Baseline Schedule. Unless otherwise stated in Exhibit 1, within ninety (90) days of Design-Builder’s receipt of Department’s Notice to Proceed, Design-Builder shall submit to Department, for its review and approval, a Baseline Schedule in accordance with Exhibit 11.1.Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Payment until such time Design-Builder furnishes an approved Baseline Schedule.
Appears in 3 contracts
Baseline Schedule. Unless otherwise stated in Exhibit 1, within Within ninety (90) days of Design-Builder’s receipt of Department’s the Notice to Proceed, Design-Builder shall submit to Department, for its review and approval, a Baseline Schedule in accordance with Exhibit 11.1.Department 17. Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Payment until such time Design-Builder furnishes an approved Baseline Schedule.
Appears in 1 contract
Samples: Comprehensive Agreement
Baseline Schedule. Unless otherwise stated in Exhibit 1, within ninety sixty (9060) days of Design-Builder’s receipt of Department’s Notice to Proceed, Design-Builder shall submit to Department, for its review and approval, a Baseline Schedule in accordance with Exhibit 11.1.Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Payment until such time Design-Builder furnishes an approved Baseline Schedule.accordance
Appears in 1 contract
Samples: Agreement
Baseline Schedule. Unless otherwise stated in Exhibit 1, within ninety (90) days of Design-Builder’s receipt of Department’s Notice to Proceed, Design-Builder shall submit to Department, for its review and approval, a Baseline Schedule in accordance with Exhibit 11.1.Department reserves the right to withhold approval for all or part of Design-Builder’s Applications for Payment until such time Design-Builder furnishes an approved Baseline Schedule.accordance
Appears in 1 contract
Samples: Agreement