Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The application shall be notarized, if required, and supported by all data substantiating the Contractor’s right to payment that the Owner or Architect require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and shall reflect retainage if provided for in the Contract Documents.
Appears in 9 contracts
Samples: Remodeling Agreement, go.boarddocs.com, www.gov.bm
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared for operations completed in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s 's right to payment that as the Owner or Architect may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect reflecting retainage if provided for in the Contract Documents.
Appears in 2 contracts
Samples: Immunicon Corp, Empire Resorts Inc
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s right to payment that as the Owner or Architect may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect retainage if provided for in the Contract Documents.
Appears in 2 contracts
Samples: bidcondocs.delaware.gov, www.fitnyc.edu
Applications for Payment. § 9.3.1 15.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.215.1, for completed portions of the Work. The application shall be notarized, if required, and ; be supported by all data substantiating the Contractor’s right to payment that the Owner or Architect require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and ; shall reflect retainage if provided for in the Contract Documents.; and include any revised cost control information required by Section
Appears in 2 contracts
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared for operations completed in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s 's right to payment that as the Owner or Architect may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect reflecting retainage if provided for elsewhere in the Contract Documents.
Appears in 2 contracts
Applications for Payment. § 9.3.1 At least ten thirty [30] business days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The application shall be notarized, if required, and supported by all data substantiating the Contractor’s right to payment that the Owner or Architect require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and shall reflect retainage if provided for in the Contract Documents.
Appears in 1 contract
Samples: www.lexpublib.org
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect Engineer an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s right to payment that as the Owner or Architect Engineer may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect retainage if provided for in the Contract Documents.
Appears in 1 contract
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect and the Owner an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s right to payment that as the Owner or Architect may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect retainage if provided for in the Contract Documents.
Appears in 1 contract
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The application shall be notarized, if required, and supported by all data substantiating the Contractor’s right to payment that the Owner or Architect require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and shall reflect retainage if provided for in the Contract Documentsretainage.
Appears in 1 contract
Samples: agenda.webbcountytx.gov:8085
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, .. for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s 's right to payment that as the Owner or Architect may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect retainage if provided for in the Contract Documents.
Appears in 1 contract
Samples: STAMPS.COM Inc
Applications for Payment. § 9.3.1 At least ten 10 working days before the date established for each progress payment, the Contractor shall submit to the Architect Design Agent and the Owner for approval an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, values for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s right to payment that as the Owner or Architect the Design Agent may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect retainage if provided for in the Contract Documents.
Appears in 1 contract
Samples: www.purchasing.ri.gov
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2., for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s right to payment that as the Owner or Architect may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect retainage if provided for in the Contract Documents.
Appears in 1 contract
Samples: 70.248.29.17:8085
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared for operations completed in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The Such application shall be notarized, if required, and supported by all such data substantiating the Contractor’s right to payment that as the Owner or Architect may require, such as copies of requisitions, and releases and waivers of liens requisitions from Subcontractors and material suppliers, and shall reflect reflecting retainage if provided for in the Contract Documents.
Appears in 1 contract
Samples: Form of Agreement
Applications for Payment. § 9.3.1 15.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect Owner an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.215.1, for completed portions of the Work. The application shall be notarized, if required, and ; be supported by all data substantiating the Contractor’s right to payment that the Owner or Architect require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and ; shall reflect retainage if provided for in the Contract Documents.
Appears in 1 contract
Samples: go.boarddocs.com
Applications for Payment. § 9.3.1 At Unless otherwise provided in the Contract Documents; at least ten twenty (20) days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared for operations completed in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The Such application shall be notarized, if required, notarized and supported by all such data substantiating the Contractor’s contractor's right to payment that including the most current Contractors Construction Schedule and/or copies of requisitions from Subcontractors and material providers as the Owner or Architect may require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and shall reflect reflecting retainage if provided for elsewhere in the Contract Documentsdocuments.
Appears in 1 contract
Samples: Architectural Services Agreement