As-Builts Sample Clauses

As-Builts. Seller shall provide final as-built drawings of the Seller-Owned Interconnection Facilities within 30 Days of the successful completion of the Acceptance Test.
AutoNDA by SimpleDocs
As-Builts. Digitally prepared and reproducible drawings using the web- based ProCore application, or comparable, to be prepared on a monthly basis pursuant to the Contract Documents, that reflect changes made during the performance of the Work, recording differences between the original design of the Work and the Work as constructed since the preceding monthly submittal. See Record Drawings.
As-Builts. Throughout the duration of the Project, Contractor shall maintain on a current basis an accurate and complete set of As-Built Drawings (and Annotated Specifications) clearly showing all changes, revisions to specifications and substitutions during construction, including, without limitation, field changes and the final location of all electrical and mechanical equipment, utility lines, ducts, outlets, structural members, walls, partitions, and other significant features. In case a specification allows Contractor to elect one of several brands, makes, or types of material or equipment, the annotations shall show which of the allowable items the Contractor has furnished. The Contractor will update the As-Built Drawings and Annotated Specifications as often as necessary to keep them current, but no less often than weekly.
As-Builts. Digitally prepared and reproducible drawings to be prepared on a periodic basis pursuant to the Contract Documents, that reflect changes made during the performance of the Work, recording differences between the original design of the Work and the Work as constructed since the preceding monthly submittal. See Record Drawings.
As-Builts. Upon completion of the construction and installation of the Facility, the Licensee shall promptly provide the City with one set of reproducible as-built, record drawings, reflecting construction and installation as actually accomplished.
As-Builts. The Contractor shall within ninety (90) days of the completion of the construction or installation of the pipeline(s) within the Municipal Road right-of-way or allowance shall provide the Municipality with as-built drawings for each pipeline crossing location indicating the as-built location and depth of pipeline relative to the road allowance and the structure within to the satisfaction of the Municipality.
As-Builts. Digitally prepared and reproducible drawings using the District’s Project Management System, to be prepared on a monthly basis pursuant to the Contract Documents, that reflect changes made during the performance of the Work, recording differences between the original design of the Work and the Work as constructed since the preceding monthly submittal. See Record Drawings.
AutoNDA by SimpleDocs
As-Builts. (As-built Drawings and Specifications). The term “As-builts” shall mean the marked-up version of the Contract Documents prepared by the construction Contractor to record as-built conditions, current changes, and selections made during construction.
As-Builts. Consultant shall compile an “As-Built” plan set on final plans during the Project closeout phase. The Project’s construction as-built plan is compiled by the contractor, provided to the City then provided to the Consultant for “As-Built” plan completion.
As-Builts. Contractor must provide redlined as-builts prior to Final Acceptance. As-builts should be provided in electronic format.