditions of the Contract Documents, including but not limited to Section 20.8 of the General Conditions. Contractor By Date City of Roanoke, Virginia City By Date CITY OF ROANOKE, VIRGINIA AFFIDAVIT OF PAYMENT OF CLAIMS By: (Insert Exact Name and Address of Firm) This day personally appeared before me, , a Notary Public in and for the City (County) of , and, being by me first duly sworn states that all subcontractors and suppliers of labor and materials have been paid all sums due them for work performed or materials furnished in the performance of the Contract between the City of Roanoke, Virginia, and ,Contractor, dated , 20 , for or arrangements have been made by the Contractor satisfactory to such subcontractors and suppliers with respect to the payment of such sums as may be due from the Contractor to the subcontractors and suppliers. CONTRACTOR: BY: PRINTED OR TYPED NAME AND TITLE: COMMONWEALTH OF VIRGINIA CITY/COUNTY OF I, , a Notary Public in and for the Commonwealth of Virginia, do hereby certify that , whose name is signed to the foregoing, has subscribed, sworn to and acknowledged the same before me this day of , 20 . Seal: Notary Public Registration #: My Commission Expires: CITY OF ROANOKE, VIRGINIA

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Certificates of Occupancy To the extent the same are in Seller’s possession, original or photocopies of certificates of occupancy for all space within the Improvements located on the Property;

  • Certificate of Completion The Interconnection Customer shall provide the EDC with a completed copy of the Interconnection Agreement Certificate of Completion, including evidence of the electrical inspection performed by the local authority having jurisdiction. The evidence of completion of the electrical inspection may be provided on inspection forms used by local inspecting authorities. The Interconnection request shall not be finally approved until the EDC’s representative signs the Interconnection Agreement Certificate of Completion.

  • Certificates of Compliance The Company shall provide, from time to time upon request of the Dealer Manager, certificates of its chief executive officer and chief financial officer of compliance by the Company of the requirements of this Agreement.

  • Tenant Estoppel Certificates (a) Seller agrees from and after receipt of the Assumption Approval as set forth in Section 9.1 and provided this Agreement is in full force and effect, within five (5) business days after being requested by Purchaser to do so, to deliver to all tenants of the Property a request for an estoppel certificate in the form of EXHIBIT D attached hereto, which form may be revised if so requested by the Existing Lender. The parties agree that, subject to the provisions of subparagraph (b) below, it shall be a condition to Purchaser's obligation to close under this Agreement that an estoppel certificate either substantially in the form of EXHIBIT D or in the form required by a tenant's Lease, dated not earlier than ten (10) business days prior to the Closing Date, be delivered to Purchaser no later than five (5) business days before Closing from tenants under the Leases occupying, in the aggregate, not less than 75% of the rentable area of the Property, including all tenants occupying at least a full floor or more of space (a "TENANT ESTOPPEL"), Seller agrees to use good faith efforts to obtain such Tenant Estoppels, provided however, Seller shall not be obligated to pay tenants in order to do so. Notwithstanding the foregoing, if at Closing Seller delivers such Tenant Estoppels from tenants occupying at least 60% of the rentable area of the Property, Seller may execute and deliver to Purchaser, at Closing, its own certificate with respect to tenants occupying up to an additional 15% of the rentable area of the Property (substantially in the form of EXHIBIT D or in the form required by a tenant's Lease, appropriately modified to reflect that they are certificates of Seller and made to Seller's knowledge; hereinafter, the "SELLER'S ESTOPPEL CERTIFICATE") and the statements of Seller contained therein shall survive the Closing until the earlier of (a) one hundred and eighty (180) days after Closing, or (b) the date Purchaser obtains an estoppel certificate from a tenant for whom Seller delivered a Seller's Estoppel Certificate.

  • Completion of Improvements Within 90 days of completion of any construction herein permitted, Company will cause to be prepared and delivered to Authority record documents as required under the Tenant Work Permit process, including but not limited to as-builts, legal descriptions, boundary surveys, and certified final cost of construction. The submission of record document electronic media will be in accordance with Authority’s Standard Procedure for computer aided design and drafting and drawings, as may be revised from time to time.

  • Completion of Repairs Borrower will commence any Repairs as soon as practicable after the date of this Loan Agreement and will diligently proceed with and complete such Repairs on or before the Completion Date. All Repairs and Capital Replacements will be completed in a good and workmanlike manner, with suitable materials, and in accordance with good building practices and all applicable laws, ordinances, rules, regulations, building setback lines and restrictions applicable to the Mortgaged Property. Borrower agrees to cause the replacement of any material or work that is defective, unworkmanlike or that does not comply with the requirements of this Loan Agreement, as determined by Lender.

Time is Money Join Law Insider Premium to draft better contracts faster.